ATTACHMENT 13 - Pre-Construction Risk Assessment.pdf

PDF 389 KB Posted

Attached to
Y1BG--EHRM Infrastructure Upgrades Construction - Syracuse - Project 528A7-22-700
Solicitation number
36C77626B0009
Issued by

About this file

This is a VHA Pre-Construction Risk Assessment (PCRA) template and completed permit for construction, renovation, and maintenance activities at VA medical facilities. The template provides minimum requirements for categorizing activity types and safety risks to determine necessary precautions for protecting patients, employees, and contractors from non-infection-related hazards during construction work.

The document establishes three activity classification levels—Inspection/Upkeep, Small-scale, and Large-scale—each with corresponding mandatory control measures that escalate in complexity. Inspection/Upkeep activities include work completable in a single shift without creating dust, vapors, or noise, requiring weekly site visits and contractor safety plans. Small-scale activities exceed single shifts but do not exceed six months, necessitating hazard communication inventories, ILSM assessments per TJC standards, hot work permits, and LOTO procedures with daily inspections. Large-scale activities exceed six months and require comprehensive Activity Hazard Analyses and Control Plans addressing excavation safety, dust control, pollution prevention, dig-safe procedures, crane lift plans, fall protection, and confined entry protocols. The completed permit example indicates a Large-scale classification for the Syracuse VA Medical Center data center and network infrastructure project (start date 04/30/2026, completion 04/28/2028), with dust control and crane lift plans marked as required. The document mandates coordination with affected adjacent areas, development of communication plans, compliance with Infection Control Risk Assessment (ICRA) requirements when necessary, and signatures from project management, safety officers, and construction safety committee chairs before work commences.

View the file

Other files

File Type Posted
36C77626B0009 0008.pdf PDF
36C77626B0009 0007.pdf PDF
Technical Questions Responses - Syracuse EHRM - 6-9-26.pdf PDF
ATTACHMENT 1 - SPEC DIV 01-13 Updated 6-3-26.pdf PDF
ATTACHMENT 4 - Drawings General - Architectural Updated 5-20-26.pdf PDF
ATTACHMENT 5 - Drawings Electrical Updated 5-20-26.pdf PDF
ATTACHMENT 6 - Drawings Mechanical Updated 5-20-26.pdf PDF
ATTACHMENT 8 - Drawings Technology Updated 5-20-26.pdf PDF
ATTACHMENT 9 - Drawings Telecommunications Updated 5-20-26.pdf PDF
36C77626B0009 0006.pdf PDF
ATTACHMENT 7 - Drawings Structural Updated 5-20-26.pdf PDF
ATTACHMENT 15 - Construction Wage Rates - Onondaga 5-18-26.pdf PDF
36C77626B0009 0005.pdf PDF
36C77626B0009 0004.pdf PDF
36C77626B0009 0003.pdf PDF
C - 52.222-90 Addressing DEI Discrimination by Federal Contractors - APR 2026.pdf PDF
VAAR 852.204-70 Personal Identity Verification of Contractor Personnel - DEV MAR 2026.pdf PDF
36C77626B0009 0002.pdf PDF
VAAR 852.204-72 Personnel Vetting and Credentialing MAR 2026 REV.pdf PDF
Section 23 09 23 Digital Control System HVAC - Updated 3-17-26.pdf PDF
Site Visit Sign-in Sheet - Syracuse EHRM 3-11-26.pdf PDF
36C77626B0009 0001.pdf PDF
ATTACHMENT 12 - Brand Name Justification.pdf PDF
ATTACHMENT 4 - Drawings General - Architectural.pdf PDF
ATTACHMENT 11 - Syracuse Campus Map.pdf PDF
ATTACHMENT 14 - Limitations on Subcontracting - Construction.docx DOCX document
ATTACHMENT 5 - Drawings Electrical.pdf PDF
ATTACHMENT 8 - Drawings Technology.pdf PDF
ATTACHMENT 10 - Asbestos Report.pdf PDF
36C77626B0009 - 3-2-26.pdf PDF
ATTACHMENT 1 - SPEC DIV 01-13.pdf PDF
ATTACHMENT 2 - SPEC DIV 21-23.pdf PDF
ATTACHMENT 3 - SPEC DIV 25-28.pdf PDF
ATTACHMENT 6 - Drawings Mechanical.pdf PDF
ATTACHMENT 7 - Drawings Structural.pdf PDF
ATTACHMENT 9 - Drawings Telecommunications.pdf PDF
ATTACHMENT 15 - Construction Wage Rates - Onondaga 1-30-26.pdf PDF
ATTACHMENT 16 - Site Visit Instructions.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VHA Pre-Construction Risk Assessment (PCRA)

VHA-PCRA-2024-1.1 (May 21, 2024) Page 1 of 5

PCRA Introductory Information and Instructions

Use this template as a baseline for performing facility Pre-Construction Risk Assessments (PCRA) for Construction, Renovation, and Maintenance work (referred to as the “activity” in this document). The template provides minimum requirements for categorizing activity type(s) and safety risk to determine the level of precautions needed to prevent impact related to Construction, Renovation and Maintenance on patients, employees, and contractors.

