Atch 1 - PreBid RFIs 7.24.2025.xlsx
XLSX spreadsheet 60 KB Posted
- Attached to
- Z2DZ--EHRM Infrastructure Upgrades Dublin, GA Project 557-22-700 Federal contract opportunity
- Solicitation number
- 36C77625B0013
About this file
This file is a comprehensive Request for Information (RFI) document containing 350 numbered questions and responses related to the Dublin VA Medical Center's EHRM (Electronic Health Record Modernization) Infrastructure Upgrades project. The project involves extensive telecommunications room (TR) renovations across multiple buildings, including network infrastructure upgrades, data cabling replacement, security system enhancements, and complex infection control requirements.
Key technical scope includes installing new data drops, replacing existing cabling, upgrading video management and access control systems, and implementing stringent infection control measures. The project spans approximately 30 buildings with multiple telecom rooms, requiring detailed coordination with VA stakeholders. Critical technical specifications include using Avigilon video management system (Version 7.14.16.14), Tyco CCURE-9000 access control system, HID Signo card readers, and Cat6A cabling. The project involves complex ICRA (Infection Control Risk Assessment) protocols, with work requiring after-hours access in sensitive areas like operating rooms, and necessitating specialized containment and negative air pressure management. The solicitation is issued by the Department of Veterans Affairs Technology Acquisition Center in Austin, with the contract number 36C77625B0013.
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| RFI # | Question | Response |
| 1 | “According to the specs, the VA seems to be in charge of hiring the Commissioning Agent: |
C. Members Appointed by VA:
1. Commissioning Agent: The designated person, company, or entity that plans, schedules, and coordinates the commissioning team to implement the commissioning process. The VA will engage the CxA under a separate contract.
The VA has no method to hire commission firms directly. They are either hired by the design firm or the contractor. This leaves a big gap in the completion of the project. Please send an RFI asking who the Cx firm is that has been contracted by the VA.”
Commissioning firm to be hired by A/E. Commissioning contract has yet to be awarded.
Commissioning plan will be finalized after award. Confirmed commissioning will be limited to new work only related to power, cooling and data testing. Startup requirements for these items are detailed in the individual specification sections
| 2 | Please advise on deck height and floor to floor heights in each building. | Bid typical floor to floor between 14'-0" and 15'-0" Deck height 13'-7" to 14'-7" in height. |
| 3 | Please advise on deck/floor construction type and thickness at each building. | For bidding assume cast in place concrete 5" thick. |
| 4 | Please provide a complete set of as-builts for all work areas. | That's not something we can provide to all builders for security reasons. |
| 5 | Please advise who is responsible for terminal cleaning. | After completion of the work, the GC is expected to clean the area thoroughly. The VA EMS staff will conduct a terminal clean in patient and/or sterile areas. |
| 6 | Please advise if the Project Superintendent can serve as a "dual hat" as the Quality Control Manager (QCM) on this project. | Yes, the project superintendent can serve as the QCM. However, one person cannot serve more than two roles. |
| 7 | Please advise if the Project Superintendent can serve as a "dual hat" as the Site Safety and Health Officer (SSHO) on this project. | Yes, the project superintendent can serve as the SHO. However, one person cannot serve more than two roles. |
| 8 | Please advise who the existing manufacturer of the Fire Alarm system. | The existing fire alarm system is Notifier. |
| 9 | Please provide existing wall finishes and rubber base as noted on Key Note 5.5 in all new rooms. No Information provided on the finish schedule. | Per design intent indicated on drawings flooring subcontractor is responsible for surveying existing conditions and cataloging products to meet match existing directive. Installed base should blend seamlessly with existing to remain. |
| 10 | Please provide specifications for the existing Wall Base in Building 2 Kitchen 102B-3. | Per design intent indicated on drawings flooring subcontractor is responsible for surveying existing conditions and cataloging products to meet match existing directive. Installed base should blend seamlessly with existing to remain. |
| 11 | Please provide specifications for the existing Wall Base in Building 2 Nourishment Prep 102C-2. | Per design intent indicated on drawings flooring subcontractor is responsible for surveying existing conditions and cataloging products to meet match existing directive. Installed base should blend seamlessly with existing to remain. |
| 12 | Please provide the existing Floor finish in order to patch flooring as per Note 2.2. and Note 5.14 in the following rooms: TR BM123A-2, 102C-2, BM101-3, 112-3, 218-3, RCC102R, CR22-6, 172-8, BM101-11, BM103-12, 117-12, 231-12, CR21-12, 142-13, 001-13, BM104-14, G-A-14, 200-14, B11-16, 110.17, 216-19, 104-26. | Per design intent indicated on drawings flooring subcontractor is responsible for surveying existing conditions and cataloging products to meet match existing directive. Installed floor should blend seamlessly with existing to remain. |
| 13 | Please provide Corner Guard Specifications for the following rooms. Note 5.3 is calling for Corner Guards on the floor plans but no additional information was provided on the finish schedule: 104-2, 112A-3, C137-5, 172C-8, 210A-9, BM107A-10, BM101A-11, BM103A-12, 117A-12, BM104A-14, 111-17, 216A-19, 106-26. | Wall protection subcontractor is responsible for surveying and providing best match suggestions as they relate to dimensions, material, style, profile, and all other associated components required for a complete installation. |
| 14 | Please provide New Wall Type as per Note 1.1 in Room 232-14 since it is not defined on Sheet A-506. No information was provided on plans. | For bidding, assume Type M3.0 |
