Atch 1 - Tech Qs - Manchester 608-315 FINAL.docx

DOCX document 80 KB Posted

Attached to
Y1DB--Construct Specialty Care Building - Manchester Minor Project 608-315
Solicitation number
36C77625B0024
Issued by

About this file

This document is a Technical Questions and Solicitation Responses Tracking Sheet for VA Project 36C77625B0024, a Specialty Care Building construction project in Manchester, New Hampshire. The solicitation involves constructing a new building with specific technical requirements, including underground utility work, piping installations, and specialized staffing provisions. Key details include a firm bid response date of August 14, 2025, and requirements for a full-time Site Safety and Health Officer (SSHO) and Contractor Quality Control (CQC) System Manager.

Critical project specifications include using AISC-certified structural steel, providing window shades, performing radiographic testing on select welds, and managing underground utility work with no specific trench length restrictions. The VA will provide water for hydrostatic testing, allow sewer drain discharge, and has already contracted DAV Energy Solutions as the commissioning agent. The project requires coordination with an active medical center campus, with contractor access primarily unescorted except in sensitive areas like the main computer room. Johnson Controls is identified as the current Building Automation System vendor, and no known asbestos or contaminated soil is anticipated during construction.

View the file

Other files

File Type Posted
36C77625B0024 0008.docx DOCX document
Attachment 5 - 084413 - Glazed Aluminum Curtain Wall.pdf PDF
Attachment 4 - VAMC_MANCHESTER_A5-2.1 - 608-315.pdf PDF
Attachment 1 - Virtual Bid Opening Updated - Manchester.pdf PDF
Attachment 2 - Tech Qs - Manchester 618-315 2025-08-22 responses.docx DOCX document
36C77625B0024 0008.docx DOCX document
Attachment 3 - VAMC_MANCHESTER_A2-2.3 - 608-315.pdf PDF
S06 - Atch 1 - Virtual Bid Opening Updated 8.19.25 - Manchester.pdf PDF
36C77625B0024 0007.docx DOCX document
S06 - Atch 1 - Tech Qs - Manchester 618-315 NEW 8.13.2025.docx DOCX document
S06 - Atch 2 - Panel DP nameplate - 608-315.jpg JPG image
36C77625B0024 0006.docx DOCX document
Atch 1 - Virtual Bid Opening UPDATED - Manchester NH 608-315.pdf PDF
36C77625B0024 0005.docx DOCX document
S06 - Atch 4 - Bid Addendum Bldg 1 Basement Floor Plan.pdf PDF
S06 - Atch 1 - Tech Qs - Manchester 618-315 8.7.2025.docx DOCX document
36C77625B0024 0004.docx DOCX document
S06 - Atch 2 - Q60 Response Select Drawings from Existing Building Construction.pdf PDF
S06 - Atch 6 - 122400 - Window Shades.pdf PDF
S06 - Atch 5 - Bid Addendum Bldg 1 First Floor Plan.pdf PDF
S06 - Atch 3 - Bid Addendum 1 Drawing Corrections.pdf PDF
36C77625B0024 0003.docx DOCX document
Atch 2 - 087100 Door Hardware 2025-07-31.pdf PDF
Atch 1 - Tech Qs - Manchester 608-315 07252025.docx DOCX document
Atch 6 - Bid Addendum Bldg 1 First Floor Plan.pdf PDF
Atch 2 - Site Visit Agenda - Manchester NH 608-315.pdf PDF
Atch 8 - 122400 - Window Shades.pdf PDF
Atch 3 - Site Visit Sign-In Sheet - Manchester NH 608-315.pdf PDF
Atch 4 - Virtual Bid Opening Information - Manchester NH 608-315.pdf PDF
36C77625B0024 0002.docx DOCX document
Atch 5 - Bid Addendum Bldg 1 Basement Floor Plan.pdf PDF
Atch 7 - Bid Addendum Drawing Corrections.pdf PDF
Atch 1 - Specs V2 of 2 - Manchester - 608-315 Rev 2025-06-24.pdf PDF
36C77625B0024 0001.docx DOCX document
Attachment 9 - Brand Name JA - Manchester Redacted - 608-315.pdf PDF
Attachment 3 - Site Visit Instructions - Manchester - 608-315.pdf PDF
Attachment 1 - Limitations on Subcontracting - Construction - 608-315.docx DOCX document
Attachment 5 - Specifications V2 of 2 - Manchester - 608-315.pdf PDF
36C77625B0024_1.docx DOCX document
Attachment 6 - Drawings Part 1 of 3 - Manchester - 608-315.pdf PDF
Attachment 8 - Drawings Part 3 of 3 - Manchester - 608-315.pdf PDF
Attachment 4 - Specifications V1 of 2 - Manchester - 608-315.pdf PDF
Attachment 2 - DBA Wage Rates - Manchester - 608-315 - NH20250021 03.14.2025.pdf PDF
Attachment 7 - Drawings Part 2 of 3 - Manchester - 608-315.pdf PDF
Show all 44

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TECHNICAL QUESTIONS AND

SOLICITATION #:
36C77625B0024
RESPONSES TRACKING SHEET
PROJECT TITLE:
Construct Specialty Care Building, Manchester
#
CONTRACTOR QUESTION
VA RESPONSE
1
Will the sign-in sheet from site visit be available in addendum?

