ATTACHMENT U - JC New Bed Tower IOTA_Key Planning Milestones_10_28_2026.pdf
PDF 84 KB Posted
- Attached to
- St. Louis JC Bed Tower IOTA RFQ
- Solicitation number
- 36C77627Q0011
About this file
This document is a project milestone and schedule summary for the JC New Bed Tower IOTA construction project managed by CFM and USACE. The project encompasses multiple construction phases with staggered timelines: CUP, Motor Pool, and Support Building construction from FY27–FY33, and Bed Tower, OTP (Outpatient), and East Site construction from FY29–FY34. Design activities commence with SD1 review and SD2 design kickoff in April 2027 (FY27), followed by design development in FY28 and construction documents in FY28–FY29. Critical medical equipment review and lead time acquisition will occur in FY32–FY34, with installation scheduled for FY34–FY35. The document identifies specific IOTA responsibilities including reviewing and updating furniture and equipment layouts during design phases, managing equipment details and layout updates, supporting design reviews, and coordinating equipment delivery and building setup around construction progress.
The proposed Basis of Decision (BOD) dates are February 2033 (FY33) for CUP, Motor Pool, and Support Building, and October 2034 (FY35) for Bed Tower and OTP, with final timing to be established by the USACE Area Office following project risk review. All estimated dates are subject to change as the project progresses, and CFM/USACE must confirm these estimates. The source document is referenced as 261001 - CFM CR IMS Schedules St. Louis, with fiscal year defined as October–September.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JC New Bed Tower IOTA Project milestones and estimated dates
Project stage Estimated timing What this means for IOTA
SD1 review and SD2 design
Design kickoff: April 2027
SD2: FY27
Review existing plans and update furniture and equipment layouts during design.
Design development FY28 Equipment details and layout updates support the design submissions.
Construction documents FY28–FY29 Support design reviews and track equipment and layout comments.
CUP, Motor Pool, Support
Bldg Construction: FY27-FY33
Plan equipment delivery and building setup around construction progress.
Bed Tower, OTP and East
Site Construction: FY29–FY34
Plan equipment delivery and building setup around construction progress.
Critical medical equipment Review / lead time: FY32–FY34
Installation: FY34–FY35
The confirmed overall schedule will add more detailed equipment dates.
CUP, Motor Pool, Support
Bldg Proposed BOD February 2033 (FY33)
The USACE Area Office will set the timing after reviewing project risks.
Bed Tower, OTP Proposed
BOD
October 2034 (FY35)
The USACE Area Office will set the timing after reviewing project risks.
Source: 261001 - CFM CR IMS Schedules St. Louis. FY means fiscal year (October–September). CFM/USACE must confirm these estimates. All dates are subject to change as project progresses.
Slide 1