| 15 | Please provide existing Civil as-built plans for all areas included in the scope of work. | Please refer to the Civil sheets (Note 4). Additional civil sheets cannot be posted due to security concerns. |
| 16 | Provide details for Wall Type F4.0 noted in Room TR101A-14 on Sheet 14.A-411 since it was defined by partition type on Sheet A-506. | Stud size is 4" metal stud with 1 layer of 5/8" Type X gyp on one side. |
| 17 | The following Mini Split systems appear on the plans but not found on the Mechanical Schedule. Please review and confirm: 2-SS-104-2, 2-SS-212-C, 10-SS-BM107A, 13-SS-104, 14-SS-101A-14, 28-SS-BM102B, 28-CU-BM102B, 29-CU-113A, 29-SS-113A, 86-SS-136, 89-CU-1216. | All but 1 of the units are in the schedule (29-SS-113A). The locations in the schedule and the plan location are how to align the plan tag/mark. Some Marks do not align with the room number, some are typos, and some stem from last minute room changes. |
| 18 | Please advise if we are to use the Asbestos quantities and information as provided in Specification Section 02 82 13.19-1. If not, please provide an Asbestos Survey. | For bidding, use the asbestos quantities and information as provided in Specifications 028213.19 and 028213.13. Also refer to Specification 028213.13, Part 1.2 for variations in quantity. |
| 19 | Please advise if we are to use the Asbestos quantities and information provided on Spec Section 02 82 13.13-1. If not please provide an Asbestos Survey. | For bidding, assume 500 feet of (<2 inches) diameter pipe insulation 500 linear feet of 2 inches - 6 inches diameter pipe insulation. 500 feet of > 6 inches diameter pipe insulation 500 feet fitting, saddle blocks, valves, T's or other mechanical appurtenances 2 inches - 6 inches in diameter other. |
| 20 | Please provide Asbestos information regarding the Ceiling in Office 202-4. As per the plan notes there may be Asbestos in the ceiling but no information was provided in the specifications. | For bidding, assume the entire ceiling is hot and follow asbestos abatement procedures in the specs. |
| 21 | Per Specification 02 41 00 Demolition, Clause 1.2 Related Work makes reference to Section 02 82 11 for the Traditional Asbestos removal but this section is not included in the Specifications. Please review and advise. | Please refer to 02 82 13.19 AsbTileMasticAbate, 028213.13 GlovebagAsbAbate, and 028333.13 Lead Based Paint for abatement requirements. |
| 22 | Please confirm who is the existing manufacturer of the current Video Management System. | Avigilon is the current VMS manufacturer. |
| 23 | Please confirm on what existing software version is the current video management system operating. | Version 7.14.16.14 |
| 24 | Please confirm what is desired frame rate, days of storage, % of Motion, on the Video Storage. | Minimum 30 frames per second, 30 days of storage, and minimum 25% motion detection - field adjustable. |
| 25 | Please confirm on what existing software version is the current video management system operating. | Please refer to RFI #23 |
| 26 | Please confirm if the cameras are to be 2MP pan/tilt/zoom or a fixed dome. | Fixed Dome minimum 5 MP. |
| 27 | Please confirm if there is there a main Video Server or are NVR’s in use. | NVRs are in use |
| 28 | Please confirm what is the preferred camera brand, megapixel, stationary, PTZ, VF. | Avigilon, 5 MP minimum, fixed. |
| 29 | Please confirm the VA will provide all Network Switches. | VA will provide all necessary switches to be installed in network racks in TRs, but will NOT provide switches for systems like SSTV, PACS, etc. |
| 30 | Please confirm if there is an existing SSA in place for VIDEO, and if so, who is the vendor servicing the SSA. | Currently Hurtvet (subcontractor: Convirgent) holds the contract. VA stakeholders report an excellent working relationship with this sub. The contract is about to expire (90 days left) and a new one is out for bid. This contract includes services for cameras, card readers, and intrusion detection system. |
| 31 | Please confirm if there is an existing interface between VIDEO & Access Control. | No interface exists. |
| 32 | Please confirm who is the existing Access Control Manufacturer. | Tyco CCURE-9000 |
| 33 | Please confirm if the VA wants to expand the current manufacturer for Access controls. | Expand access controls only as needed for new TRs. |
| 34 | Please confirm what is the existing software version of the access control system operating. | Version 3.00.3 |
| 35 | Please confirm how many card readers are currently being operated or in use. | 125 readers throughout the facility |
| 36 | Please confirm if we are we expected to support version updates as part of our scope of work. | Contractor is expected to integrate new components into existing infrastructure |
| 37 | Please confirm there are sufficient Access Control Software licenses to support the new doors. | No additional licenses are available. Contractor to purchase any additional licenses required. |
| 38 | Please confirm if there is an existing integration between the access control and CCTV systems and if so, what is the base platform (Access Control or Video) that operates both. | No integration exists. |
| 39 | Please confirm if there is an existing SSA in place for Access Control, and if so, who is the vendor servicing it. | Currently Hurtvet (subcontractor: Convirgent) holds the contract. VA stakeholders report an excellent working relationship with this sub. The contract is about to expire (90 days left) and a new one is out for bid. This contract includes services for cameras, card readers, and intrusion detection system. |
| 40 | Please confirm if there are existing software licenses available from the VA that can be used for the new reader/ Controllers. | No additional licenses are available. Contractor to purchase any additional licenses required. |
| 41 | Please confirm if the new access control system needs to be FICAM Compliant and if so, is there a current FICAM License. | All components need to support a FICAM compliant system. FICAM License does not need to be included in the bid for this project. |
