This document contains an anticipated construction schedule for a Sterile Processing Service relocation project at the VA Connecticut Healthcare System West Haven Campus. Key tasks in the 560 day schedule include notice to proceed on January 1st, 2024, critical submittals from January 3rd to January 22nd, 2024, mobilization from January 15th to January 19th, 2024, demolition from January 5th to February 1st, 2024, excavation from January 11th to February 7th, 2024, foundations from January 26th to February 14th, 2024, and other construction activities such as HVAC ductwork from March 21st to April 29th, 2024, gypsum wall installation from November 5th to November 19th, 2024, painting from December 13th, 2024 to January 1st, 2025, plumbing fixture installation from January 3rd to January 27th, 2025, and substantial completion planned for June 9th, 2025. The related federal contract opportunity is solicitation number 36C77624R0041 for the Sterile Processing Service Relocation and Renovation Minor project at the VA Connecticut Healthcare System West Haven campus.
View the file
Other files
Show all 44
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Work Days Start Finish
1 Contract Duration 560 days Mon 1/1/24 Fri 7/4/25
2 Notice to Proceed 0 days Mon 1/1/24 Mon 1/1/24
3 Critical Submittals 20 days Wed 1/3/24 Mon 1/22/24
4 Bond 0 days Tue 1/2/24 Tue 1/2/24
5 Mobilization 5 days Mon 1/15/24 Fri 1/19/24
6 Temporary Signage 3 days Tue 1/16/24 Thu 1/18/24
7 Temporary Partitions 5 days Mon 1/15/24 Fri 1/19/24
8 Demolition 28 days Fri 1/5/24 Thu 2/1/24
9 Excavation 28 days Thu 1/11/24 Wed 2/7/24
10 Foundations 20 days Fri 1/26/24 Wed 2/14/24
11 Door Lead Time 30 days Mon 1/22/24 Tue 2/20/24
12 AHU Lead Time 85 days Tue 1/23/24 Mon 4/15/24
13 Roofing Lead Time 19 days Mon 1/22/24 Fri 2/9/24
14 Widows Lead Time 68 days Mon 1/22/24 Thu 3/28/24
15 Plumbing Fixtures Lead Time 20 days Wed 1/24/24 Mon 2/12/24
16 ACM 10-day Notice 10 days Tue 1/30/24 Thu 2/8/24
17 Interior Lighting Lead Time 40 days Mon 1/29/24 Fri 3/8/24
18 Plumbing Fixtures Delivery 13 days Thu 2/8/24 Tue 2/20/24
19 Floor Tile and Mastic Abatement 15 days Tue 2/27/24 Tue 3/12/24
20 Door & Harware Delivery 1 day Tue 3/12/24 Tue 3/12/24
21 Toilet Accessories Delivery 0 days Fri 3/15/24 Fri 3/15/24
22 Door and Wall Protection Delivery 1 day Thu 3/21/24 Thu 3/21/24
23 Interior Lighting Delivery 1 day Thu 3/21/24 Thu 3/21/24
24 Window Delivery 0 days Mon 3/25/24 Mon 3/25/24
25 Exterior Door Delivery 0 days Fri 3/29/24 Fri 3/29/24
26 Exterior Wall Insulation 6 days Wed 3/13/24 Mon 3/18/24
27 Sprinkler - New Piping 20 days Fri 3/15/24 Wed 4/3/24
28 Facility Water Distribution 20 days Fri 3/15/24 Wed 4/3/24
29 HVAC Ductwork 40 days Thu 3/21/24 Mon 4/29/24
30 Raceways & Boxes for Elec. Systems 30 days Tue 4/2/24 Wed 5/1/24
31 Patch Floor After Demolition 10 days Tue 4/2/24 Thu 4/11/24
32 Applied Fireproofing 5 days Mon 4/1/24 Fri 4/5/24
33 Air Terminal Units 40 days Fri 4/5/24 Tue 5/14/24
34 Self-Leveling 10 days Wed 4/17/24 Fri 4/26/24
35 Metal Framing Walls & Corridors 15 days Tue 5/7/24 Tue 5/21/24
36 Facility Sanitary & Vent Piping 20 days Fri 5/10/24 Wed 5/29/24
37 Hollow Metal Frames 40 days Mon 5/13/24 Fri 6/21/24
38 Low-Voltage Electrical Power, Conductors & Cables
35 days Wed 5/29/24 Tue 7/2/24
39 Raceways for Comm Systems 20 days Wed 6/12/24 Mon 7/1/24
40 Exterior Windows Install 36 days Wed 6/19/24 Wed 7/24/24
41 Exterior Entranceways Install 15 days Tue 7/2/24 Tue 7/16/24