Ensure that the activity statement of work and any drawings available are used for the PCRA assessment and included in the project file with the completed PCRA.

Communication and coordination of all types of activity with affected areas are to be included among the control measures. The development of communication and coordination plans must begin during the activity planning phase.

Facilities may customize this template to incorporate site-specific information and requirements.

NOTE: This VHA PCRA template pertains specifically to non-infection-related safety for Construction, Renovation, and Maintenance activities. It must be used in conjunction with the VHA Infection Control Risk Assessment (ICRA) for the activity, if required, which specifically addresses infection risks outside the scope of this PCRA.

PERMIT: See the last page of this document for a fillable permit form to be used for posting at the activity site.

Activity Location:

Activity Name, Number, and/or Brief Description:

Table 1 - Construction, Renovation, and/or Maintenance Activity Type and Control Measures NOTE: If any of the bulleted criteria in a higher activity type pertains to the work that will be done (even if the other criteria are in a lower type), use the higher activity type for the VHA PCRA.

Controls defined in Table 1 for the activity must be in place before the activity begins and maintained until work is completed and the area is activated. Control measures for each activity must also include the control measures in the preceding row(s).

As the activity progresses, a full re-evaluation of remaining activity type and risk is required prior to changing the level of control measures.

Activity Type determined from Table 1:

Activity Type and Description Control Measures Inspection/upkeep generally defined as follows:

• Work can be completed in a single shift, not to exceed 10 hours.

• Patients, employees and/or visitors may be in the area depending on the activity.

• Work that does not create dust or debris.

• Work that does not create vapors or fumes.

• Removal of ceiling tile or access to mechanical or electrical chase for visual inspection that will not impair fire safety systems and are limited to 1 tile per 50 square feet with limited

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team.

Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved where a contact is in place. For internal work the

VHA-PCRA-2024-1.1 (May 21, 2024) Page 2 of 5 exposure time (not to exceed an hour for each tile) within the shift.

• Minor interior updates (e.g., replacing floor or ceiling tiles, carpentry work to include hanging signage, and painting with hand tools) that do not create vibration or noise.

• Limited building system maintenance that does not require Lock Out Tag Out (LOTO) such as plumbing on potable systems limited to faucet replacement, steam trap replacement etc. and electrical work such as replacement of bulbs, receptacles, or switches.

shop involved must work with Safety to ensure proper precautions are in place.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact to patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small scale Construction, Renovation and general maintenance/repair work, generally defined as follows:

• Prolonged work that may take longer than a single shift but not exceeding six months.

• Patients and employees are not to be in the area until activity is completed.

• Work that creates some noise and vibration due to power tool use.

• Selective demolition/removal of preexisting floor covering, casework, lay-in ceiling, or other architectural elements that may o disturb asbestos, lead or silica o create the potential for falling objects o create vibration and/or noise in excess of 80 dB(A) in surrounding areas.

o cause penetrations in fire or smoke barrier

• Plumbing work such as the installation of new sinks, showers and toilets and associated plumbing that requires utility outages or work on the steam system that may require:

o LOTO o The use of compressed gas cylinders

• Electrical work such as installation of conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. Electrical work such as installation of cabling/wiring/conduit for a single device, installation of new device such as a light fixture that require LOTO.

• Air Handler and/or fan shutdown/startup and HVAC work such as replacement of a single diffuser, single terminal unit, a single device and the installation of ductwork, diffusers, and terminal units for an area that may require:

o Work on ladders o Rigging, hoisting or lifting of equipment or materials overhead

• Modification of existing fire alarm and suppression systems requiring system outages and ILSMs or obstruction of exits and or impact on corridors.

• Architectural, structural, or any other work that may cause vapors or fumes such as:

o Roofing work o Flooring work o Painting or other large-scale use of such substances.

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. Where construction, Renovation and maintenance are done in an accredited facility, and ILSM assessment is required to be done and ILSMs put into place in accordance with TJC LS.01.02.01 and the local facility policy including Fire watch if necessary. Staff is trained and the ILSM is verified regularly

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor or shop supervisor and documented on their daily log.

Large-scale construction, renovation, or maintenance generally defined as follows:

• Work exceeding 6 months in duration.

• Patients and employees are not to be in the area until activity is completed.