| 42 | Please confirm if CESIP Certification is required. | Yes, it is required . |
| 43 | Please confirm who is the desired manufacturer for the new card readers. | HID Signo card readers |
| 44 | Please confirm the Telecom Room electronics that the VA will provide, if any (i.e network switches, UPS,..) | The VA will only provide Network Switches for the TR Channel Racks. All other equipment shall be provided by the contractor. |
| 45 | Per Sheet A-001, Phasing Note 1, please provide additional information in general terms the after hours and weekend requirements for each of the three (3) phases noted including any downtime required between each phase. | Please refer to G-007 for after hours work. |
| 46 | Please confirm that although work must be completed in the phased sequence specified on Sheet A-001, Phasing Note 1, activities for each phase can occur concurrently. For example, activities required to construct the new TR rooms can occur at the same time work is in progress to install new infrastructure (duct banks, fiber backbone extension, new headend equipment)? Similarly, work to install new cabling from new TR rooms to individual data/comm receptacles can be performed at the same time work is in progress to complete the TR rooms? | Yes, with the condition that current phase of TRs completed before moving to the next phase of TRs. |
| 47 | Please confirm the use of flexible conduit and cut-in boxes will be permitted for the installation of new cabling in vertical partitions to serve new data/comm receptacles? | Yes. |
| 48 | Please confirm the use of surface mounted conduit and j-boxes will be permitted for the installation of new cabling to serve new data/comm receptacles where the existing walls are constructed of concrete masonary units or similar? | Yes. |
| 49 | During the site visit, the statement was made that the existing data/comm receptacles must remain in operation until the new data/comm receptacles are installed, tested, and commissioned. Will the VA consider coordinated, short duration service interruptions over a single after-hours shift to facilitate utilization of existing in-wall conduits and j-boxes where practical? | Acceptable as temporary solution. |
| 50 | During the site visit, the statement was made that some additional underground and building entry work should be anticipated to connect new fiber circuitry to buildings not shown on the current Civil plans. Please identify all locations where all such work is needed to complete the desired improvements and provide details for new building points of entry. | Bid all work shown on 00.TS101 and reference details in the key notes and on other detail sheets which show how to enter buildings. |
| 51 | During the site visit, the statement was made that a maximum of six TR rooms could be activated at one time. Please confirm this statement was referring to actual transition of services from the existing to new communication system and that work may progress on multiple TR rooms in multiple buildings simultaneously. | Please refer to G-006 Key phasing note B. |
| 52 | VA please confirm that a contractor’s office trailer and laydown yard can be provided and installed in a location on campus approved by the COR. This is not shown in the drawings. | Yes, there will be a laydown area for contractor. |
| 53 | The representative for Apogee mentioned at the site visit that there were tables within the specifications that gave further ACM information. These tables could not be located within the specifications. Please provide these tables. | Refer to spec Section 02 82 13.13, Part 1.1 and Section 02 82 13.19, Part 1.1. |
| 54 | Architectural drawing note B found on Sheet G-006 states that a limited amount of “(4) four TRs can be demolished and modified at one time and that rooms must be completed and approved by the COR prior to proceeding to work on additional rooms.” Given the complexity of the work and only being to work in 6 rooms concurrently within, and proposed tie-in locations and quantifications, the 740 Period of Performance might not be able to be met. Would the VA consider extending the total PoP to allow for proper coordination for the work to be performed and completed? | No, plan to be limited to 4 TRs as any given time. Time extensions will be evaluated on a case by case basis. |
| 55 | Are the existing elevators available to use during this project? | There is one freight elevator and multiple passenger elevators. Freight elevator is located at the loading dock (bldg. 2). |
| 56 | The drawings reflect the new Technology Systems (Data Drops) to be routed in the main corridors at each building. The drawings do not show the current ceiling materials that will be affected (ie ACT, GWB, Plaster, etc…). Can the existing ceiling information be provided to price accordingly? | For bidding purposes, assume all corridor ceilings are ACT. For rooms where there is existing hard ceilings, emphasis should be given to re-using conduits from corridor. |
| 57 | Spec Section 2715 10, (PDF Page 1142) New Cable Distribution by TR chart ends with information for Building 19 – Level A for TR117. Information for Building 19 Level B Shown on Sheet 19.G-101 is missing. Please provide the information or confirm that Building 19 Level B is not in SOW. | Bid all buildings in the drawings and the specifications. See sheet notes for work to be done. Many buildings require disconnecting existing cables and re-terminating cables on new patch panels in new Channel Racks. |
| 58 | New Cable Distribution by TR chart does not include any new data drop information for Buildings 25, 26, 27, 28, 29, 30, 85, 86, 87, and 89. Please provide the information or confirm that these Buildings are not in SOW. | Buildings 87 and 89 have existing to remain racks and existing to remain cabling. See drawings for scope of work in those buildings. |
Buildings 25, 26, 27, and 29 have existing to remain cabling that are to be disconnected and re-terminated on new patch panels. For bidding purposes, bid the disconnection and re-termination of 480 cables per TR and 96 cables per TE.