42 Metal Framing Walls & Offices 25 days Fri 7/19/24 Mon 8/12/24
43 Firestopping 5 days Mon 8/5/24 Fri 8/9/24
44 Plumbing Rough-In at Slabs 20 days Fri 8/16/24 Wed 9/4/24
45 HVAC Insulation 20 days Mon 9/2/24 Sat 9/21/24
46 Communications Horizontal Cable 30 days Tue 9/3/24 Wed 10/2/24
47 Metal Framing Ceilings 30 days Thu 9/26/24 Fri 10/25/24
48 Plumbing Rough-In at Walls 20 days Wed 10/2/24 Mon 10/21/24
49 Plumbing Insulation 15 days Wed 10/16/24 Wed 10/30/24
50 Wiring Devices 15 days Wed 10/16/24 Wed 10/30/24
51 Panelboards 10 days Mon 11/4/24 Wed 11/13/24
52 Tie-In Elcectric Panels 3 days Tue 11/12/24 Thu 11/14/24
53 Enclosed Switches & Circuit Breakers 5 days Mon 11/11/24 Fri 11/15/24
54 Gypsum Walls Offices 15 days Tue 11/5/24 Tue 11/19/24
55 Gypsum Walls Corridors & Staff 20 days Fri 11/15/24 Wed 12/4/24
56 Ceramic/Porcelain Tile 15 days Mon 11/18/24 Mon 12/2/24
57 ACT Grid 20 days Wed 11/27/24 Mon 12/16/24
58 Access Panels 10 days Wed 12/4/24 Fri 12/13/24
59 Interior Wood Doors 20 days Fri 12/6/24 Wed 12/25/24
60 Resinous Specialty Glazed Coating 20 days Fri 12/13/24 Wed 1/1/25
61 Painting - Prime 20 days Fri 12/13/24 Wed 1/1/25
62 ACT Tile Cutouts 15 days Fri 12/27/24 Fri 1/10/25
63 Sprinkler Drops 20 days Wed 1/1/25 Mon 1/20/25
64 Plumbing Fixtures 25 days Fri 1/3/25 Mon 1/27/25
65 HVAC Outlets & Inlets 20 days Wed 1/15/25 Mon 2/3/25
66 Interior Lighting 15 days Fri 1/24/25 Fri 2/7/25
67 Integrated Door Assemblies 20 days Wed 1/29/25 Mon 2/17/25
68 Painting - Finish 30 days Fri 1/31/25 Sat 3/1/25
69 Resiliant Tile & Sheet Flooring 21 days Fri 2/14/25 Thu 3/6/25
70 Fire Detection & Alarm 15 days Wed 2/19/25 Wed 3/5/25
71 Glazing 15 days Mon 2/24/25 Mon 3/10/25
72 DDC for HVAC 18 days Mon 2/24/25 Thu 3/13/25
73 Joint Sealants 5 days Mon 3/10/25 Fri 3/14/25
74 Lighting Controls 10 days Wed 3/5/25 Fri 3/14/25
75 PA System 15 days Thu 3/6/25 Thu 3/20/25
76 Door Hardware 30 days Mon 2/24/25 Tue 3/25/25
77 Testing & Balancing 10 days Wed 3/19/25 Fri 3/28/25
78 Toilet Accessories Install 15 days Fri 3/21/25 Fri 4/4/25
79 CCTV 10 days Mon 3/31/25 Wed 4/9/25
80 Finish Carpentry - Cabinets & Lockers 10 days Wed 4/9/25 Fri 4/18/25
81 Resilient Base and Accessories 10 days Tue 4/15/25 Thu 4/24/25
82 Wall & Door Protection Install 15 days Mon 4/21/25 Mon 5/5/25
83 Signage 15 days Mon 5/5/25 Mon 5/19/25
84 ACT Tiles 10 days Mon 5/12/25 Wed 5/21/25
85 Solid Surface Countertops & Sills 15 days Mon 5/12/25 Mon 5/26/25
86 Carpeting 20 days Thu 5/15/25 Tue 6/3/25
87 Fire Extinguisher Cabinets 3 days Wed 6/4/25 Fri 6/6/25
88 Sprinkler Heads 15 days Wed 6/4/25 Wed 6/18/25
89 Substantial Completion 0 days Mon 6/9/25 Mon 6/9/25
90 Punchlist 25 days Fri 6/6/25 Mon 6/30/25
91 Final Completion 0 days Fri 7/4/25 Fri 7/4/25
1/1
1/2
3/15
3/25
3/29
6/9
7/4
22 27 1 6 11 16 21 26 31 5 10 15 20 25 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 19 24 29 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 1 6 11 16 21 26 31 5 10 15 20 25 30 4 9 14 19 24 1 6 11 16 21 26 31 5 10 15 20 25 30 5 10 15 20 25 30 4 9 14 19 24 29 4 9 14 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025 March 2025 April 2025 May 2025 June 2025 July 2025
Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Manual Progress
Sterile Processing Service Relocation - Project #689-408 - VA Connecticut Healthcare System (VACHS) - West Haven Campus - 950 Campbell Avenue, West Haven, CT 06516
ANTICIPATED CONSTRUCTION SCHEDULE
West Haven SPS Relocation Construction Schedule Final.mpp