This document contains responses from the government to contractor questions regarding Solicitation Number 36C78623B0033 for the Dayton National Cemetery PIC/Admin Building, road repairs, and replacement of Committal Shelter B. Key details include that the project involves renovating an existing administration building and constructing a new honor guard building and committal shelter. The government anticipates awarding the contract within 90 days of the bid opening date and expects phase one work to begin in the spring of 2024. Responses clarify specifications around roofing materials, door schedules, drainage systems, and finish materials for the various buildings. No utilities are available at the designated construction staging area.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation: 36C78623B0033 Project: 810CM3030 Dayton PIC-Admin_Roads_Shelter Contractor Questions & GOV Responses
1. The Fire Alarm drawing states that the new panel shall monitor and read the existing panels. What is the existing system and model? Would Siemens be considered a match?
1. GOV Response: Existing Honeywell FA panel and it must be compatible with the existing system.
2. The project plans and the bid schedule do not match for what is being proposed for pricing. Ie..the demolition and reconstruction of Committal Shelter B is called out in CLIN 0001 on the bid schedule but the reconstruction of Committal Shelter B is called out as CLIN 0003 on the project plans.
Please clarify how we are to price this.
2. GOV Response: See Amendment 0001 and its attachment for this solicitation. The A/E has provided a Memorandum identifying the discrepancy and providing clarification.
3. Can the government provide an anticipated award date for this project? Based on the current bid date and the 90 day review period, it would be very beneficial to all contractors to know if we need to anticipate earthwork/clearing to happen this winter or if we will need to push all phase 1 work out to spring of 2024 to avoid freeze thaw with the proposed building foundations.?
3. GOV Response: The Government anticipates awarding this project within 90 days of bid opening. Phase I work shall be priced to begin in the spring of 2024.
4. The reflective ceiling plans are the only plan sheets that appear to call out proposed sprinkler systems within the proposed new buildings and the existing admin renovation. However, the legend symbol for the sprinklers appears to be contradictory. Can we get revised plan sheets to accurately reflect what is proposed for the sprinkler system?
4. GOV Response: The new building will not be sprinklered.
5. The existing administration building renovation plans appear to call out proposed sprinkler system, but during the site visit it didn’t appear that there is any existing sprinkler system within the existing building.
| a. | Can the government confirm the presence of existing sprinkler system within the existing administration building? |
| b. | Also, can the government provide the location of the tie-in of the new sprinkler system with the existing in the existing administration building? |
5. GOV Response: a. building is not currently sprinklered, b. the new building will not be sprinklered.
6. There are no layouts for the sprinkler system in the proposed new buildings and admin extension other than the apparent locations of the sprinkler heads. Can the government provide the proposed layout, pipe type, size, details, etc.. for what is intended to be installed? Also, there doesn’t appear to be any call outs or locations for the standpipes/sprinkler system supply lines. Can the government provide clarification for this?
6. GOV Response: The new building will not be sprinklered.
7. Drawing sheet CU101 calls out water lines to connect to the new admin building and honor guard building but does not indicate size or type of pipe. Please clarify what size and type is the service line to the proposed buildings?
7. GOV Response: Admin building water service line is 2.5" copper type K. Honor Guard building water service line is 2" copper type K. See profiles on sheet CU231.
8. Can you tell me if this project will be tax exempt?
8. GOV Response: The Government will not provide any tax exempt forms. All taxes should be included in the bid.
9. Committal Shelter B Architectural Drawings show wood trusses, ¾” plywood decking and asphalt shingles, Structural Drawings show cold formed metal trusses and metal decking and no type of roofing material indicated. There is no specification for the asphalt shingles. New wall sections would be needed if we are to use metal trusses, metal decking and metal roofing. Please clarify which system to use.
9. GOV Response: See attached new Specification for Asphalt shingles. The roof structure is to be cold formed metal trusses.
