ATTACHMENT 2 - SPEC DIV 21-23.pdf
PDF 22 MB Posted
- Solicitation number
- 36C77626B0009
About this file
This file contains comprehensive technical specifications for Divisions 21-23 and related sections of the EHRM Infrastructure Upgrades project at Syracuse VA Medical Center. The specifications cover fire suppression systems (wet-pipe sprinklers and clean agent suppression), plumbing systems (domestic water distribution, sanitary/storm drainage, water pumps), and HVAC systems (common work results, motors, noise/vibration control, testing/balancing, insulation, commissioning, controls, hydronic piping, pumps, steam/condensate piping, and refrigerant piping).
Key technical requirements include: fire suppression systems must comply with NFPA standards and be designed by NICET-certified professionals; domestic water systems require copper or stainless steel piping with NSF-certified materials and lead-free components; sanitary piping uses cast iron soil pipe with hub-and-spigot or hubless connections; HVAC systems must employ BACnet-compliant direct digital controls with native networking, premium efficiency motors, vibration isolation, and comprehensive commissioning with factory-authorized training; hydronic piping uses copper tubing or steel with welded/flanged joints and requires flushing and water treatment; steam/condensate piping uses Schedule 40 seamless steel with brazed or welded joints and mandatory non-destructive examination of 50 percent of initial welds plus 10 percent of subsequent welds; refrigerant piping uses ASTM B280 copper tubing with brazed connections per AWS standards. All systems require seismic restraint per Section 13 05 41, comprehensive as-built documentation with CAD files, operations and maintenance manuals, factory certification, and commissioning documentation coordinated with a VA-appointed Commissioning Agent. Shop drawings must be submitted for approval prior to material procurement, with specific quality assurance requirements including manufacturer certifications, 5-year spare parts availability, and qualified installation personnel with documented experience on comparable projects.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
21 OCTOBER 2025
EHRM
INFRASTRUCTURE
UPGRADES
PROJECT #: 528A7-22-700
SYRACUSE VA MEDICAL CENTER
SYRACUSE, NY
SPECIFICATIONS
Divisions 21-23
100% SUBMITTAL
CONSTRUCTION DOCUMENTS 2
EHRM INFRASTRUCTURE UPGRADES PROJECT #: 528A7-22-700
SYRACUSE VA MEDICAL CENTER – SYRACUSE, NY PUB. DATE: 07-27-2023
TABLE OF CONTENTS 00 01 10 - 01
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO. DIVISION AND SECTION TITLES DATE
DIVISION 00 - SPECIAL SECTIONS
00 01 07 Seals Page
00 01 10 Table of Contents 07-23
00 01 15 List of Drawing Sheets 05-18
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21
01 33 23 Shop Drawings, Product Data & Samples 22-23
01 35 26 Safety Requirements 05-24
01 42 19 Reference Standards 11-20
01 45 00 Quality Control 02-22
01 57 19 Temporary Environmental Controls 01-21
01 74 19 Construction Waste Management 04-22
01 81 13 Sustainable Construction Requirements 10-17
01 91 00 General Commissioning Requirements 04-22
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 11-21
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-21
05 31 00 Steel Decking 11-21
05 36 00 Composite Metal Decking 11-21
05 40 00 Cold-Formed Metal Framing 11-21
05 50 00 Metal Fabrications 08-18
05 51 00 Metal Stairs 01-21
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 10-17
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 05-18
07 21 19 Foamed-In-Place Insulation 05-18
07 22 00 Roof and Deck Insulation 05-18
TABLE OF CONTENTS 00 01 10 - 02
07 27 27 Fluid-Applied Membrane Air Barrier, Vapor Retarding 05-18
07 40 00 Roofing and Siding Panels 01-21
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 05-18
07 60 00 Flashing and Sheet Metal 05-18
07 71 00 Roof Specialties 05-18
07 81 00 Applied Fireproofing 05-18
07 84 00 Firestopping 05-18
07 92 00 Joint Sealants 05-18
07 95 13 Expansion Joint Cover Assemblies 01-21
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 05-18
08 14 00 Interior Wood Doors 05-18
08 71 00 Door Hardware 05-18
08 90 00 Louvers and Vents 01-21
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 05-18
09 06 00 Schedule for Finishes 05-18
09 22 16 Non-Structural Metal Framing 05-18
09 29 00 Gypsum Board 05-18
09 51 00 Acoustical Ceilings 05-18
09 65 13 Resilient Base and Accessories 05-18
09 65 19 Resilient Tile Flooring 05-18
09 66 00 Static Dissipative Sealer for Concrete Substrates 05-18
09 91 00 Painting 05-18
DIVISION 10 - SPECIALTIES
10 14 00 Signage 05-18
10 26 00 Wall and Door Protection 05-18
10 44 13 Fire Extinguisher Cabinets 05-18
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural Components 05-18
DIVISION 21- FIRE SUPPRESSION
21 08 00 Commissioning of Fire Suppression System 11-16
21 13 13 Wet-Pipe Sprinkler Systems 06-15
21 22 00 Clean Agent Fire Suppression Systems 05-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 09-20
22 05 23 General-Duty Valves for Plumbing Piping 11-22
TABLE OF CONTENTS 00 01 10 - 03
22 05 33 Heat Tracing for Plumbing Piping 09-20