All control measures in the two rows above and the following Activity Hazard Analyses and Control Plans (check all that apply):

1. Excavation safety plan in place ☐

2. Dust control plan in place ☐

VHA-PCRA-2024-1.1 (May 21, 2024) Page 3 of 5

• Excavation or heavy equipment use taking place o Dig safe required utility location o Trench safety o Dust control plan o Equipment exhaust, Noise, Vibration

• Confined space entry required (permit required or not)

• Requires crane work o General crane work o Lift over buildings

• Includes elevated work o Roof work, fall protection o Window work, scaffolding and fall protection o Odor control

• Welding, cutting or use of torches requiring burn permits

• Demolition of building components and infrastructure including removal of multiple doors, walls, framing, ceilings, flooring, piping, electrical and HVAC that may o require asbestos, lead or silica abatement o create the potential for falling objects o create vibration and/or noise in excess of 90 dB(A) in surrounding areas.

o cause breaches to fire or smoke barrier

• The installation building components such as new walls, ceilings and doors including framing, drywall and associated plaster work that requires transport of significant materials through building and up elevators i.e., weight limits of floors and elevators

• Plumbing work requiring LOTO and system shutdown and startup such as the installation of:

o new medical gas systems, o steam/heating hot water, condensate systems, o Potable water and sanitary drainage, multiple sinks, showers and toilets including associated plumbing.

• Electrical work such as installation of electrical feeders, distribution panels, conduit and wire for lighting, receptacles and switches for an area, the installation of conduit and wire for new devices such as terminal units, fans etc. requiring LOTO and system isolation.

• Installation of fire alarm and suppression systems requiring outages of those systems and ILSMs or closure of exits/corridors

• Mechanical work such as the installation of air handling equipment, associated ductwork, diffusers, heat exchangers, terminal units and controls requiring lifting and support of equipment and systems.

3. Pollution prevention plan in place ☐

4. Dig safe paper work in place ☐

5. Crane lift plan in place ☐

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained ☐

7. Confined entry plan in place and staff trained ☐

Table 2. Affected Adjacent Area Assessment In addition to the minimum precautions noted above for the Activity Type, it is critical that the activity be coordinated with the areas adjacent to the activity to ensure operations in those areas are not disrupted or impacted. List the adjacent areas in Table 2 below and develop activity-specific coordination plans and associated communication plans with each area to address activity work that could impact or disrupt the operation of the areas, in general as follows:

• If adjacent area is vacant (e.g., work outside, construction of new building, etc.):

o Coordination is typically not necessary other than potentially traffic flow and pedestrian access.

VHA-PCRA-2024-1.1 (May 21, 2024) Page 4 of 5

• If adjacent area is non-continuously occupied (e.g., areas where outpatient care is provided, employee health, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., conduct work after hours).

• If adjacent area is occupied continuously (e.g., areas where inpatient care is provided, residential areas such as Community Living Centers, etc.):

o Develop a list of activities that will potentially impact or disrupt the operation of the area (e.g., work involving noise, vibration or exit obstruction) and meet with POC to coordinate execution of work in a way that mitigates the impact (e.g., move affected party temporarily).

Area Service(s)/Type(s) of Area(s)

(e.g., OR, Unit/Ward, Sterile Processing, Administrative, etc)*

Point of Contact

(POC)

POC Contact Information

Construction plan communicated to POC?

Activity Area**

Area Above

Area Below

Adjacent Area 1

Adjacent Area 2

Adjacent Area 3

Adjacent Area 4

* There may be more than one Service/type of area for each row. List all. The information entered on this table must be used in the ICRA if required.

** List the area(s) in which the construction/renovation/maintenance activity will occur.

Infection Control Risk Assessment (ICRA)

Consult with Infection Prevention and Control regarding the assessment of potential patient infection risks associated with the activity and the need for control measures. For example, activities such as a boiler plant project and/or facility steam shutdown, if properly planned, should have minimal to no patient infection risk impacts and likely not to require an ICRA. See VHA Directive 7715 and the VHA ICRA Template for more information.

Is an ICRA required for the Activity? Yes ☐ No ☐

VHASYRKERESP

Text Box X

Pre-Construction Risk Assessment (PCRA) Permit This page must be posted at the entrance to the project area, or other designated area

Unique permit number:

Location and brief description of construction/renovation/maintenance Project manager Project start date Contact phone number Completion date Contractor or lead shop Permit expiration date

Activity Type Inspection/Upkeep, Small-scale, or Large-scale)

Activity Type Control measures to be in place for the duration of the activity (Check the box for the Activity Type to indicate the Control Measures)

Inspection/Upkeep

1. Immediately replace any ceiling tile, close access panels, etc., upon completion of work.

2. Site visits of construction area are required weekly by member of multi-disciplinary team. Site visits will be documented on standard checklist.