Site visit sign-in sheet attached to this amendment (Amendment 0002).

2
Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?

The site superintendent may not be a dual hat to cover the requirements of SSHO, as required by Specification 01 35 26.

3
If no to the question above, will the SSHO need to be full-time for this project?

The SSHO will need to be full-time for this project, as required by Specification 01 35 26. MH3-0.0 shows correct entry to Specialty Care Building. Underground steam piping shall enter building directly into basement pump room. C-5.0 & MS2-0.2 seem to show approximately same entry point to Boiler Plant Building. C-5.0 defers to mechanical drawings for more information. MS2-0.2 shows indoor tie in point relative to existing piping and equipment in the boiler plant.

4
Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC?

The superintendent may be a dual hat to cover the requirement for a Contractor Quality Control System Manager, as required by Spec 01 45 00.

Replace Specification 01 45 00, paragraph 3.4.B with the following: “CQC System Manager: Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matter for the Contractor. The CQC System Manager is required to have at least 5 years construction experience on construction similar to the scope of this Contract. The CQC System Manager is on the site at all times during construction and is employed by the General Contractor. Identify in the plan an alternate to serve in the event of the CQC System Manager’s absence. The requirements for the alternate are the same as the CQC System Manager.”

Remove Specification 01 45 00 paragraph 3.4.C in its entirety.

5
If no to the question above, will the QA/QC need to be full time for this project?

N/A, see response to Question 4.

6
Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC?

No. See responses to Questions 2-4 above.

7
Please provide the latest wage determination for this project’s county.

Reference Attachment 2 – DBA Wage Rates – Manchester – 608-315 – NH20250021 03.14.2025 uploaded to SAM.gov on June 30, 2025.

8
Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation?

The applicable wage determination will be issued as part of the contract. Any changes to the effective wage determination will be made via an amendment/modification to the IFB/contract.

9
Is there a plan on the drawings that identify the deducts? If, yes please explain what it is.

Deduct Alternates are listed in Spec 01 00 00. Some deduct alternates have drawing mark-ups attached to Spec 01 00 00. Revised drawings will be provided for deduct alternates taken, if needed.

10
Who is responsible for contracting the commissioning agent?

The VA has already contracted a commissioning agent. DAV Energy Solutions is providing the commissioning for this project.

11
Will shutdowns be required to be done during off hours or weekends?

Shutdown are required to be performed on off hours, which is outside the hours of 7am – 4:30pm, Monday through Friday.

12
Will hydrostatic testing be sufficient on all pipe welds or will x-ray be required?

Radiographic examination/testing is required for some of the work of this project, refer to the specifications for more details.

Mechanical Piping. See Spec 23 21 13 3-5 Leak Testing Above Ground Piping. X-Ray Not Required.

13
If X-ray is required, what percentage of welds and who will be responsible for the cost of testing?

Refer to the specifications for the percentage of welds that require radiographic examination/testing. The contractor is responsible for the cost of the testing.

14
If hydrostatic testing is required will the water necessary for hydrostatic testing of piping systems be provided by the facility?

Yes, water will be provided by the facility for hydrostatic testing.

15
Can discharge water from hydrostatic testing be allowed to go into sewer drains or will the contractor need to provide a frac tank?

Discharge water from hydrostatic testing is allowed to go into the sewer drains.

16
Please confirm if there is assumed asbestos on any piping that is to be removed whether underground or within manholes or buildings?

There are no known or assumed asbestos-containing materials impacted by this project. If the Contractor encounters any material that they suspect to be asbestos-containing, they shall notify the Contracting Officer’s Representative immediately and shall not disturb the material without further direction by the VA.

17
Will any existing glycol be required to be removed and disposed of by the contractor? If so, can the total volume of glycol be provided?

No existing equipment containing glycol is expected to be impacted by this project. If glycol removal is required as part of installation of the new equipment called for in the drawings and specifications, the contractor will be responsible for removal and disposal.

18
Who is the vendor or contractor currently servicing and maintaining the Building Automation System or Temperature Controls System?

Johnson Controls.

19
RFI, Specification 33 63 00, 2.2D: Would a thermally efficient equivalent thickness of Aerogel/Pyrogel insulation be acceptable so long as its thickness meets or exceeds the thermal performance for that of the specified insulation types?