22 07 11 Plumbing Insulation 09-19
22 08 00 Commissioning of Plumbing Systems 11-16
22 11 00 Facility Water Distribution 05-21
22 11 23 Domestic Water Pumps 09-15
22 13 00 Facility Sanitary and Vent Piping 09-20
22 14 00 Facility Storm Drainage 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23
23 05 12 General Motor Requirements for HVAC Equipment 03-23
23 05 41 Noise and Vibration Control for HVAC Piping and Equipment 03-23
23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23
23 07 11 HVAC Insulation 02-20
23 08 00 Commissioning of HVAC Systems 03-23
23 09 23 Direct-Digital Control System for HVAC 03-23
23 21 13 Hydronic Piping 05-18
23 21 23 Hydronic Pumps 03-23
23 22 13 Steam and Condensate Heating Piping 02-20
23 23 00 Refrigerant Piping 03-24
23 31 00 HVAC Ducts and Casings 03-23
23 34 00 HVAC Fans 03-23
23 37 00 Air Outlets and Inlets 03-23
23 40 00 HVAC Air Cleaning Devices 03-20
23 72 00 Air-to-Air Energy Recovery Equipment 03-23
23 73 00 Indoor Central-Station Air-Handling Units 03-23
23 81 23 Computer-Room Air-Conditioners 03-24
23 81 43 Air-Source Unitary Heat Pumps 03-20
23 82 00 Convection Heating and Cooling Units 03-20
23 82 16 Air Coils 03-23
23 84 00 Humidity Control Equipment 03-20
DIVISION 25 – INTEGRATED AUTOMATION
25 10 10 Advanced Utility Metering System 12-22
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 12-22
26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-20
26 05 26 Grounding and Bonding for Electrical Systems 11-20
26 05 33 Raceway and Boxes for Electrical Systems 11-20
26 05 73 Overcurrent Protective Device Coordination Study 11-20
26 08 00 Commissioning of Electrical Systems 11-16
26 09 23 Lighting Controls 11-22
TABLE OF CONTENTS 00 01 10 - 04
26 19 11 Motor Controllers 11-22
26 22 00 Low-Voltage Transformers 11-22
26 24 16 Panelboards 11-21
26 25 11 Busways 11-22
26 27 26 Wiring Devices 11-20
26 29 11 Motor Controllers 11-22
26 29 21 Enclosed Switches and Circuit Breakers 11-22
26 33 53 Static Uninterruptible Power Supply 11-22
26 36 23 Automatic Transfer Switches 11-22
26 41 00 Facility Lightning Protection 11-22
26 43 13 Surge Protective Devices 01-23
26 51 00 Interior Lighting 11-22
DIVISION 27 – COMMUNICATIONS
27 05 26 Grounding and Bonding for Communications Systems 12-22
27 05 33i Raceways and Boxes for Communications Systems 12-22
27 05 36i Cable Tray For Communications System 12-22
27 05 53i Identification For Communications System 12-22
27 10 00i Structured Cabling 12-22
27 11 16i Communications Cabinets, Racks, Frames, and Enclosures 12-22
27 11 19i Communications Terminal Blocks And Patch Panels 12-22
27 11 26 Communications Rack Mounted Power Protection And Power Strips 12-22
27 13 13 .13i Communications Copper Cable Splicing And Terminations 12-22
27 13 13 Communications Copper Backbone Cabling 12-22
27 13 23.13i Communications Optical Fiber Splicing And Terminations 12-22
27 13 23 Communications Optical Fiber Backbone Cabling 12-22
27 15 13i Communications Copper Horizontal Cabling 12-22
27 16 19i Communications Patch Cords, Station Cord, And Cross Connect wire 12-22
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and Security 11-21
28 05 26 Grounding and Bonding for Electronic Safety and Security 09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and Security 09-11
28 08 00 Commissioning of Electronic Safety and Security Systems 11-16
28 13 00 Physical Access Control System 10-11
28 13 53 Security Access Detection 09-11
28 23 00 Video Surveillance 09-11
28 31 00 Fire Detection and Alarm 09-11
SYRACUSE VA MEDICAL CENTER – SYRACUSE, NY PUB. DATE: 11-01-16
COMMISSIONING OF FIRE SUPPRESSION SYSTEMS 21 08 00 -01
SECTION 21 08 00
COMMISSIONING OF FIRE SUPPRESSION SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. The requirements of this Section apply to all sections of Division 21.
B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING
REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A Commissioning Agent
(CxA) appointed by the VA will manage the commissioning process.
1.2 RELATED WORK
A. Section 01 00 00 GENERAL REQUIREMENTS.
B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.
C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
1.3 SUMMARY
A. This Section includes requirements for commissioning the Fire Suppression systems, subsystems and equipment. This Section supplements the general requirements specified in Section 01 91
00 General Commissioning Requirements.
B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.
1.4 DEFINITIONS
A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.
1.5 COMMISSIONED SYSTEMS
A. Commissioning of a system or systems specified in Division 21 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00 and of
Division 21, is required in cooperation with the VA and the Commissioning Agent.
B. The Fire Suppression systems commissioning will include the systems listed in Section 01 91 00
General Commissioning Requirements
COMMISSIONING OF FIRE SUPPRESSION SYSTEMS 21 08 00 -02
1.6 SUBMITTALS
A. The commissioning process requires review of selected Submittals. The Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to Section 01
33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.
B. The commissioning process requires Submittal review simultaneously with engineering review.
Specific submittal requirements related to the commissioning process are specified in Section 01
91 00 GENERAL COMMISSIONING REQUIREMENTS.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 CONSTRUCTION INSPECTIONS
A. Commissioning of the building fire suppression systems will require inspection of individual elements of the fire suppression construction throughout the construction period. The
Contractor shall coordinate with the Commissioning Agent in accordance with Section 01 91 00 and the Commissioning plan to schedule inspections as required to support the Commissioning
Process.
3.2 PRE-FUNCTIONAL CHECKLISTS
A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance
Testing. The Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The
Commissioning Agent may spot check a sample of completed checklists. If the Commissioning
Agent determines that the information provided on the checklist is not accurate, the
Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission. If the Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the Commissioning Agent will select a broader sample of checklists for review. If the Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the type of equipment will be returned to the Contractor for correction and resubmission. Refer to
SECTION 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for submittal requirements for
Pre-Functional Checklists, Equipment Startup Reports, and other commissioning documents.
COMMISSIONING OF FIRE SUPPRESSION SYSTEMS 21 08 00 -03
3.3 CONTRACTORS TESTS
A. Contractor tests as required by other sections of Division 21 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected Contractor tests at the sole discretion of the Commissioning Agent. Contractor tests shall be completed prior to scheduling Systems
Functional Performance Testing.
3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING
A. The Commissioning Process includes Systems Functional Performance Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The
Commissioning Agent will prepare detailed Systems Functional Performance Test procedures for review and approval by the COR. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed.
See Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS, for additional details.
3.5 TRAINING OF VA PERSONNEL
A. Training of the VA operation and maintenance personnel is required in cooperation with the
COR and Commissioning Agent. Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of Section 01 91 00. The instruction shall be scheduled in coordination with the COR after submission and approval of formal training plans.
Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS and Division 21 Sections for additional Contractor training requirements.
----- END -----
SYRACUSE VA MEDICAL CENTER – SYRACUSE, NY PUB. DATE: 06-01-15
WET-PIPE SPRINKLER SYSTEMS 21 13 13 - 01
SECTION 21 13 13
WET-PIPE SPRINKLER SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Design, installation and testing shall be in accordance with
a. NFPA 13.
B. Modification of the existing sprinkler system as indicated on the drawings and as further required by these specifications.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Section 07 84 00, FIRESTOPPING.
D. Section 09 91 00, PAINTING.
E. Section 22 05 23, GENERAL-DUTY VALVES FOR PLUMBING PIPING.
F. Section 28 31 00, FIRE DETECTION AND ALARM.
1.3 DESIGN CRITERIA
A. Design Basis Information: Provide design, materials, equipment, installation, inspection, and testing of the automatic sprinkler system in accordance with the requirements of NFPA 13.
1. Perform hydraulic calculations in accordance with NFPA 13 utilizing the Area/Density method. Do not restrict design area reductions permitted for using quick response sprinklers throughout by the required use of standard response sprinklers in the areas identified in this section.
2. Sprinkler Protection: Sprinkler hazard classifications shall be in accordance with NFPA 13.
The hazard classification examples of uses and conditions identified in the Annex of NFPA 13 shall be mandatory for areas not listed below. Request clarification from the Government for any hazard classification not identified. To determining spacing and sizing, apply the following coverage classifications:
a. Light Hazard Occupancies: Telecommunication Rooms and Data Center’s..
b. Ordinary Hazard Group 1 Occupancies: Laboratories, Mechanical Equipment Rooms, Transformer Rooms, Electrical Switchgear Rooms, Electric Closets, and Repair Shops.
3. Hydraulic Calculations: Calculated demand including hose stream requirements shall fall no less than 10 percent below the available water supply curve.
WET-PIPE SPRINKLER SYSTEMS 21 13 13 - 02
5. Zoning:
a. For each sprinkler zone provide a control valve, flow switch, and a test and drain assembly with pressure gauge. For buildings greater than two stories, provide a check valve at each control valve.
b. Sprinkler zones shall conform to the smoke barrier zones shown on the drawings.
6. Provide seismic protection in accordance with NFPA 13. Contractor shall submit load calculations for sizing of sway bracing for systems that are required to be protected against damage from earthquakes.
1.4 SUBMITTALS
A. Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV
Sprinkler Technician or stamped by a Registered Professional Engineer licensed in the field of
Fire Protection Engineering. As the Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in Paragraphs
1.4(A)1 through 1.4(A)5 electronically in pdf format on a compact disc or as directed by the COR.
Submittals shall include, but not be limited to, the following:
1. Qualifications:
a. Provide a copy of the installing contractors fire sprinkler and state contractor’s license.
b. Provide a copy of the NICET certification for the NICET Level III or Level IV Sprinkler
Technician who prepared and signed the detailed working drawings unless the drawings are stamped by a Registered Professional Engineer licensed in the field of Fire
Protection Engineering.
c. Provide documentation showing that the installer has been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working drawings conforming to the Plans and Calculations chapter of NFPA 13. Drawings shall include graphical scales
WET-PIPE SPRINKLER SYSTEMS 21 13 13 - 03
that allow the user to determine lengths when the drawings are reduced in size. Include a plan showing the piping to the water supply test location.
3. Manufacturer’s Data Sheets: Provide data sheets for all materials and equipment proposed for use on the system. Include listing information and installation instructions in data sheets.
Where data sheets describe items in addition to those proposed to be used for the system, clearly identify the proposed items on the sheet.