3. Site specific safety plan, task hazard analysis, and hazard communication required to be provided by the contractor and approved.

4. Must address identified hazards and controls that will be implemented to ensure minimal impact patients, employees, contractors and facility.

5. Communication and coordination plan for all affected areas

Small-scale

All control measures in the row above and the following:

1. Hazard communication chemical inventory required to be provided by the contractor and approved.

2. ILSMs in place and staff trained on situation

3. Hot Work or burn permits in place and staff trained

4. LOTO procedures in place and staff trained on their use

5. Site visits will be reviewed using the criteria in standardized guide.

6. Daily inspections of the site are to be conducted by the General Contractor and documented on their daily log.

Large-scale

All control measures in both rows above and the following Activity Hazard Analyses and Control Plans as applicable (check all that apply):

1. Excavation safety plan in place ☐

2. Dust control plan in place ☐

3. Pollution prevention plan in place ☐

4. Dig safe paperwork in place ☐

5. Crane lift plan in place ☐

a. Crane placement

b. Crane swing

c. Crane load evaluation

6. Fall protection plan in place and staff trained ☐

7. Confined entry plan in place and staff trained ☐

*The location of all Activity Hazard Analyses and Control Plans (excavation, dust, pollution, etc.) as applicable shall be identified on this permit and shall be made available to all workers on the job.

VHA-PCRA-2024-1.1 (May 21, 2024)

Additional requirements:

Is an Infection Control Risk Assessment (ICRA) required for the Activity? Yes ☐ No ☐ Infection Prevention and Control signature:

Date:

Project Manager signature Date

Safety Officer signature Date

Chair, Construction Safety Committee signature

Date

PERMIT See the last page of this document for a fillable permit form to be used for posting at the activity site: Syracuse Va Medical Center & Rome Location
andor Brief Description: Building New Data Center and TR rooms run all new Cat 6 Ethernet cabling at Syracuse Location. Rome will have Data center updated.
As the activity progresses a full reevaluation of remaining activity type and risk is required prior to changing: Mostly Large Scale at start, then small scale later on in project
Excavation safety plan in place: Off
Dust control plan in place: Off
Dig safe paper work in place: Off
Crane lift plan in place: Off
Fall protection plan in place and staff trained: Off
undefined: Off
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcActivity Area: There are multiple areas that will be worked on.
Point of Contact POCActivity Area: Areas will be addressed when plan is in place
POC Contact InformationActivity Area:
Construction plan communicated to POCActivity Area:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcArea Above:
Point of Contact POCArea Above:
POC Contact InformationArea Above:
Construction plan communicated to POCArea Above:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcArea Below:
Point of Contact POCArea Below:
POC Contact InformationArea Below:
Construction plan communicated to POCArea Below:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 1:
Point of Contact POCAdjacent Area 1:
POC Contact InformationAdjacent Area 1:
Construction plan communicated to POCAdjacent Area 1:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 2:
Point of Contact POCAdjacent Area 2:
POC Contact InformationAdjacent Area 2:
Construction plan communicated to POCAdjacent Area 2:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 3:
Point of Contact POCAdjacent Area 3:
POC Contact InformationAdjacent Area 3:
Construction plan communicated to POCAdjacent Area 3:
ServicesTypes of Areas eg OR UnitWard Sterile Processing Administrative etcAdjacent Area 4:
Point of Contact POCAdjacent Area 4:
POC Contact InformationAdjacent Area 4:
Construction plan communicated to POCAdjacent Area 4:
Is an ICRA required for the Activity: Off
Activity Type InspectionUpkeep Smallscale or Largescale:
1 Excavation safety plan in place: Off
2 Dust control plan in place: On
3 Pollution prevention plan in place: Off
4 Dig safe paperwork in place: Off
5 Crane lift plan in place: On
6 Fall protection plan in place and staff trained: Off
7 Confined entry plan in place and staff trained: Off
Additional requirements:
Is an Infection Control Risk Assessment ICRA required for the Activity: Off
Pollution prevention plan in place: Off
Unique permit number:
Project manager: Paul Kerestedjian
Contact phone number: 315-425-4400 x 54704
Project Start Date_af_date: 04/30/2026
Completion Date_af_date: 04/28/2028
Permit Expiration Date_af_date:
Contractor or lead shop: TBD
Location and brief description of Construction/Renovation/Maintenance: Syracuse Rome locations
Check Box6: Off
Check Box7: Off
Check Box8: Yes
Date10_af_date:
2025-12-04T13:59:51-0500
PAUL KERESTEDJIAN
315 425 4400 ex 55644
2025-12-09T06:29:25-0500
VAMC Syracuse NY
DAVID RODABAUGH
Project Manager Date Signed_af_date:
Safety Officer Date Signed_af_date:
CCS Date Signed_af_date: