Amendment to Solicitation/Modification of Contract

This is Amendment 0005 to Solicitation 36C77625B0050, issued by the Department of Veterans Affairs (VA), Program Contracting Activity Central, located in Independence, Ohio. The amendment is effective January 14, 2026, with an extended receipt deadline of February 18, 2026. The Contracting Officer is Bridget May, referenced as VA-VHA-RPOC-2023-0041.

The amendment serves to distribute RFI (Request for Information) responses and related attachments, specifically providing a Technical Questions Tracker along with Attachments 1-6. Additionally, the amendment updates the Price Schedule for the solicitation, correcting the quantity for CLINs 0001 and 0002 from 0.00 Job Breaks (JB) to 1.00 JB. Offerors must acknowledge receipt of this amendment prior to the specified hour and date by completing the form and returning one copy to the issuing office, acknowledging receipt on each offer copy submitted, or by separate written or electronic communication that references both the solicitation and amendment numbers. Failure to acknowledge receipt by the deadline may result in rejection of the offer.

View the file

Other files

File Type Posted
S05 - Tech Questions Tracker - EHRM Portland Phase 2 - VA Responses Update 2-26-26.pdf PDF
36C77625B0050 0008.pdf PDF
36C77625B0050 0007.pdf PDF
36C77625B0050 0006.pdf PDF
Tech Questions Tracker - EHRM Portland Phase 2 - VA Responses Update.pdf PDF
Attachment 4 - Electrical Schedules.pdf PDF
Attachment 2 - Project Schedules.pdf PDF
Attachment 6 - Geotech Report Vancouver Campus WA.pdf PDF
Attachment 3 - Overall Site Plan.pdf PDF
Tech Questions Tracker - EHRM Portland Phase 2 - VA Responses.pdf PDF
Attachment 5 - Div 28 Specifications.pdf PDF
Attachment 1 - Site Map.pdf PDF
36C77625B0050 0004.pdf PDF
Attachment - Site Visit Sign-in Sheet - Portland Campus - Completed 1-29-26.pdf PDF
Attachment - Site Visit Sign-in Sheet - Vancouver Campus - Completed 1-29-26.pdf PDF
36C77625B0050 0003.pdf PDF
EHRM Pre Bid Site Maps Portland and Vancouver 1-22-2026.pdf PDF
36C77625B0050 0002.pdf PDF
EHRM Infra Upgrades Phase 2 Portland Site Visit Instructions.pdf PDF
36C77625B0050 0001.pdf PDF
EHRM pre-bid site visit maps.pdf PDF
Attachment 4A - Construction WD - Vancouver WA - 01-02-2026.pdf PDF
Attachment 5 - Site Visit Instructions.pdf PDF
Attachment 6 - Limitations on Subcontracting - Construction.pdf PDF
Attachment 4B - Construction WD - Portland OR - 01-02-2026.pdf PDF
Attachment 2 - Portland EHRM Phase 2 ICRA - Final.pdf PDF
Attachment 1 - Portland EHRM Phase 2 Drawings - Final.pdf PDF
Attachment 3 - Portland EHRM Phase 2 Specs - Final.pdf PDF
36C77625B0050_1.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 1

0005 02-18-2026

648-24-701

36C776

Department of Veterans Affairs Program Contracting Activity Central

6100 Oak Tree Blvd, Suite 490 Independence OH 44131

36C776

Department of Veterans Affairs Program Contracting Activity Central

6100 Oak Tree Blvd, Suite 490 Independence OH 44131

36C77625B0050

01-14-2026

X

X X

See CONTINUATION Page

X 1 (ONE)

The purpose of this amendment is to provide RFI responses and attachments.

Please find the attached Technical Questions Tracker along with Attachments 1-6.

In addition, this amendment updates the Price Schedule. Please note that the IFB indicates 0.00 JB for CLINS 0001 and 0002. This amendment updates the Quantity to 1.00 JB.

Bridget May Contracting Officer