Attachment 2 - Tech Qs - Manchester 618-315 2025-08-22 responses.docx

DOCX document 208 KB Posted

Attached to
Y1DB--Construct Specialty Care Building - Manchester Minor Project 608-315
Solicitation number
36C77625B0024
Issued by

About this file

This document is a Technical Questions and Solicitation Responses Tracking Sheet for a VA construction project in Manchester, NH (Solicitation #36C77625B0024). The document contains detailed technical queries and responses related to the construction of a Specialty Care Building, focusing specifically on glass, aluminum, and framing systems for the project. Key technical discussions include blast requirements, mission critical design specifications (50ft Set-Back with Design Threat W1 and GP-2), curtain wall and storefront system requirements, glazing types, and finish specifications. Responses address concerns about window sizing, structural glazing, frame dimensions, and material finishes, with several references to revised drawings dated 8-21-2025 that provide updated technical details for the contractors.

View the file

Other files

File Type Posted
36C77625B0024 0008.docx DOCX document
Attachment 5 - 084413 - Glazed Aluminum Curtain Wall.pdf PDF
Attachment 4 - VAMC_MANCHESTER_A5-2.1 - 608-315.pdf PDF
Attachment 1 - Virtual Bid Opening Updated - Manchester.pdf PDF
36C77625B0024 0008.docx DOCX document
Attachment 3 - VAMC_MANCHESTER_A2-2.3 - 608-315.pdf PDF
S06 - Atch 1 - Virtual Bid Opening Updated 8.19.25 - Manchester.pdf PDF
36C77625B0024 0007.docx DOCX document
S06 - Atch 1 - Tech Qs - Manchester 618-315 NEW 8.13.2025.docx DOCX document
S06 - Atch 2 - Panel DP nameplate - 608-315.jpg JPG image
36C77625B0024 0006.docx DOCX document
Atch 1 - Virtual Bid Opening UPDATED - Manchester NH 608-315.pdf PDF
36C77625B0024 0005.docx DOCX document
S06 - Atch 4 - Bid Addendum Bldg 1 Basement Floor Plan.pdf PDF
S06 - Atch 1 - Tech Qs - Manchester 618-315 8.7.2025.docx DOCX document
36C77625B0024 0004.docx DOCX document
S06 - Atch 2 - Q60 Response Select Drawings from Existing Building Construction.pdf PDF
S06 - Atch 6 - 122400 - Window Shades.pdf PDF
S06 - Atch 5 - Bid Addendum Bldg 1 First Floor Plan.pdf PDF
S06 - Atch 3 - Bid Addendum 1 Drawing Corrections.pdf PDF
36C77625B0024 0003.docx DOCX document
Atch 2 - 087100 Door Hardware 2025-07-31.pdf PDF
Atch 1 - Tech Qs - Manchester 608-315 07252025.docx DOCX document
Atch 6 - Bid Addendum Bldg 1 First Floor Plan.pdf PDF
Atch 2 - Site Visit Agenda - Manchester NH 608-315.pdf PDF
Atch 8 - 122400 - Window Shades.pdf PDF
Atch 3 - Site Visit Sign-In Sheet - Manchester NH 608-315.pdf PDF
Atch 4 - Virtual Bid Opening Information - Manchester NH 608-315.pdf PDF
36C77625B0024 0002.docx DOCX document
Atch 5 - Bid Addendum Bldg 1 Basement Floor Plan.pdf PDF
Atch 1 - Tech Qs - Manchester 608-315 FINAL.docx DOCX document
Atch 7 - Bid Addendum Drawing Corrections.pdf PDF
Atch 1 - Specs V2 of 2 - Manchester - 608-315 Rev 2025-06-24.pdf PDF
36C77625B0024 0001.docx DOCX document
Attachment 9 - Brand Name JA - Manchester Redacted - 608-315.pdf PDF
Attachment 3 - Site Visit Instructions - Manchester - 608-315.pdf PDF
Attachment 1 - Limitations on Subcontracting - Construction - 608-315.docx DOCX document
Attachment 5 - Specifications V2 of 2 - Manchester - 608-315.pdf PDF
36C77625B0024_1.docx DOCX document
Attachment 6 - Drawings Part 1 of 3 - Manchester - 608-315.pdf PDF
Attachment 8 - Drawings Part 3 of 3 - Manchester - 608-315.pdf PDF
Attachment 4 - Specifications V1 of 2 - Manchester - 608-315.pdf PDF
Attachment 2 - DBA Wage Rates - Manchester - 608-315 - NH20250021 03.14.2025.pdf PDF
Attachment 7 - Drawings Part 2 of 3 - Manchester - 608-315.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL QUESTIONS AND

