This permit fees document pertains to the GSL Marina Water Line Replacement project (DFCM Project #22236510) managed by the Utah Division of Facilities and Construction Management in coordination with the Greater Salt Lake Municipal Services District, Salt Lake City, and the Utah Department of Transportation. The document outlines all contractor-applicable permit fees and associated costs for the project, which involves installation of a new water line serving Great Salt Lake State Park and Great Saltair, construction of an above-ground water storage tank, and a booster pump station. The contractor must utilize the listed fees with no markup in base bid pricing and is responsible for all permits and fees, including those not explicitly listed. Fees were updated as of April 14, 2026, and reflect charges across multiple jurisdictions.
The permit fee schedule itemizes costs across Greater Salt Lake Municipal Services District (excavation permits totaling $115,218.50, stormwater review at $2,424.94, and SWPPP-related fees), Salt Lake City Department of Public Utilities ($52,434.58 total including connection and plan review fees), Salt Lake City SWPPP and traffic control permits ($352 combined), and UDOT encroachment permits with variable costs dependent on project duration and inspection hours. The contractor will be reimbursed directly for all permit and fee costs without markup, ensuring transparent cost allocation. Total identifiable permit fees across all jurisdictions exceed $170,000, representing a significant component of the project's overall construction cost estimate of $10.2 million.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
GSL MARINA WATER LINE REPLACEMENT
(DFCM PROJECT # 22236510)
CONTRACTOR TO UTILIZE LISTED FEES BELOW
WITH NO MARKUP IN BASE BID PRICING
1 Excavation permits are applied for through the GSL MSD Engineering Department and require 48-hours of notice for inspection.
2 Stormwater review and floodplain development permits are applied for through the Planning and Development services within the GSL MSD. Only one set of fees will be charged for SWPPPs submitted to both unincorporated Salt Lake County and Magna City.
3 Contractor shall be responsible for all fees, including any not listed, and will be reimbursed directly for these costs. Fees were updated on April 14, 2026.
Greater Salt Lake Municipal Services District
Excavation Permit 1 – $115,218.50
• Unincorporated Salt Lake County Property:
o Asphalt and Dirt Removal – $112,118.50 (224,237 sq ft * $0.50 per sq ft)
• Magna City Property o Asphalt Removal – $3,100.00 (6,200 sq ft * $0.50 per sq ft)
• Stormwater Review – per acre fee - $2,424.94 (15.28 acres * $158.70 per acre)
SWPPP Review 2 – base fee - $200
SWPPP Per Acre Review – $458.40 (15.28 acres * $30 per acre)
Floodplain Development Permit - $75
SWPPP Oversite Inspection – $60 per month until project is complete
Salt Lake City
• SLC Department of Public Utilities Fees Total - $52,434.58 o 4-Inch Connection Fee – $43,622.22 o PU Plan Review Fee - $2,124.00 o Water Inspection Fee - $110.00 o Water Resource Fee - $6,578.36
• Salt Lake City SWPPP Permit o Application and Initial Inspection Fee - $132 o Discharge into City Storm Water Sewer System / Notice of Intent Fee - $132 o Discharge into City Storm Water Sewer System / Preconstruction Fee - $44 o Discharge into City Storm Water Sewer System Reinspection Fee - $44
• Salt Lake City Traffic Control Permit - $40
UDOT
UDOT Encroachment Permit o Long Impact (up to 4 weeks) - $900 per application o Inspection - $110 per hour o Overtime Inspection - $150 per hour