Buildings 28, 30, and 86 have existing cabling to be removed and replaced. Bid the number of cables listed in sheet note J at 80 meters per cable.
| 59 | Due to the large number of RFI’s, will VA provide adequate time (14 days min) to incorporate the RFI answers and move the Bid Date accordingly? | Yes, there will be ample time for contractor's to incorporate answers. |
| 60 | During the site visit, it was mentioned about the Telecom Locations having a “blue tape” pre-installation conference to determine the exact wall and location for each drop listed in Specs chart. Not having the specific wall locations within rooms defined does create more pricing ambiguity and it is almost impossible to quantify correctly. The specific lengths will vary depending on which wall along with the associated cost of installing in a potential fire rated wall, standard wall, exterior perimeter masonry wall, etc… (ie. New Drops are listed in Corridors that can be 80’ to 100’ in length). |
| a. | Can the locations for new Telecom drops be reflected on floor plans? | Bids need to consider the cost variability associated with the placement of devices based on a blue tape survey. | ||
| 61 | During the site visit, a very limited (3 to 4 rooms) locations were viewed. There is a significant amount that will be converted into new TR’s (existing offices, Corridor spaces, conference rooms) and evaluation of those spaces will be important. | Work to be bid is specified within the construction solicitation. No further site visits will be arranged. | ||
| 62 | The ICRA Risk level chart (G-007) lists all the VAMC departments but there is no way to relate this list of departments when viewing the floor plans and location from floor to floor. Can the floor plans reflect the Listed departments boundaries since this will affect ICRA plans and associated cost. | Attachment provided with each department and the ICRA level required for the TR construction. Keep in mind the data drops may require additional IC precautions. For instance, the TR for the endoscopy area is not near the procedure area, but drops need to be made in the procedure area. All patient areas will have a minimum ICRA of a III and a maximum of a level IV. | ||
| 63 | General specifications question: Several sections of the systems specs include testing, cleaning, commissioning, etc. that do not appear to apply to the scope of work required for this contract. One example would be specification 22 05 11 “Common Work Results for Plumbing” appears to include complete flushing and disinfecting of the entire plumbing system as part of the work. This could be very costly to accomplish. With the limited scope of work required by this contract for this and similar systems, within each building, please confirm that testing described within the specifications only relates directly to the affected work. | Correct, this would only apply to impacted areas due to the work completed. | ||
| 64 | Spec section 01 00 00, Par. 1.4.F.2 appears to include a limit of parking permits for contractors to 2-5 permits. VA please confirm if more parking permits could be added for contractors during construction if needed. | More permits can be issued if the COR determines the need is necessary. | ||
| 65 | Spec section 01 00 00, Par. 1.5.J requires a chain-link construction fence around the work areas indicated on the drawings. The work for this contract appears to cover mostly interior work within multiple hospital buildings. The exterior work includes working with existing and new ductbank across the VA Hospital Campus and could jeopardize egress for the hospital. VA please confirm extent of construction fencing (location and approximate linear feet) as it relates to both interior and exterior work. This information is important in allowing bidders to provide accurate pricing for this work. | Chainlink fences will only be required for sections of work area that are left unattended between shifts or as a measure to reroute pedestrian traffic and should not be used in a way that blocks traffic. | ||
| 66 | Spec section 01 00 00, Par. 1.14 lists requirements for a Resident Engineer’s Field Office. The spec requires the contractor to provide a temporary field office where shown on the drawings. It does not appear this office is shown on the drawings. VA please confirm that the provision and installation of a temporary Resident Engineer’s Field Office is NOT required as part of this work. | Resident engineers office will not be required | ||
| 67 | Spec section 01 32 16.15, Par. 1.13 indicates phasing for the project. VA please confirm the phasing for this project listed is correct as it relates to head end equipment, redundancy, new TR room locations, HVAC work, cabling distribution and will not affect the any other portion of the VAMC. | This is a general overview of phasing indicating the progression of each TR. For overall specific phasing requirements see the drawing set. | ||
| 68 | Section 01 33 23, Par. 1.2.D appears to require samples be submitted to the VA for approval. This also includes mock-ups for verification. VA please confirm the extent of required samples. This project appears to include data cabling, conduit, etc. that will be hidden from finished work. Please confirm samples will only be required for finishes like ceiling tiles, paint, etc. | Limited to finishes indicated on finish schedule shown on A-603 | ||
| 69 | Specification section 01 35 26 references roles and requirements for contractor’s on-site personnel, including SSHO and CP, etc. VA please confirm if the on-site superintendent can have shared duties such as Alternate SSHO or another role on the project. VA please confirm the main SSHO must be a separate individual with no other roles or responsibilities and must be on site at all times throughout the duration of construction. | One person can only be assigned two roles. | ||
| 70 | Specification section 01 91 00, Par. 1.7.B includes a table that indicates a list of the systems to be commissioned as part of this work. The list appears to include work that is not part of this project scope. Please revise the list of commissioned systems to only include those that relate to this project. (i.e. electrical, data, communications, HVAC, etc.) | Commissioning plan will be finalized after award. Confirmed commissioning will be limited to new work only related to power, cooling and data testing. Startup requirements for these items are detailed in the individual specification sections . | ||