Specification 336300 – 2.2D lays out the requirements for the pipe insulation. The proposed product would need to be submitted with information showing that it meets the minimum requirements.

20
RFI, Drawing C-5.0: The building entry locations as shown on Drawing C-5.0 for the underground 6”HPS and 3”PC piping are not coordinated with those shown on Drawings MS2-0.2 and MH3-0.0; which drawings depict the correct locations?

MH3-0.0 shows correct entry to Specialty Care Building. Underground steam piping shall enter building directly into basement pump room. C-5.0 & MS2-0.2 seem to show approximately same entry point to Boiler Plant Building. C-5.0 defers to mechanical drawings for more information. MS2-0.2 shows indoor tie in point relative to existing piping and equipment in the boiler plant.

21
With regards to underground utility work how much open trenching be allowed at a time?

There is not a limit to how much open trenching is allowed, provided that all applicable safety requirements are met. Note that the contractor is required to follow the medical center’s Excavation Management Standard Operating Procedure (attached to Spec 01 35 26), which requires that open excavations be backfilled as soon as possible.

22
After backfilling, topsoil and seed have been applied who is responsible for watering? If the contractor is responsible will water be provided by the facility?

Contractor is responsible for watering in accordance with the specifications. Water will be provided by the facility from existing spigots.

23
On all underground utility work please confirm if excavated material is acceptable for re-use as backfill?

Specifications define what unacceptable soils. Once excavated the CM or Geotechnical Engineer can determine If the material is approved to be re-used as backfill. Costs for replacing unacceptable soils should be carried as part of the base cost.

24
Please confirm if the contractor is responsible for any rock removal that is encountered. If so, what is the assumed elevations and quantity of rock material?

The contractor is responsible for rock/ledge removal as detailed in the contract documents. The drawings specify the quantities of rock/ledge removal to include in the bid. Drawings C-3.0 and S0-1.0 specifically provide quantities to be included in the bid. The Geotechnical Engineering Report is provided as Appendix 2 in the specifications (located near the front of the specification Volume 1).

25
Please confirm if a unit price can be established for rock removal as opposed to carrying in bid?

Rock removal shall be carried in the bid. The firm fixed price contract type does not allow for unit prices. Please see the response to Question 24 for more information on where to find rock removal quantities in the bid documents.

26
If an extreme amount of rock is encountered/removed, please confirm if extra time will be added to the contract completion date?

See the response to Question 24 for the amount of rock/ledge removal to be included in the bid. No extra time will be added to the contract completion date if the amount of rock/ledge removal is less than or equal to the amount required to be included in the bid. If additional rock/ledge removal is required, a contract modification will be negotiated between the VA and the Contractor.

27
Please confirm if there is a separate staging area onsite for fill material to be stockpiled for re-use?

A separate staging area can be provided on the campus. The Contractor will be required to secure the area and to provide appropriate storm water controls for the stockpile.

28
Please confirm if an onsite arborist is required for any tree removal or tree protection?

An arborist is not required.

29
Please advise if the site contains any contaminated soil that needs to be removed.

There is no known contaminated soil to be disturbed as part of this project.

30
Please confirm if we will be allowed to keep a locked storage container or conex box within the grounds.

The contractor will be allowed to keep a locked storage container or conex box on site at a location approved by the VA.

31
Will a guard / escort be required at all work areas including but not limited to buildings, outside areas?

No guard is required. An escort will be required at all times when working the MDF room (the main computer room) and if work is required in other highly sensitive areas. For the most part, however, the contractor is allowed to work on the campus with contractor badges without an escort. The contractor shall schedule work in active areas of the medical center with the COR in advance. A facility service employee is required to be at the facility any time the contractor is working, but is not required to continually escort the contractor.

32
To allow sufficient time to review responses and prepare our bid we kindly request that you please extend the bid date.

The bid response date will NOT be extended and remains August 14, 2025.

33
The finishes note Treads/riser with smooth profile. A smooth profile is not available in treads/risers. Is there to be a replacement/substitute?

Use Hammered Tread/Riser (HNTR)

34
The Patcraft LVT flooring has been discontinued. Will there be a substitute?

The Patcraft flooring was provided as a basis of design. The contractor may propose an equivalent flooring meeting the specification.

35
Can the AISC certification for the structural steel fabrication and installation be waived?

No, the AISC certification will not be waived.

36
Are any window treatments or roller shades to be provided? On Drawing Number ID-1.0, in the Miscellaneous Finish Notes, it states the specs for roller shades, but then it also says window treatments shall be owner furnished. Please clarify.

Window shades to be provided and installed by the contractor. See attached spec section 12 24 00 Window Shades.

See attached mark ups to drawings SE6-0.1, T2-1.1, and T6-0.1.

Drawings of the Basement and First Floor of the existing Building 1 that the addition will attach to are provided for reference.

image1.png image2.jpeg