2023.01.18_Addendum_02.pdf
PDF 64 KB Posted
- Attached to
- Lobby Security Upgrades Keating Federal Building Construction Project Federal contract opportunity
- Solicitation number
- 47PC0222R0025
About this file
This document provides details for the Lobby Security Upgrades project at the Kenneth B. Keating Federal Building and Courthouse in Rochester, NY. The project includes base bid work such as modifications to planters, security fences and gates, structural hardening of columns, provision of a temporary and permanent public entrance, installation of an airlock vestibule and doors, ensuring a protected path for public entry and egress, installation of a curtain wall system, concrete work, and modifications to mechanical, electrical, plumbing and fire protection systems. Additional work comprises constructing a security station, gun locker and storage room, modifying a stair vestibule, and providing turnstiles and signage. Questions for the solicitation are due by May 18th, 2022 with bids due on June 1st, 2022. The General Services Administration Public Buildings Service Region 2 is the contracting agency.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 2
January 18, 2023
DATE OF ISSUE:JANUARY 18, 2023
Project: Lobby Security Upgrades
Kenneth B. Keating U.S. Federal Office Building and Courthouse Rochester, NY
Owner: General Services Administration
A/E Contract No.: GS-07-P-16-UC-7008
Owner Point of Contact: Peter Smith
Prepared by: N.K. BHANDARI, Architecture & Engineering, P.C.
TO ALL BIDDERS:
The following additions, deletions, and/or changes or clarifications to the drawings, specifications, and bidding documents for this project, shall become and are hereby made part of the Contract Documents. They change the original documents only in the manner and to the extent stated. Each bidder shall acknowledge receipt of this ADDENDUM in the appropriate location on the bid proposal form.
This ADDENDUM consists of two (2) pages, including this page. All requirements of the original Specifications and Drawings and previous Addendum, if applicable, shall remain in force except as noted by this ADDENDUM.
THE PURPOSE OF THIS ADDENDUM IS TO CHANGE THE FOLLOWING ITEMS:
Drawing Revisions:
1. Sheet G-110:
a. Construction to restore the temporary public entrance back to the employee entrance.
b. Replace sheet G-110 dated 3/11/2022 with sheet G-110 date 01/18/2023.
2. Sheet AE600:
a. Doors 001 and 002 were added to the door schedule for the work to restore the temporary public entrance back to the employee entrance.
b. Replace sheet AE600 dated 3/11/2022 with sheet AE600 date 01/18/2023.
3. Sheet AE601:
a. Finishes revised for the temporary public entrance, and to restore the temporary public entrance back to the employee entrance.
b. Replace sheet AE601 dated 3/11/2022 with sheet AE601 date 01/18/2023.
Specifications Revisions:
1. Replace Specification Section 011000 dated 3/11/2022 with Section 011000 dated 01/18/2023.
a. Text added to the end of Section 011400-1.1F to read as follows:
i. “Contractor shall substantially complete work in the man public lobby such that the main public lobby is not out of commission, and the temporary public entrance is not utilized for a duration in excess of 6 months (183 calendar days), or as approved by the property manager.
Contractor shall remove the existing curtainwall and install the new curtainwall between the months of April and October, and as approved by GSA’s property manager. Contractor is not permitted to remove the existing curtainwall and install the new curtainwall outside of this timeframe.”
January 18, 2023
b. Revised Section 011000-1.2A to read as follows:
i. “Commencement: The Contractor shall commence performance of the Work within 1 day after the Contractor receives the Notice to Proceed (NTP). Contractor shall complete all contract work no later than four hundred and eighty-seven (487) calendar days (42-days for security clearances and submittals + 415-days for construction and contract closeout) after the Notice to Proceed is issued. Notice to Proceed will shortly follow award.”
c. Revised Section 011000-1.2B to read as follows:
i. Substantial Completion: The Contractor shall achieve Substantial Completion of the Work, as that term is defined in this Agreement, no later than four hundred and fifty-seven (457) calendar days from issuance of Notice to Proceed (NTP).
2. Add Section 092300 Gypsum Plastering to the Specification.
a. Minor plaster patching will be required for the temporary public entrance.
b. To restore the north employee entrance a CMU wall with plaster at the corridor side is required.
ATTACHMENTS:
1. Drawing G-110 dated 01/18/2022
2. Drawing AE600 dated 01/18/2022
3. Drawing AE601 dated 01/18/2022
4. Specification Section 011000 Summary dated 01/18/2022
5. Specification Section Gypsum Plastering dated 01/18/2022
END OF ADDENDUM NO. 2