| 71 | Specification section 01 91 00, Par. 3.5.D has a list of commissioning tasks for equipment that do not appear to be included as part of the work in this project scope. (i.e. steam pumps, boiler controls, fan coil units, etc.) While some of these types of devices are scheduled to be removed as part of the project scope, none appear to be new. New components are limited to electrical, data, and small stand-alone mini-split HVAC units for each TR. VA please revise the list of required commissioning tasks to only include new equipment that is part of this project. | Commissioning plan will be finalized after award. Confirmed commissioning will be limited to new work only related to power, cooling and data testing. Startup requirements for these items are detailed in the individual specification sections . | ||
| 72 | VA, please confirm that commissioning is required only for the systems that have been installed as part of this work, and that entire building and total systems commissioning is NOT required as part of this work. | Confirmed | ||
| 73 | Please confirm that a CxA commissioning agent will need to be provided by the Contractor only for the systems that are to be commissioned upon previous RFI clarifications. | Confirmed | ||
| 74 | Specification section 02 82 13.13, Par. 1.1.B and spec section 02 82 13.19, Par. 1.1.B states that the quantities listed in the spec are “for information purposes only and the contractor shall satisfy himself as to the actual quantities to be abated.” This will be difficult for contractors to quantify prior to bidding given the limited amount of information provided. Does the VA have previous ACM test reports that can identify locations, quantities, and types of existing ACM that is required to be removed? | Reference the "Dublin EHRM_ACM_Matrix" for comprehensive ACM survey data. Contractors should use the provided quantities for bidding purposes. | ||
| 75 | During abatement on interior closets, negative air containments will be forced to exhaust inside the building. Confirm that this will be allowed so long as air scrubbing/filtering of the exhaust is included as part of the work. | Correct, allowable so long as air scrubbing/filtering of the exhaust is included as part of the work. | ||
| 76 | Spec section 02 82 13 2.3 Monitoring, Inspection and Testing Section States: “Pressure readings with the containment may be omitted if negative pressure Glove bag procedures are used.” VA please confirm this is the case when using glove bag methods due to other sections of the specifications stating that all asbestos abatement must be completed under a fully enclosed negative pressure containment. | Correct, negative pressure and readings are required for this work and asbestos abatement must be completed under a fully enclosed negative pressure containment. | ||
| 77 | Will the VA require the contractor to provide hazardous materials testing to verify locations and quantities of ACM or other hazardous materials to ascertain limits of abatement? | Reference the "Dublin EHRM_ACM_Matrix" for comprehensive ACM survey data. Contractors should use the provided quantities for bidding purposes. | ||
| 78 | If hazardous material testing results indicate additional ACM exists within the work area, will the VA consider this a differing site condition and issue a contract modification to the contractor for the abatement of the additional ACM? | Please refer to RFI # 135. | ||
| 79 | Specification section 02 82 13.13, Par. 1.1.B.1 lists quantifications and totals of 250 lf of existing pipe insulation to be removed as part of the work for this project (other quantities are listed and see to be not edited to reflect SOW). VA please clarify if the amount listed in the section is the total for the entire project. VA confirm if more existing pipe insulation is discovered to contain ACM that needs to be removed to complete the work, that this will be considered a differing site condition, and a contract modification will be issued to the contractor for abatement of the additional ACM. | Disregard. |
Instead, reference the "Dublin EHRM_ACM_Matrix" for comprehensive ACM survey data. Contractors should use the provided quantities for bidding purposes.
80 Specification section 02 82 13.19, Par. 1.1.B.2 lists quantification of 1000 s.f. of existing flooring and mastic to be removed as part of the work for this project. VA please clarify if the amount listed in the section is the total for the entire project. VA confirm if more existing flooring and mastic is discovered to contain ACM that needs to be removed to complete the work, that this will be considered a differing site condition, and a contract modification will be issued to the contractor for abatement of the additional ACM. Disregard.
Instead, reference the "Dublin EHRM_ACM_Matrix" for comprehensive ACM survey data. Contractors should use the provided quantities for bidding purposes.
| 81 | Spec section 06 20 00 Finish Carpentry is included in the project documents and appears to include acoustical wall panel construction. VA please confirm and clarify location and quantification of these components required for this project. If no requirement exists, request VA omit this spec section. | 06 20 00 Finish Carpentry applicable - Please refer to fire-retardant treated plywood in each TR. |
| 82 | Spec section 07 21 13 Thermal Insulation is included in the project documents. VA please confirm and clarify location and quantification of thermal insulation required for this project. If no requirement exists, request VA omit this specification. | Instead, reference the "Dublin EHRM_ACM_Matrix" for comprehensive ACM survey data. Contractors should use the provided quantities for bidding purposes. |
| 83 | Spec section 07 84 00, Par. 1.5 lists requirements for fire stopping materials and installers. VA please confirm that all firestopping must be either installed by a FM Global approved contractor, or a UL qualified firestop certified contractor. | Yes, the fire stop needs to be installed by persons who have completed the required trainings as designated in the specifications. |
| 84 | Please confirm that the contractor is required to obtain the services of a third party independent firestopping inspector. | Yes, the specs call for an inspector. We want to keep this requirement as it will ensure all firestopping has been done correctly. |
| 85 | Spec Section 07 95 13 Expansion Joint Cover Assemblies is included in the project documents. VA please confirm and clarify location and quantification of expansion joint covers required for this project. If no requirement exists, request VA omit this specification. | Spec Section 07 95 13 is applicable to the project. I.e. Telecom Room Floor Plan and New Key Note 7.1 on Sheet 03.A-421. |
| 86 | Spec section 08 11 13, Par. 2.4 includes requirements for hollow metal doors. Door schedule found on sheet A601 does not appear to include any HM doors, only WD doors. | Refer to Door Schedule on Sheet A-601 for door material. |
| 87 | VA please confirm this spec only relates to the HM frames as required and HM doors are not required as part of the work for this project. | Refer to Door Schedule on Sheet A-601 for door material. |
