This amendment modifies a solicitation for design-build services to replace the fire alarm and emergency communication system at two federal buildings in Concord, New Hampshire. The General Services Administration seeks to upgrade an aging Simplex fire alarm system that lacks key functions required by standards, including a voice evacuation system. The amendment provides additional attachments of floor plans and photos. It clarifies the existing elevator machine room walls are two-hour rated, and firefighter phones are in each stairwell landing. Specification details for detector locations and the need to coordinate with the existing alarm monitoring provider are also amended.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
INSTRUCTIONS (Back Page):
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contracting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Items 9, (Amendment of Solicitation Number - Dated), and 10, (Modification of Contract/Order Number - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries:
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document.
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 11/2016) BACK
(1) Accounting classification Net increase $
Description of Modification Continuation Page
2. The following documents are incorporated into this solicitation via amendment 0007
ATTACHMENT J: RUDMAN FLOOR PLANS
ATTACHMENT K CLEVELAND FLOOR PLANS
ATTACHMENT L PHOTOS OF INSIDE OF ELEVATOR BUTTONS
ATTACHMENT M - MAR - 2020
3. Statement of work is hereby amended as follows:
Page 15 Paragraph 4 amended as follows:
From:
The existing fire alarm system providing coverage in this building is a Simplex system. The fire alarm panel was replaced in 2014-2015 time-frame. GSA has determined that the current system lacks some of the key functions required by PBS P-100 as well as USMS Publication 64. The existing system also lacks a voice evacuation system.
To:
The existing fire alarm system providing coverage in this building is a Simplex system. The fire alarm panel was replaced in 2014-2015 time-frame. GSA has determined that the current system lacks some of the key functions required by PBS P-100 as well as USMS Publication 64. The existing system also lacks a voice evacuation system.
The elevator machine room walls are 2-hour rated CMU walls.
From:
Provide an updated communication system that permits an effective means to communicate among the floors individually. The existing firefighter phone locations can be utilized for the new firefighting phone system. .
To:
Provide an updated communication system that permits an effective means to communicate among the floors individually. The existing firefighter phone locations can be utilized for the new firefighting phone system. The firefighter phones/intercoms are located within each stairwell at each floor landing.
Page 19 Item 27 amended as follows
From:
Provide a smoke evacuation control panel adjacent to the new fire alarm control panel.
To:
Provide a smoke evacuation control panel adjacent to the new fire alarm control panel. The new smoke evacuation control panel provided as part of this work shall match the functions of the existing smoke evacuation control panel and shall be located at the Fire Command Center. Provide all required points from the fire alarm system or incorporate the smoke control panel into the fire alarm system.
4. Specification 283101 is hereby amended as follows:
Page 12 Item 13B amended as follows:
47PB0020R0027/0007
From:
A single dedicated telephone line installation and alarm monitoring account creation/transfer shall be coordinated with the Property Manager. The telephone line in existing buildings shall be provided to the location of the telephone terminal block closest to the Digital Alarm Communicator Transmitter by the Property Manager. The telephone line shall be connected to the telephone terminal block and then run in conduit and connected to the Digital Alarm Communicator Transmitter by the Contractor.
To:
A single dedicated telephone line installation and alarm monitoring account creation/transfer shall be coordinated with the Property Manager. The telephone line in existing buildings shall be provided to the location of the telephone terminal block closest to the Digital Alarm Communicator Transmitter by the Property Manager. The telephone line shall be connected to the telephone terminal block and then run in conduit and connected to the Digital Alarm Communicator Transmitter by the Contractor. GSA has an alarm monitoring account with the Mega-Center and the DB Contractor will need to coordinate with the Mega Center to ensure it complies with Mega Center requirements.
See Attachment M for the MAR Form that will need to be completed and submitted as part of this project.
Page 54 Item E.1 amended as follow:
From:
Locate detectors as shown on the drawings on a 4 inch (100 mm) mounting box. Detectors located on the ceiling shall be installed not less than 4 inches (100 mm) from a sidewall to the near edge. Those located on the wall shall have the top of the detector at least 4 inches (100 mm) and not more than 12 inches (300 mm) below the ceiling. In the case of solid joist construction, the detectors shall be mounted on the bottom of the joists. On smooth ceilings, detectors shall be installed not over 30 feet (9.1 meters) apart in any direction. Closer spacing shall be used when recommended by the detector manufacturer or required by NFPA 72. Install smoke detectors no closer than 5 feet (1.5 meters) from air handling supply outlets
TO:
Locate detectors as shown on the DB Contractor Design drawings on a 4 inch (100 mm) mounting box. Detectors located on the ceiling shall be installed not less than 4 inches (100 mm) from a sidewall to the near edge. Those located on the wall shall have the top of the detector at least 4 inches (100 mm) and not more than 12 inches (300
mm) below the ceiling. In the case of solid joist construction, the detectors shall be mounted on the bottom of the joists. On smooth ceilings, detectors shall be installed not over 30 feet (9.1 meters) apart in any direction. Closer spacing shall be used when recommended by the detector manufacturer or required by NFPA 72. Install smoke detectors no closer than 5 feet (1.5 meters) from air handling supply outlets.
----------------Nothing follows---------------------
47PB0020R0027/0007
| topmostSubform[0]: |
| Page2[0]: |
| TextField1[5]: |
| TextField1[2]: |
| TextField1[1]: |
| TextField1[4]: |
| TextField1[3]: |
| TextField1[0]: |
| Page1[0]: |
| Code[0]: 1PQB |
| Copies[0]: |
| CheckBox9[0]: 1 |
| Code[2]: 1PQB |
| NameandTitleOfficer[0]: Michele Valenza, Contracting Officer |
| Is[0]: Off |
| CheckBox10[0]: Off |
| NameandAddress[0]: |
| DateSigned[1]: |
| Pages[0]: 4 |
| AmendmentNo[0]: 0007 |
| Dated10B[0]: |
| ModificationNo[0]: |
| AdministeredBy[0]: Acquisition Management Division (1PQ) Contract Operations Branch (1PQB) GSA/PBS |
10 CAUSEWAY ST., RM 1100
BOSTON, MA 02222-1077 USA
| FacilityCode[0]: |
| CheckBox13B[0]: Off |
| CheckBox13D[0]: Off |
| ReqNumber[0]: EQ1PC-20-0013 |
| Dated9B[0]: 9/4/2020 |
| C13[0]: |
| Description[0]: 47PB0020R0027, Amendment 0007 is hereby amended as follows: |
1. Delete Amendment 0004 responses to the following questions # 38, 54 and 55 that read:
*Both building contain mixed use occupancies A (Assembly), B (Business), S (Storage), and I (Institutional)”...
[See Description of Modification Continuation Page]
| NotExtended[0]: 1 |
| Code[1]: |
| AmendmentNo[1]: 47PB0020R0027 |
| ContractIDCode[0]: |
| DateSigned[0]: |
| CheckBox11[0]: 1 |
| Page[0]: 1 |
| AccountingData[0]: |
| CopiesReturned[0]: |
| CheckBox13A[0]: Off |
| IsNot[0]: Off |
| EffectiveDate[0]: 10/22/2020 |
| A13[0]: |
| ProjectNo[0]: |
| CheckBox13C[0]: Off |
| Extended[0]: Off |
| D13[0]: |
| IssuedBy[0]: Acquisition Management Division (1PQ) Contract Operations Branch (1PQB) GSA/PBS |
10 CAUSEWAY ST., RM 1100
BOSTON, MA 02222-1077 USA
NameandTitleSigner[0]:
File details come from the government source that posted it. Updated .