ATTACHMENT U - JC New Bed Tower IOTA_Key Planning Milestones_10_28_2026.pdf

PDF 84 KB Posted

Attached to
St. Louis JC Bed Tower IOTA RFQ
Solicitation number
36C77627Q0011
Issued by

About this file

This document is a project milestone and schedule summary for the JC New Bed Tower IOTA construction project managed by CFM and USACE. The project encompasses multiple construction phases with staggered timelines: CUP, Motor Pool, and Support Building construction from FY27–FY33, and Bed Tower, OTP (Outpatient), and East Site construction from FY29–FY34. Design activities commence with SD1 review and SD2 design kickoff in April 2027 (FY27), followed by design development in FY28 and construction documents in FY28–FY29. Critical medical equipment review and lead time acquisition will occur in FY32–FY34, with installation scheduled for FY34–FY35. The document identifies specific IOTA responsibilities including reviewing and updating furniture and equipment layouts during design phases, managing equipment details and layout updates, supporting design reviews, and coordinating equipment delivery and building setup around construction progress.

The proposed Basis of Decision (BOD) dates are February 2033 (FY33) for CUP, Motor Pool, and Support Building, and October 2034 (FY35) for Bed Tower and OTP, with final timing to be established by the USACE Area Office following project risk review. All estimated dates are subject to change as the project progresses, and CFM/USACE must confirm these estimates. The source document is referenced as 261001 - CFM CR IMS Schedules St. Louis, with fiscal year defined as October–September.

View the file

Other files

File Type Posted
ATTACHMENT L - Procurement Package Template and 6500 8.20.2026.pdf PDF
ATTACHMENT O - PDAT Summary - St. Louis.pdf PDF
ATTACHMENT K - Integrated Move Plan Template.xlsx XLSX spreadsheet
ATTACHMENT I - Room Contents Acq Plan Template 9.21.2023.xlsx XLSX spreadsheet
ATTACHMENT G - Change Management Log Template.xlsx XLSX spreadsheet
ATTACHMENT B - Task Order 1 Terms and Conditions - St. Louis.pdf PDF
ATTACHMENT P - VSC Security Package 12.8.2025.pdf PDF
ATTACHMENT T - ProjectRoomContents_VA STLHCS-JC SD1 INPATIENT TOW.xlsx XLSX spreadsheet
ATTACHMENT A - IOTA IDIQ PWS - St. Louis 10.20.2026.pdf PDF
ATTACHMENT A1 - IOTA TO1 PWS - St. Louis 10.26.2026.pdf PDF
ATTACHMENT C - Travel Authorization Request.pdf PDF
ATTACHMENT J - Proposed FTE Report.xlsx XLSX spreadsheet
ATTACHMENT F - Risk Management Plan and Register Template.xlsx XLSX spreadsheet
ATTACHMENT S - ProjectRoomContents_VA STLHCS-JC SD1 ENGINEERING.xlsx XLSX spreadsheet
ATTACHMENT D - Contract Staff Roster.pdf PDF
ATTACHMENT R - Design Submittal SD1 Room Contents.pdf PDF
ATTACHMENT V - Pricing Worksheet - St. Louis New Bed Tower IOTA.xlsx XLSX spreadsheet
ATTACHMENT H - Equipment Inventory_ReUse and Disposal Plan Template.xlsx XLSX spreadsheet
ATTACHMENT E - WBS Template.pdf PDF
ATTACHMENT N - QASP - St. Louis.docx DOCX document
ATTACHMENT M - Furniture IDIQ Templates.pdf PDF
ATTACHMENT Q - Wage Determination.pdf PDF
RFQ 36C77627Q0011 Solicitation St. Louis IDIQ and TO1 - PDF COPY.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JC New Bed Tower IOTA Project milestones and estimated dates

Project stage Estimated timing What this means for IOTA

SD1 review and SD2 design

Design kickoff: April 2027

SD2: FY27

Review existing plans and update furniture and equipment layouts during design.

Design development FY28 Equipment details and layout updates support the design submissions.

Construction documents FY28–FY29 Support design reviews and track equipment and layout comments.

CUP, Motor Pool, Support

Bldg Construction: FY27-FY33

Plan equipment delivery and building setup around construction progress.

Bed Tower, OTP and East

Site Construction: FY29–FY34

Plan equipment delivery and building setup around construction progress.

Critical medical equipment Review / lead time: FY32–FY34

Installation: FY34–FY35

The confirmed overall schedule will add more detailed equipment dates.

CUP, Motor Pool, Support

Bldg Proposed BOD February 2033 (FY33)

The USACE Area Office will set the timing after reviewing project risks.

Bed Tower, OTP Proposed

BOD

October 2034 (FY35)

The USACE Area Office will set the timing after reviewing project risks.

Source: 261001 - CFM CR IMS Schedules St. Louis. FY means fiscal year (October–September). CFM/USACE must confirm these estimates. All dates are subject to change as project progresses.