| 88 | Spec Section 08 90 00 Louvers and Vents is included in the project documents. VA please confirm and clarify location and quantification of louvers and vents required for this project. If no requirement exists, request VA omit this specification. | There will be no new louver for this project. Remove spec Section 08 90 00. |
| 89 | Spec section 09 91 00, Par. 1.3.E requires sample paint panels to be submitted for approval. Can the contractor provide manufacturer paint sample swatch color samples to satisfy this requirement? | Yes |
| 90 | Section 09 91 00, Par. 3.13.B requires identification and painting of stencils above ceiling for smoke barriers and fire barriers. VA please confirm that this requirement only applies to new walls erected by this work and that application of stencils to existing walls is not part of this construction contract. | Only stencil new walls |
| 91 | Due to partial wall construction in hallways, please confirm painting unless otherwise noted is to be (3) three coats (prime, body, finish) will be from “seam to seam” or to a change of materials walls are patched and refinished. | The painting scope will vary depending on the area. The overall intent is for new construction and any patching to blend seamlessly with existing conditions. In most cases, this will require painting “seam to seam” or to a logical material transition using three coats (primer, body, finish), unless otherwise noted. Please field-verify conditions and coordinate with design intent to ensure a uniform appearance. |
| 92 | Spec section 21 13 13 Wet-Pipe Sprinkler Systems is included in the project documents. This project appears to only require replacement of selected existing fire sprinkler pipes and limited number of sprinkler heads. Spec section 21 13 13 includes a lot of requirements for new fire sprinkler design shop drawings, etc. that may not be applicable to the work included in the drawings. VA please confirm requirements in spec 21 13 13 and provide revised spec. | Please refer to RFI #95. |
| 93 | Specification section 21 13 13 indicates requirements for a wet pipe fire sprinkler system which also requires submittal of calculations for the work. To provide this with any sort of accuracy, a flow test would need to be performed near the work area(s) at each building or other means of confirming available flow rates to ascertain proper water flow requirements are currently being met and to satisfy flow requirements for the new work. Please if this is a project requirement or can the minor adjustments to existing sprinkler heads be coordinated onsite. If not, please provide as-built drawings for fire protection system plus flow tests. | Please refer to RFI #95. |
| 94 | If the VA cannot provide the required flow tests near the work areas for the fire sprinkler work, will the VA require the contractor to perform this testing? | Flow tests that are not on the annual report will need to be completed by the GC. |
| 95 | Spec section 21 13 13 Wet-Pipe Sprinkler Systems is included in the project documents. This project appears to only require replacement of selected existing fire sprinkler pipes and limited number of sprinkler heads. Spec section 21 13 13 includes a lot of requirements for new fire sprinkler design shop drawings, etc. that may not be applicable to the work included in the drawings. VA please confirm requirements in spec 21 13 13 and provide revised spec. |
Specification section 21 13 13 indicates requirements for a wet pipe fire sprinkler system which also requires submittal of calculations for the work. To provide this with any sort of accuracy, a flow test would need to be performed near the work area(s) at each building or other means of confirming available flow rates to ascertain proper water flow requirements are currently being met and to satisfy flow requirements for the new work. Please if this is a project requirement or can the minor adjustments to existing sprinkler heads be coordinated onsite. If not, please provide as-built drawings for fire protection system plus flow tests.
If the VA cannot provide the required flow tests near the work areas for the fire sprinkler work, will the VA require the contractor to perform this testing?
Owner will provide existing flow test data from recent testing if available. If no recent data exists. Full hydraulic calculations are not required for this limited scope work.
Contractor shall demonstrate through basic calculations that existing system performance is maintained after alterations. Calculations shall verify adequate flow and pressure for new/relocated sprinkler heads.
| 96 | Spec section 27 08 00 Par. 3.3 requires the contractor to provide commissioning for “Public Address & Mass Notification System” as well as “Nurse Call System”. The project drawings do not appear to clearly identify work required for either the MNS or nurse call. VA please confirm that no work (including commissioning) is required for these systems. | No formal commissioning required for these systems. Any affected devices to be tested to ensure they operate with the existing system. | |
| 97 | Spec section 27 15 10, Par. 1.3.C requires the contractor to “pre-survey all spaces prior to installation to ensure that the number of data jacks are sufficient to replace the ones presently in use.” VA please confirm the total number of data jacks and locations are accurately shown in the Cable Distribution By TR within the specification. | Bid the specified number of jacks in the specification | |
| 98 | If the VA requires additional data jacks that are not shown in the Cable Distribution By TR, will the VA consider this a differing site condition and issue a modification to the contractor for the installation of additional data jacks? | Include 5% additional cables and jacks as part of the bid | |
| 99 | Do the existing CAT6A copper drops need to be re-tested when re-termination is required because of TR expansion? | Yes. | |
| 100 | If the existing CAT6A copper cabling is not long enough to reach the new rack location in a TR, how is the contractor to proceed? | It is anticipated that the cables will reach. | |
| 101 | Is testing of any existing CAT6A cables required if they are not moved off patch panels? | No. | |
| 102 | Please confirm all CAT6A-CMP cables shall be tested to 10G ANSI performance installed on this project. | The goal is to achieve 10 GBE over copper. New Copper Horizontal Cable must meet Category 6a performance, TIA-EIA-568-C.2-10, and TSB-155. | |
| 103 | Spec section 28 05 00 lists requirements for contractor personnel. VA please confirm the project superintendent must be a BICSI Certified Commercial Installer Level 1, Level 2, or technician provide oversight of the project. | Yes. | |