4. Calculation Sheets:
a. Submit hydraulic calculation sheets in tabular form conforming to the requirements and recommendations of the Plans and Calculations chapter of NFPA 13.
b. Submit calculations of loads for sizing of sway bracing in accordance with NFPA 13.5.
Valve Charts: Provide a valve chart that identifies the location of each control valve.
Coordinate nomenclature and identification of control valves with COR. Where existing nomenclature does not exist, the chart shall include no less than the following: Tag ID
No., Valve Size, Service (control valve, main drain, aux. drain, inspectors test valve, etc.), and Location.
6. Final Document Submittals: Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in Section 01 33 23, SHOP DRAWINGS, PRODUCT
DATA, AND SAMPLES. In addition, submittals shall include, but not be limited to, the following:
a. A complete set of as-built drawings showing the installed system with the specific interconnections between the system switches and the fire alarm equipment. Provide a complete set in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the COR.
1) One full size (or size as directed by the COR) printed copy.
2) One complete set in electronic pdf format.
3) One complete set in AutoCAD format or a format as directed by the COR.
b. Material and Testing Certificate: Upon completion of the sprinkler system installation or any partial section of the system, including testing and flushing, provide a copy of a completed Material and Testing Certificate as indicated in NFPA 13. Certificates shall be provided to document all parts of the installation.
c. Operations and Maintenance Manuals that include step-by-step procedures required for system startup, operation, shutdown, and routine maintenance and testing. The
WET-PIPE SPRINKLER SYSTEMS 21 13 13 - 04
manuals shall include the manufacturer's name, model number, parts list, and tools that should be kept in stock by the owner for routine maintenance, including the name of a local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization, including address and telephone number, for each item of equipment.
d. One paper copy of the Material and Testing Certificates and the Operations and
Maintenance Manuals above shall be provided in a binder. In addition, these materials shall be provided in pdf format on a compact disc or as directed by the COR.
e. Provide one additional copy of the Operations and Maintenance Manual covering the system in a flexible protective cover and mount in an accessible location adjacent to the riser or as directed by the COR.
1.5 QUALITY ASSURANCE
A. Installer Reliability: The installer shall possess a valid State of New York) fire sprinkler contractor's license. The installer shall have been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
B. Materials and Equipment: All equipment and devices shall be of a make and type listed by UL or approved by FM, or other nationally recognized testing laboratory for the specific purpose for which it is used. All materials, devices, and equipment shall be approved by the VA. All materials and equipment shall be free from defect. All materials and equipment shall be new unless specifically indicated otherwise on the contract drawings.
1.6 APPLICABLE PUBLICATIONS
*Note: From the date contract documents are provided, the Contractor shall use the most current published versions of all listed standards and references below.
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. National Fire Protection Association (NFPA):
13-13 .......................................... Installation of Sprinkler Systems
25-14 .......................................... Inspection, Testing, and Maintenance of Water-Based Fire
Protection Systems
101-15 ........................................ Life Safety Code
170-15 ........................................ Fire Safety Symbols
WET-PIPE SPRINKLER SYSTEMS 21 13 13 - 05
C. Underwriters Laboratories, Inc. (UL):
Fire Protection Equipment Directory (2011)
D. Factory Mutual Engineering Corporation (FM):
Approval Guide
PART 2 - PRODUCTS
2.1 PIPING & FITTINGS
A. Piping and fittings for sprinkler systems shall be in accordance with NFPA 13.
1. Plain-end pipe fittings with locking lugs or shear bolts are not permitted.
2. Piping sizes 50 mm (2 inches) and smaller shall be black steel Schedule 40 with threaded end connections.3. Piping sizes 65 mm (2 ½ inches) and larger shall be black steel Schedule
10 with grooved connections. Grooves in Schedule 10 piping shall be rolled grooved only.
3. Plastic piping shall not be permitted.
4. Flexible sprinkler hose shall be FM Approved and limited to hose with threaded end fittings with a minimum inside diameter or 1-inch and a maximum length of 6-feet.
2.2 VALVES
A. General:
1. Valves shall be in accordance with NFPA 13.
2. Do not use quarter turn ball valves for 50 mm (2 inch) or larger drain valves.
B. Control Valve: The control valves shall be a listed indicating type. Control valves shall be UL
Listed or FM Approved for fire protection installations. System control valve shall be rated for normal system pressure but in no case less than 175 PSI.
C. Check Valve: Shall be of the swing type with a flanged cast iron body and flanged inspection plate.
D. Automatic Ball Drips: Cast brass 20 mm (3/4 inch) in-line automatic ball drip with both ends threaded with iron pipe threads.
E. Alarm Check Valve: Alarm check valve shall be UL Listed and Factory Mutual Approved. The alarm check valve shall be listed for installation in the vertical or horizontal position. The alarm check valve shall be equipped with a removable cover assembly, gauge connections on the system side and supply side of the valve clapper, variable pressure trim, and an external bypass to eliminate false water flow alarms. The alarm check valve trim piping shall be galvanized.
Maximum water working pressure to 250 PSI.
WET-PIPE SPRINKLER SYSTEMS 21 13 13 - 06
2.3 SPRINKLERS
A. except Provide FM approved quick response sprinklers in all areas, except that standard response sprinklers shall be provided in telecommunication rooms and data centers.
B. Temperature Ratings: In accordance with NFPA 13 except that sprinklers in elevator shafts and elevator machine rooms shall be no less than intermediate temperature rated and sprinklers in generator rooms shall be no less than high temperature rated.
