Amendment 6 RFI Answers (SAM post).pdf
PDF 78 KB Posted
- Attached to
- Y1FE--36C78622R0020 | Georgia NC; Expansion Ph 2 Construction 922CM3006 (VA-21-00103342)
- Solicitation number
- 36C78622R0020
About this file
This document contains answers to questions regarding an amendment to a solicitation for the construction of Phase II of the expansion of the Georgia National Cemetery.
The solicitation is for the construction of approximately 6,624 pre-placed double-depth crypts in 3'x8' plots, 362 oversized preplaced double-depth crypts in 5'x10' plots, 294 traditional full casket gravesites in 5'x10' plots, 6,944 in-ground cremation sites in 4'x4' plots, and 7,300 columbarium niches. Associated site and infrastructure work is also required. The solicitation number is 36C78622R0020 and was issued by the Department of Veterans Affairs National Cemetery Administration for work at the Georgia National Cemetery located at 25 Mount Carmel Church Ln, Canton, GA 30114.
The amendment answers clarify that OSHA 30 training is only required for supervisors and safety managers, while other trades must have OSHA 10 training. Additionally, the preliminary BMP plan provided can be used as the baseline for costs but will be reviewed, validated and any additional costs negotiated.
View the file
Other files
Show all 42
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C78622R0020 Georgia National Cemetery 09/29/2022 Amendment #6
Question:
1.1.G.1 of 01 00 02 General Requirements calls for all employees of general contractor and subs to have successfully completed OSHA 30 HR training. In the past the OSHA 30 has been a requirement for supervisors and general trade labor has completed OSHA 10 HR training. Please verify that all employees on jobsite are to have OSHA 30 HR training.
OSHA 30 HR Training is only a requirement for supervisors and safety managers. All other trade labor must have OSHA 10 HR training.
Question:
Sheet GC001 (Right Side of Drawing) Includes:
The note indicates that this is only a preliminary plan and that costs for deficiencies in this plan will be on the contractor to cover. Being this is not a design build project, will the VA allow this preliminary plan to be the baseline for BMPs and allow for reimbursement for any additional BMPs that our Level II Designer deems necessary to meet Georgia requirements?
We will allow the preliminary plan to be the baseline for BMPs and review/validate/negotiate any costs for additional BMP costs