| 104 | Please confirm the cable installer must have on staff a Registered Communication Distribution Designer (RCDD) certified by Building Industry Consulting Service International (BICSI). | Yes. | |
| 105 | Please confirm the telecom subcontractor must be a licensed BICSI contractor with a minimum of five (5) years of experience installing and servicing systems of similar scope and complexity. | Yes. | |
| 106 | Please confirm the telecom contractor must submit copies of systems manufacturer certification for all technicians that will be working on site. | Supervisory staff and those doing sign-offs for cable testing and certification must have the required certifications. | |
| 107 | Can the VA provide product information for access controls and system panels in the existing buildings? | Tyco CCURE-9000 | |
| 108 | Can the VA provide the company currently providing and servicing the existing access controls, card readers, door contact switches, exit sensors etc. for the facility? | Currently Hurtvet (subcontractor: Convirgent) holds the contract. VA stakeholders report an excellent working relationship with this sub. The contract is about to expire (90 days left) and a new one is out for bid. This contract includes services for cameras, card readers, and intrusion detection system. | |
| 109 | Will the contractor relocating, handling, or replacing any of the above-mentioned access control devices, etc. be required to hold manufacturer certifications specific to each product? | Yes. | |
| 110 | Will the contractor be required to directly diagnose, troubleshoot, test, and resolve issues using each system’s specific software and hardware, in addition to necessary connectivity and network infrastructure services? | Yes. | |
| 111 | Project drawings do not directly Div. 28 Systems SOW or locations, but project specifications were included in the contract documents. VA please clarify and / or confirm if relocation of the existing nurse call, access controls, video surveillance, and camera devices will be required by this work? | Drawings define what work is to be completed by this contract. | |
| 112 | Spec section 28 05 00 includes requirements for video surveillance, controls, and recording systems. Project drawings do not clearly identify work associated with video surveillance devices, etc. VA please clarify and confirm work requirements and limits for this work and provide revised specification that correlates with the work required for this project. | Drawings define what work is to be completed by this contract. Additionally each TR receives a new camera. | |
| 113 | Spec section 28 05 13 has requirements for fire alarm work. The project drawings do not clearly identify work regarding existing or new fire alarm devices, other than relocation of existing FACP. VA please clarify work requirements for the fire alarm system(s) within each building. | Bid relocation of FACP. | |
| 114 | Can the VA provide the existing Fire Alarm manufacturer? | Notifier is the existing manufacturer | |
| 115 | 64. | Is there an existing Fire Alarm maintenance contractor for the existing facility? | Yes, there is a contract with JCI. The site is working to get a new one established with a notifier certified contractor. New one expected to be established in Oct. 2025 |
| 116 | Will any inner ducts be required to be installed in the outside conduit? | No | |
| 117 | Will the conduit be required to be installed inside of all buildings to support the riser fibers? | Conduit is not required if using armored fiber cable. If conduit is used between floors, UL listed materials must be used to maintain the floor rating. | |
| 118 | Will innerduct or Maxcell be required to be installed in any inside plant conduits being installed for the riser fibers? | Innerduct and maxcell are not required for ISP. | |
| 119 | Can armored fiber be utilized instead of conduit and innerduct for the fiber riser cabinets? | Yes, armored fiber may be used instead of conduit and innerduct. | |
| 120 | Are there any new voice-cabling requirements for new TR’s or floor end stations? | Project documents do not add new dedicated voice cabling to TRs or floor WAOs. Provide structured Cat 6A cabling as shown/spec’d. | |
| 121 | Are all new indoor fiber cables to be plenum armored cables with no innerduct? | Yes. | |
| 122 | Are all new outdoor fiber cables armored indoor/outdoor with no innerducts? | Indoor/Outdoor rated, tight buffered, OS2 rated, armored fiber cables. | |
| 123 | Do any of the existing areas of the hospital need a new building entry pathway for the new fiber back-bone cabling? | Site plans define new exterior pathways. All exterior pathways connecting to buildings will need building entry | |
| 124 | Will the contractor be required to use plenum rated cabling for all areas or can riser rated cabling in non-plenum spaces be utilized? | Riser rated cabling may be used in non-plenum spaces. It is the burden of the division 27 contractor to ensure that the link loss budget minus the total optical fiber link loss (including splices) is greater than 0 to ensure functionality. See TDMM chapter 6 for more information. | |
| 125 | Is the contractor to assume all new cables will require new pathways, and that no existing pathways are scheduled to be reused? | For bidding, assume all pathways will be new. | |
| 126 | Please confirm if cabling in corridors should be run through conduit or in cable tray or “J” hooks? | J-hooks | |
| 127 | Does the VA have extra network equipment (switch gear, routers, UPS’s) to keep the network connected during construction and cut-over? Or can the system have an 8 hour down time? | VA will have approximately 10 extra switches that can be utilized for cutovers. Data drops serving individual rooms can be down for the duration of a shift but all data drops in use must be operable by the end of the shift. | |
| 128 | Sheet G-005 ICRA NOTE 1 states “after each phase, perform tasks stated in note 6A. There does not appear to be a note 6A. Please provide clarification and/or instructions for this task. | Removed this sentence from Note 1. | |
| 129 | Sheet G-005 note E found on drawings requires the contractor to replace ceiling tiles damaged during construction at no extra cost to the GOV. Please confirm this note only applies to existing ceiling tiles that are damaged during construction. | Yes, correct | |
| 130 | Sheet Note A on drawing 01.G-101states “contractor to assume all corridor, stairwell, and elevator walls are fire rated…” Multiple new TR rooms throughout the drawings appear to include new doors in assumed fire rated walls. Door schedule on sheet A-601 only calls out three doors to have a fire rating (106-86 and 106-26, 45min. and BM101-3, 90 min.). VA please revise door schedule to reflect correct fire ratings for other doors that are scheduled to be installed in fire rated walls. | Per discussion with HEFP personnel during many EHRM projects, HEFP has stated new TR doors do not need to be rated. | |