C. Provide sprinkler guards in Telecommunication Rooms, Data Center’s, and in accordance with
NFPA 13 and when the elevation of the sprinkler head is less than 7 feet 6 inches above finished floor. The sprinkler guard shall be UL listed or FM approved for use with the corresponding sprinkler.
2.4 SPRINKLER SYSTEM SIGNAGE
Rigid plastic, steel or aluminum signs with white lettering on a red background with holes for easy attachment. Sprinkler system signage shall be attached to the valve or piping with chain.
2.5 SWITCHES:
A. OS&Y Valve Supervisory Switches shall be in a weatherproof die cast/red baked enamel, oil resistant, aluminum housing with tamper resistant screws, 13 mm (1/2 inch) conduit entrance and necessary facilities for attachment to the valves. Provide two SPDT switches rated at 2.5 amps at 24 VDC.
B. Water flow Alarm Switches: Mechanical, non-coded, non-accumulative retard and adjustable from 0 to 60 seconds minimum. Set flow switches at an initial setting between 20 and 30 seconds.
C. Alarm Pressure Switches: Activation by any flow of water equal to or in excess of the discharge from one sprinkler. The alarm pressure switch shall be UL Listed or Factory Mutual Approved for the application in which it is used. Activation of the alarm pressure switch shall cause an alarm on the fire alarm system control unit.
D. Valve Supervisory Switches for Ball and Butterfly Valves: May be integral with the valve.
2.6 GAUGES
Provide gauges as required by NFPA 13. Provide gauges where the normal pressure of the system is at the midrange of the gauge.
2.7 PIPE HANGERS, SUPPORTS AND RESTRAINT OF SYSTEM PIPING
Pipe hangers, supports, and restraint of system piping shall be in accordance with NFPA 13.
WET-PIPE SPRINKLER SYSTEMS 21 13 13 - 07
2.8 WALL, FLOOR AND CEILING PLATES
Provide chrome plated steel escutcheon plates.
2.9 VALVE TAGS
Engraved black filled numbers and letters not less than 15 mm (1/2 inch) high for number designation, and not less than 8 mm (1/4 inch) for service designation on 19 gage, 40 mm (1-1/2 inches) round brass disc, attached with brass "S" hook, brass chain.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be accomplished by the licensed contractor. Provide a qualified technician, experienced in the installation and operation of the type of system being installed, to supervise the installation and testing of the system.
B. Installation of Piping: Accurately cut pipe to measurements established by the installer and work into place without springing or forcing. In any situation where bending of the pipe is required, use a standard pipe-bending template. Concealed piping in spaces that have finished ceilings.
Where ceiling mounted equipment exists, such as in operating and radiology rooms, install sprinklers so as not to obstruct the movement or operation of the equipment. Sidewall heads may need to be utilized. In stairways, locate piping as near to the ceiling as possible to prevent tampering by unauthorized personnel and to provide a minimum headroom clearance of 2250 mm (seven feet six inches). Piping shall not obstruct the minimum means of egress clearances required by NFPA 101. Pipe hangers, supports, and restraint of system piping, and seismic bracing shall be installed accordance with NFPA 13.
C. Welding: Conform to the requirements and recommendations of NFPA 13.
D. Drains: Provide drips and drains, including low point drains, in accordance with NFPA 13. Pipe drains to discharge at safe points outside of the building or to sight cones attached to drains of adequate size to readily carry the full flow from each drain under maximum pressure. Do not provide a direct drain connection to sewer system or discharge into sinks. Install drips and drains where necessary and required by NFPA 13. The drain piping shall not be restricted or reduced and shall be of the same diameter as the drain collector.
E. Supervisory Switches: Provide supervisory switches for sprinkler control valves.
F. Waterflow Alarm Switches: Install waterflow alarm switches and valves in stairwells or other easily accessible locations.
WET-PIPE SPRINKLER SYSTEMS 21 13 13 - 08
G. Inspector's Test Connection: Install and supply in accordance with NFPA 13, locate in a secured area, and discharge to the exterior of the building.
H. Affix cutout disks, which are created by cutting holes in the walls of pipe for flow switches and non-threaded pipe connections to the respective waterflow switch or pipe connection near to the pipe from where they were cut.
I. Provide escutcheon plates for exposed piping passing through walls, floors or ceilings.
J. Clearances: For systems requiring seismic protection, piping that passes through floors or walls shall have penetrations sized 50 mm (2 inches) nominally larger than the penetrating pipe for pipe sizes 25 mm (1 inch) to 90 mm (3 ½ inches) and 100 mm (4 inches) nominally larger for penetrating pipe sizes 100 mm (4 inches) and larger.
K. Sleeves: Provide for pipes passing through masonry or concrete. Provide space between the pipe and the sleeve in accordance with NFPA 13. Seal this space with a UL Listed through penetration fire stop material in accordance with Section 07 84 00, FIRESTOPPING. Where core drilling is used in lieu of sleeves, also seal space. Seal penetrations of walls, floors and ceilings of other types of construction, in accordance with Section 07 84 00, FIRESTOPPING.
L. Provide pressure gauges at each water flow alarm switch location and at each main drain connection.
M. Firestopping shall be provided for all penetrations of fire resistance rated construction.
Firestopping shall comply with Section 07 84 00, FIRESTOPPING.