SOLICITATION #:
36C77625B0024
RESPONSES TRACKING SHEET
PROJECT TITLE:
Construct Specialty Care Building, Manchester
1
Please provide the blast requirements for this project to properly quote this project. Could you also please provide the threat magnitude.
The Mission Critical Design will be 50ft Set-Back with Design Threat W1 and GP-2.
2
· Description of what “Modified Mission Critical Design per VA” is and if or how it would affect the glass & aluminum package?

· Standoff distances and weights for our use in determining the correct aluminum and glass systems, reinforcing, attachment and glass make up.

· We believe (expecting these questions back from Kawneer Eng) the W1, W2 and GP1 & GP2 references in the SF spec should be further defined to one of those and not all four?

See below (snapshots) and attached with pertinent items highlighted.

:Structural Page

Storefront Spec:

The Mission Critical Design will be 50ft Set-Back with Design Threat W1 and GP-2.

3
Large storefront window marked as # D on page A2-2.3. Comment per manufacturer - window wall is much too large for 2 x 4 ½ storefront metal. Please advise as to what CW system and requirements are.
Spray applied fireproofing required. (no intumescent paint required)
4
Please clarify locations of the glazing types on the door and storefront schedule.

a. The door schedule clearly marks GL-1 filming but also calls out G glass type with no reference.

b. The storefront schedule has ¼” glazing details for the exterior frames Door schedule refers to storefront elevations on sheet A2-2.3. Hardware is listed as set 6

5
Frame D is beyond the sizing limit for storefront framing. Is it your intention to use a curtainwall system for this span that will pass the wind speeds provided?

i. Please provide a detail or part # for the 2-1/2” x 12” extended covers for this frame.

Curtainwall is required for window type “D”. Specifications and revised details to be provided

6
Please clarify the description of what “Modified Mission Critical Design per VA” is and if or how it would affect the glass & aluminum package?
Glazing type marks refer to descriptions provided in specification section 08 80 00. Revised door schedule and Glazing Elevations have been provided. (Dated 8-21-2025).

Exterior glazing will be 1” insulated. Frames will need to have 1” glazing pockets. The ¼” glazing details are for interior borrowed lights only.

7
Please clarify the standoff distances and weights for our use in determining the correct aluminum and glass systems, reinforcing, attachment and glass make up.
(see reply above)
8
In section 08 41 13 Aluminum Framed Entrances and Storefronts 2.2 materials 4-a is calling for anodized finish but 2.7-A is calling for a 3 coat metallic system. Please confirm which one is correct.
Use 3-coat Metallic System
9
Drawing page A2-2.3 frame D is calling out for Vertical Mullion Cover Fins can further detail be provided. Manufacturers do not recommend additional fins on a impact application.
See Revised A2-2.3 Dated 8-21-2025.
10
Drawing page A2-2.3 frame type D is calling for Structurally glazed horizontals. Storefront systems don’t have a structurally glazed horizontal. Plus I’m unable to get the storefront to pass structural analysis. Would a 2 1/2" x 6” curtain wall system be acceptable.
See Revised A2-2.3 Dated 8-21-2025.
11
Please provide the blast requirements for this project to properly quote this project. Could you also please provide the threat magnitude.
The Mission Critical Design will be 50ft Set-Back with Design Threat W1 and GP-2.