| 131 | Sheet Note I on page 01.G-101 states “fire stop and smoke stop all penetrations throughout rated partitions. Include all partitions discovered unsealed during execution of work.” This will be impossible to quantify and provide an accurate price for the work without surveying all buildings in their entirety. VA please confirm the provided drawings indicating the existing fire rated and smoke rated walls are accurate and pricing should be based off the VA provided information. This information is critical in allowing offerors the opportunity to provide an accurate cost proposal for the work required. VA consider providing a pre-specified s.f. amount for this task. If the s.f. is exceeded, will the VA consider this a differing site condition and issue a modification to the contractor to provide additional smoke and fire stopping? | Sheet Note A stated to assume all corridor, stairwell and elevator walls are fire rated. Refer to engineering drawings for the location of duct and piping penetrations. | |
| 132 | Current bid documents do not designate building construction type or fire ratings for the existing exterior walls. VA please confirm if any exterior walls are to be considered fire rated. This information is requested for each building that is part of this construction contract. | For bidding, assume they are rated. | |
| 133 | Office Demolition Reflected Ceiling Plan on Drawing Sheet 04.A-421states “original plaster @ 9’-1” a.f.f. may be asbestos.” Does the VA have previous test results that confirm the existing ceiling material is ACM? | If the plans indicated the area may contain asbestos, assume the ceiling material is hot and provide costs for abatement. Refer to asbestos matrix provided. | |
| 134 | Will the VA require the contractor to test the existing ceiling material prior to abatement, or should the contractor assume the existing ceiling material is hot and provide costs for abatement? | GC shall test existing ceiling material prior to abatement that is suspected to be hot prior to any other actions. | |
| 135 | If additional areas of hazardous materials are suspected during construction (after contract award), will the VA consider this a differing site condition and issue a modification to the contractor for testing and abatement? | No, for bidding purposes, carry hazardous materials testing for suspected materials; if suspected material is hot account quantities against Dublin EHRM_ACM_Matrix. | |
| 136 | Sheet CD101 indicates two locations plan SE on the page that appear to be existing trees with X’s on them but are not clearly called out to be removed. (15”HW and 12” HW). Sheet CS101shows ‘UGC’ routed along this area. VA please confirm the existing trees on sheet CD101 are to be removed. | Per the legend, X indicates "EXISTING TREE TO BE REMOVED" | |
| 137 | If existing trees are to be removed in RFI response above, will the contractor be required to provide and install new trees in a different location to offset any local tree ordinance quantities? If so, VA please provide requirements. | Project was not subject to local municipality review or permitting. | |
| 138 | Note 1 under Equipment General Notes found on sheet A-001 requires the contractor to remove and relocate all existing furniture, fixtures, and equipment for renovation. VA please confirm this only applies to office furniture, etc. and the removal and relocation of existing medical equipment (i.e. x-ray machines, imaging devices, and other large stationary equipment is NOT the responsibility of the contractor. | The VA has a furniture moving contract for desks, chairs, shelving, etc. The contractor will not be asked to move any large medical equipment. | |
| 139 | Demolition Note 15 on sheet A-001 indicates that “removed and reinstalled items shall be cleaned, repaired, packaged, and transported to temporary storage”. VA please confirm the storage area/facility/location is the responsibility of the VA, not the contractor. | The storage shall be the responsibility of the VA. | |
| 140 | Demolition Note 21 on sheet A-001 requires the contractor to “provide temporary shoring and support for existing construction affected by demolition efforts”. The note further requires the contractor to provide engineered plans for temp shoring that are signed and sealed by a registered engineer. This task will be difficult to quantify without proper information provided by the VA during bidding. VA please provide locations of work areas in question where temporary shoring would be required as well as the existing construction type so this information can be coordinated with a structural engineer and accurate pricing can be provided for this work. | General note, omit if not applicable to this project. | |
| 141 | If the VA cannot provide the information listed above and additional temporary shoring supports and details are required, will the VA consider this a differing site condition and issue a modification for the contractor to obtain the services of a licensed engineer to provide the temporary shoring details and engineering needed to complete the work? | General note, omit if not applicable to this project. | |
| 142 | Demolition note 2.1 on the Architectural drawings state for the contractor to remove the existing flooring. This work will be difficult to quantify given the numerous types of flooring that can be encountered. For bidding purposes, VA please clarify each existing space floor type or confirm that all existing flooring to be removed shall be considered as some type of VCT. | For bidding assume all existing flooring to be some type of VCT. | |
| 143 | Is the contractor to consider all existing flooring and mastic that is to be removed as ACM? | Only as indicated in the specifications and drawings. | |
| 144 | Keyed Note 1.2 on Architectural drawings call for 4x8x3/4” AC FRT plywood backing board along the interior of the new TRs, but do not call out a quantity. VA please confirm quantities of the new FRT plywood or clarify coverage that can be quantified for bidding purposes. | 3/4" thick AC FRT Plywood to be mounted 8" AFF to 8'-8" AFF. See floor plans for dimensions for quantity needed in each TR room. | |
| 145 | Architectural drawings have notes that require removal and/or modification of existing handrails. VA please provide details and dimensions, material, style, profile, etc. of existing handrails to be matched. | Wall protection subcontractor is responsible for surveying and providing best match suggestions as they relate to dimensions, material, style, profile, and all other associated components required for a complete installation. |