N. Painting of Pipe: In finished areas where walls and ceilings have been painted, paint primed surfaces with two coats of paint to match adjacent surfaces, except paint valves and operating accessories with two coats of gloss red enamel. Exercise care to avoid painting sprinklers.
Painting of sprinkler systems above suspended ceilings and in crawl spaces is not required.
Painting shall comply with Section 09 91 00, PAINTING. Any painted sprinkler shall be replaced with a new sprinkler.
O. Sprinkler System Signage: Provide rigid sprinkler system signage in accordance with NFPA 13 and NFPA 25. Sprinkler system signage shall include, but not limited to, the following:
1. Identification Signs:
a. Provide signage for each control valve, drain valve, sprinkler cabinet, and inspector’s test.
b. Provide valve tags for each operable valve. Coordinate nomenclature and identification of operable valves with COR. Where existing nomenclature does not exist, the Tag
WET-PIPE SPRINKLER SYSTEMS 21 13 13 - 09
Identification shall include no less than the following: (FP-B-F/SZ-#) Fire Protection, Building Number, Floor Number/Smoke Zone (if applicable), and Valve Number. (E.g., FP-500-1E-001) Fire Protection, Building 500, First Floor East, Number 001.)
2. Instruction/Information Signs:
a. Provide signage for each control valve to indicate valve function and to indicate what system is being controlled.
b. Provide signage indicating the number and location of low point drains.
3. Hydraulic Placards:
a. Provide signage indicating hydraulic design information. The placard shall include location of the design area, discharge densities, required flow and residual pressure at the base of riser, occupancy classification, hose stream allowance, flow test information, and installing contractor. Locate hydraulic placard information signs at each alarm check valve.
P. Repairs: Repair damage to the building or equipment resulting from the installation of the sprinkler system by the installer at no additional expense to the Government.
Q. Interruption of Service: There shall be no interruption of the existing sprinkler protection, water, electric, or fire alarm services without prior permission of the Contracting Officer. Contractor shall develop an interim fire protection program where interruptions involve occupied spaces.
Request in writing at least one week prior to the planned interruption.
3.2 INSPECTION AND TEST
A. Preliminary Testing: Flush newly installed systems prior to performing hydrostatic tests in order to remove any debris which may have been left as well as ensuring piping is unobstructed.
Hydrostatically test system, including the fire department connections, as specified in NFPA 13, in the presence of the Contracting Officers Representative (COR) or his designated representative. Test and flush underground water line prior to performing these hydrostatic tests.
B. Final Inspection and Testing: Subject system to tests in accordance with NFPA 13, and when all necessary corrections have been accomplished, advise COR to schedule a final inspection and test. Connection to the fire alarm system shall have been in service for at least ten days prior to the final inspection, with adjustments made to prevent false alarms. Furnish all instruments, labor and materials required for the tests and provide the services of the installation foreman or other competent representative of the installer to perform the tests. Correct deficiencies and
WET-PIPE SPRINKLER SYSTEMS 21 13 13 - 10
retest system as necessary, prior to the final acceptance. Include the operation of all features of the systems under normal operations in test.
3.3 INSTRUCTIONS
Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system, on the dates requested by the COR.
- - - E N D - - -
SYRACUSE VA MEDICAL CENTER – SYRACUSE, NY PUB. DATE: 05-01-15
CLEAN AGENT FIRE SUPPRESSION SYSTEMS 21 22 00 - 01
SECTION 21 22 00
CLEAN AGENT FIRE SUPPRESSION SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. Design, installation and testing of a calculated automatic and manual fixed total flooding clean agent fire extinguishing system and releasing system in accordance with NFPA 2001, NFPA 72, NFPA 70, and NFPA 75 and manufacturer’s written instructions for the locations shown on the contract drawings. The installation shall include all mechanical, controls and electrical components necessary for a complete and operating clean agent fire suppression system.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
B. Section 07 84 00, FIRESTOPPING
C. Section 09 91 00, PAINTING
D. Section 28 05 13, CONDUCTORS AND CABLES FOR ELECTRONIC SAFETY AND SECURITY
E. Section 28 05 28.33, CONDUIT AND BACKBOXES FOR ELECTRONIC SAFETY AND SECURITY
F. Section 28 31 00, FIRE DETECTION AND ALARM
1.3 DESIGN CRITERIA
A. The clean agent fire extinguishing system shall be a fixed total flooding type utilizing clean agent designed to provide a uniform concentration throughout the protected spaces in accordance with NFPA 2001 for a Class C fire.
1. The system shall provide a minimum design concentration by volume, throughout the protected spaces at the minimum anticipated temperature within the protected space.
2. The design concentration within any protected space shall not exceed by volume the no observable adverse effects level (NOAEL). Special means such as mechanical exhaust, shall not be permitted to be used to achieve this criterion.
3. The clean agent shall have a global warming potential (GWP) of less than 4000 and the clean agent shall be readily available throughout the continental United States.
4. Provide the quantity of clean agent as required by NFPA 2001 and manufacturer’s written instructions. Such factors as unenclosed openings (if any), “rundown” time of fans, time required for dampers to close, and any other feature of the facility that could affect concentration shall be taken into consideration.