10. Door , frame and hardware types need to be shown for doors at the Committal Shelter B.
10. GOV Response: See attached revised sheet A-101R for updated door schedule.
11. Need specification for Engineered Wood Ceiling System shown on Committal Shelter B drawings.
11. GOV Response: The ceiling/soffit system at the Committal Shelter will be metal panels.
12. Sprinkler heads are noted on drawing sheets A-110, A-111, A-112 in two ways, solid black dot and solid black dot with circle. There is no source system to these heads. Drawing sheet CU101, note 8, identifies a tap to existing fire hydrant to new Admin building but no riser.
a. Is a sprinkler system to be installed in this facility?
b. What is the specification for the water line to the new admin facility? What is the termination?
c. What is the source for the noted sprinkler heads?
12. GOV Response: The new building will not be sprinklered.
13. On drawing sheet A-201, the elevations of the Admin Bldg show the downspouts draining to splash pads. On drawing sheet CU-101, the locations of the downspouts indicate that the downspouts route to the PVC drainage system. Which method is correct?
13. GOV Response: Downspouts shall route to PVC drainage system as shown on sheet CU101. Splash pads have been removed from drawing A-201R.
14. 2. On drawing sheet CU-101, the PVC drainage system for the Admin Bldg shows a symbol at the connection bends. Are these symbols a cleanout or just a fitting? If it is a cleanout, can we have a detail for this?
14. GOV Response: These are cleanouts and Key Notes added on Sheet CU101R. Detail added to Sheet CU562R.
15. Drawing A101 – Door Schedule for Shelter B does not show any details for the door S1:
a. Need Frame type – HM?
b. Need Door type – HM?
c. Need Hardware type -?
15. GOV Response: See attached revised sheet A-101R for updated door schedule.
16. During the site visit, it was noted that there is a considerable amount of materials stored around the maintenance shed where the pavement and option work is to be completed. Can the government confirm that this material will be moved/relocated prior to construction of this contract?
16. GOV Response: Material relocations will need to be coordinate with the cemetery staff. Contractor to provide date when the area need to be cleared.
17. Section 02 21 00 appears to be describing an Alta Survey for the entire cemetery grounds. Can the government confirm that this is what is being required? If this the case, performing an ALTA survey on the entire grounds is a long process to complete, even if it begins during the initial construction start. Can the government indicate that additional time to the contract will be provided to complete this or at least consider the project substantially complete prior to the completion of the Site Survey?
17. GOV Response: This is standard NCA Spec. Unless otherwise desired by NCA, I believe the survey would only be for the benefit of the contractor and an ALTA is not required.
18. Can the government provide information on the availability of utilities at the Construction Staging area?
| a. | Water |
| b. | Sewer |
| c. | Electric |
18. GOV Response: No utilities are available.
19. I need clarification on a product. WOC-1 – There is walk-off carpet in the material legend, but the is no WOC-1 on the finish schedule. All of the entries/vestibules show CPT-1 for their finishes. Cpt-1 and WOC-1 are very different types of carpet tile.?
19. GOV Response: Finish schedule now includes WOC-1, see revised sheet I-001R.
20. Sheet I-102 Mechanical Room 115, there doesn’t appear to be any Finishes described for this room. Please clarify.
20. GOV Response: This is an existing space, no new finishes needed.
21. WOC-1 is called out in the specifications but does not appear to be called out in the project plans. Can the govt. please clarify where the Walk Off Carpet is to be installed?
21. GOV Response: Finish schedule now includes WOC-1, see revised sheet I-001R.
22. Toilet/Shower 124 calls for EP-1 on the Finish Schedule but elevations are showing PT-2 wall tile in several locations ... Please clarify which is correct.
22. GOV Response: Elevations on revised sheet I-432R are correct.
23. Can the government please clarify where the breakpoint between Lobby 101 CPT & Reception 101 LVT is?
23. GOV Response: Transition added with Key Note, see revised sheet I-101R.
24. PTB is called out in several areas on the Finish Schedule. Many of these areas are full height wall tile and details show those as a metal cove piece .... Please clarify.
a. Where base is required, where there is no wall tile, are we to figure the wall tile cut down to 4x24 with a metal cove & cap or what is expected in those areas? Please clarify.
24. GOV Response: Specified tile line includes a bullnose trim piece 3”x12”, Portfolio, Dove grey P43C9. PTB-1 is called out in Admin Building detached restrooms 122 and 123 and keynoted in elevations on sheet I-433.