5. Provide seismic bracing for the clean agent fire extinguishing system components.
CLEAN AGENT FIRE SUPPRESSION SYSTEMS 21 22 00 - 02
1.4 SUBMITTALS
A. Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level IV Special
Hazards Suppression Systems Technician. As the Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or binders and provide an index referencing the appropriate specification section. In addition to the hard copies, provide submittal items in Paragraphs 1.4
(A) 1 through 1.4 (A) 5 electronically in pdf format on a compact disc or as directed by the
Contracting Officers Representative (COR). Submittals shall include, but not be limited to, the following:
1. Qualifications:
a. Provide a copy of the installing contractors Special Suppression Systems and state contractors license.
b. Provide a copy of the NICET certification for the NICET Level IV Special Hazards
Suppression System Technician who will prepare and sign the detailed working drawings.
c. Provide documentation showing that the installer has been actively and successfully engaged in the installation of clean agent fire suppression systems for the past ten years.
2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working plans and drawings of the clean agent fire extinguishing system conforming to NFPA 2001. Submit detailed 1:100
(1/8 inch) scale (minimum) working plans and drawings of the releasing system conforming to NFPA 72. Drawings shall include graphical scales that allow the user to determine lengths when the drawings are reduced in size.
3. Manufacturers Data Sheets:
a. Provide for all materials and equipment proposed for use on the clean agent fire extinguishing system, including the releasing system. Include listing information and installation instructions in data sheets. Where data sheet describes items in addition to that item being submitted, clearly identify proposed item on the sheet.
4. Calculation Sheets:
CLEAN AGENT FIRE SUPPRESSION SYSTEMS 21 22 00 - 03
a. Submit flow calculation sheets in tabular form conforming to the requirements of NFPA
2001. Calculations shall include total storage capacity, flooding concentrations, enclosure leakage rates, discharge times, flow through distribution network, pipe sizes, and nozzle orifice sizes.
b. Submit battery calculations sheets in tabular form conforming to the requirements of
NFPA 72.
c. Submit voltage drop calculations in tabular form. Calculations shall indicate circuit amperage draw, wire resistance, circuit length, and voltage drop. The voltage drop shall demonstrate that voltage provided at the each appliance is within its operating voltage range. Voltage drop calculations shall assume an initial voltage of 20.4 volts.
d. Submit calculations of loads for sizing of sway bracing.
5. Clean Agent Recharging Certification: Provide a letter to the COR or his designated representative certifying that the installer maintains or has access to a clean agent recharging station. The installer shall also provide proof of the ability to recharge the largest clean agent fire extinguishing system capacity within 48 hours.
6. Test Plan: Provide a test plan to the COR or his designated representative. The testing plan shall describe the procedures to be used to test the system. The testing plan shall include a step-by-step procedure of all tests to be performed, including indication of which tests will present a disruption to building occupants. No tests shall be conducted until the testing plan is approved by the COR or his designated representative.
7. Final Document Submittals: Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in Section 01 33 23, SHOP DRAWINGS, PRODUCT
DATA, AND SAMPLES. Submittals shall include, but not be limited to, the following:
a. A complete set of as-built drawings showing the installed system with the specific interconnections between the system switches and the fire alarm equipment. Provide a complete set in the formats as follows. Submit items 2 and 3 below on a compact disc or as directed by the COR.
1) One full size (or size as directed by the COR) printed copy.
2) One complete set in electronic pdf format.
3) One complete set in AutoCAD format or a format as directed by the COR.
b. System Certification: Upon completion of the clean agent fire extinguishing system installation, including testing, the authorized representative of the manufacturer of the
CLEAN AGENT FIRE SUPPRESSION SYSTEMS 21 22 00 - 04
major equipment shall certify that the installation complies with all manufacturer’s requirements and that satisfactory total system operation has been achieved. Provide a copy of the Record of Completion for the releasing system in accordance with NFPA 72.
c. Operating and Maintenance Manuals that include step-by-step procedures required for operation, shutdown, and routine maintenance and testing. The manuals shall include the manufacturer’s name, model number, parts list, the name of the local supplier, simplified wiring and controls diagrams, troubleshooting guide, and recommended service organization, including address and telephone number, for each item of equipment.
d. One paper copy of the System Certification and Record of Completion and the Operating and Maintenance Manuals listed above shall be provided in a binder. In addition, these materials shall be provided in pdf format on a compact disc or as directed by the COR.
e. Provide one additional copy of the Operations and Maintenance Manual for the system in a binder and mount in an accessible location adjacent to the storage cylinder(s).
1.5 QUALITY ASSURANCE
A. Installer Reliability: The installer shall possess a valid State of New York contractor's license. The installer shall have been actively and successfully engaged in the installation of clean agent special suppression systems for the past ten years. The installer shall maintain or have access to a clean agent recharging station. The installer shall provide proof of the ability to recharge the largest clean agent fire extinguishing system capacity within 48 hours.
B. Materials and Equipment: All equipment and devices shall be UL listed or approved by FM. All materials, devices, and equipment shall be approved by the VA. All materials and equipment shall be free from defect.
1.6 APPLICABLE PUIBLICATIONS
*Note: From the date contract documents are provided, the Contractor shall use the most current published versions of all listed standards and references below.
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. National Fire Protection Association (NFPA):
70 ............................................... National Electric Code
72 ............................................... National Fire Alarm Code
75 ............................................... Fire Protection of Information Technology Equipment
CLEAN AGENT FIRE SUPPRESSION SYSTEMS 21 22 00 - 05
170 ............................................. Fire Safety Symbols
2001 ........................................... Installation of Clean Agent Fire Extinguishing Systems
C. Underwriters Laboratories, Inc. (UL):
2011................... Fire Protection Equipment Directory
D. Factory Mutual Engineering Corporation (FM):
2015................... Approval Guide
1.7 WARRANTY
All work performed and all material and equipment furnished under this contract shall be free from defects and shall remain so for a period of one year from the date of acceptance of the entire installation by the COR.
PART 2 PRODUCTS
2.1 GENERAL
All equipment and components shall be new and the manufacturer’s current model. All equipment and components shall be UL listed or FM approved for its intended use. The authorized representative of the manufacturer of the major equipment shall certify that the installation complies with all manufacturer’s requirements and that satisfactory total system operation has been achieved.
2.2 CLEAN AGENT FIRE EXTINGUISHING SYSTEM
A. General:
1. The clean agent fire extinguishing system shall be UL listed and shall be in accordance with
NFPA 2001.
B. Piping and fittings:
1. All piping and fittings shall be in compliance with NFPA 2001.
2. Multi-outlet fittings, other than tees, shall not be permitted.
3. All piping shall be reamed, blown clear, and swabbed with appropriate solvent to remove mill varnish and cutting oils before assembly.
4. Ordinary cast iron steel and non-metallic piping and fittings and flexible hoses shall not be used unless specifically required by the manufacturer.
C. Piping Support:
1. All piping shall be supported in accordance with the manufacturer’s written instructions.
2. Piping shall be supported within 12 inches (304 mm) of discharge nozzles. The supports shall prevent the upward movement of the nozzle.
CLEAN AGENT FIRE SUPPRESSION SYSTEMS 21 22 00 - 06
3. Seismic bracing shall be installed.
D. Storage Cylinders:
1. Provide storage cylinders as required by the manufacturer’s written instructions and in accordance with NFPA 2001.
2. Cylinder assemblies shall be of steel construction designed to meet the requirements of the
U.S. Department of Transportation.
3. Filling of the storage cylinders shall be by an authorized systems distributor in conjunction with a factory authorized agent filling station. Initial filling and recharge shall be performed in accordance with manufacturer’s written instructions and shall not require replacement components for normal service.
4. Cylinders shall be securely attached to the wall. Provide factory- or field-fabricated retaining brackets consisting of steel straps and channels; suitable for container support, maintenance, and tank refilling or replacement.
5. For halocarbon clean agents, storage cylinders shall be provided with a low agent pressure switch.
E. Valve Actuators:
1. Electric valve actuators shall be of brass construction and stackable design with swivel connections to allow removal of actuators for maintenance or testing.
2. Operation of actuators shall not require replacement of components. No electro-explosive devices may be used to actuate the valve assembly. Actuators shall include an indication if they are set or actuated.
3. Electric valve actuators shall be magnetic latch, continuous duty type for 24 VDC operation.
4. Actuation devices shall be UL listed or FM approved for use with the system.
5. Removal of the electric valve actuator shall cause a trouble on the clean agent control panel.
F. Discharge Nozzles:
1. Nozzles shall be permanently marked with the manufacturer’s part number. The nozzles shall be threaded directly to the discharge piping without the use of special adaptors.
2.3 RELEASING SYSTEM
A. General
1. The releasing system shall be an analog addressable intelligent reporting, microprocessor controlled system, capable of remote sensitivity testing of the smoke detectors, and be installed in accordance with NFPA 70, NFPA 72, and NFPA 2001.
CLEAN AGENT FIRE SUPPRESSION SYSTEMS 21 22 00 - 07
B. Clean Agent Control Panel:
1. General:
a. The clean agent control panel shall be UL listed or FM approved and include a UL listed or FM approved releasing module.
b. Each protected space shall be provided with its own clean agent control unit.
c. All circuits shall be monitored for integrity.
d. Visually and audibly annunciate all alarm, supervisory, and trouble signals including, but not limited to main power failure, open circuit, short circuit, ground faults, and system bypass activation.
e. The panel or releasing module shall include a 0-60 second programmable timer.
f. The clean agent control panel shall be provided with separate contacts to provide common supervisory, alarm, and trouble signals to the main building fire alarm system.
2. Enclosure:
a. The clean agent control unit shall be housed in a cabinet suitable for both recessed and surface mounting. The cabinet and front panel shall be corrosion protected, given a rust-resistant prime coat, and manufacturer's standard finish.
b. The cabinet shall contain all necessary relays, terminals, lamps, and legend plates to provide control for the system.
3. Power Supply:
a. The clean agent control unit shall derive its normal power from a 120 volt, 60 Hz dedicated supply connected to the emergency power system. Standby power shall be provided by a 24 volt DC battery as hereinafter specified. The normal power shall be transformed, rectified, coordinated, and interfaced with the standby battery and charger.
b. The power supply for smoke detection systems shall be taken from the clean agent control unit.
4. Circuit Supervision: Each alarm initiating device circuit, signaling line circuit, and notification appliance circuit, shall be supervised against the occurrence of an open, short circuit, or ground fault condition in the field wiring. These conditions shall cause a trouble signal to sound in the control unit until manually silenced by an off switch.
a. Initiating device circuits (IDC) shall be wired Class B in accordance with NFPA 72.
b. Signaling line circuits (SLC) shall be wired Class B in accordance with NFPA 72.
CLEAN AGENT FIRE SUPPRESSION SYSTEMS 21 22 00 - 08
c. Notification appliance circuits (NAC) shall be wired Class B in accordance with NFPA
72.
5. Supervisory Alarm Devices: The low agent…