A22-Price Schedule EXAMPLE.pdf
PDF 109 KB Posted
- Attached to
- Y1DZ--Construct Inpatient Pharmacy West Haven Minor Construction 689-411 Federal contract opportunity
- Solicitation number
- 36C77624B0030
About this file
This document is a Price/Cost Schedule for a federal contract opportunity to construct a new inpatient pharmacy at the West Haven VA Medical Center in Connecticut. The solicitation number is 36C77624B0030, and the project is expected to cost between $20,000,000 and $50,000,000. The period of performance is approximately 730 calendar days from the Notice to Proceed.
The Price/Cost Schedule includes the base work (CLIN 0001) to prepare the site, demolish existing elements, and construct the new 10,500 SF two-story inpatient pharmacy addition. It also includes four deduct options (CLINs 0002-0005) that provide cost reductions by removing certain scope elements such as the exterior envelope system, storage space, conference rooms, and office space. Bidders are instructed to provide unit prices for each CLIN and understand that the deduct options include the cumulative reductions of the previous deducts. The contract will be a single, Firm-Fixed-Price Design-Bid-Build (DBB) contract set aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB).
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A.3 PRICE/COST SCHEDULE
ITEM INFORMATION
ITEM
NUMBER
DESCRIPTION OF
SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0.00 JB ___________$10_______ ___________$10_______
Base Work:
Contractor shall completely prepare project site for operations, including demolition and removal of existing site elements, and furnish labor and materials and perform work for at the West Haven VA Medical Center Project 689-411, Construct New Inpatient Pharmacy as required by drawings and specifications. Period of performance is projected to be Seven hundred thirty
(730) calendar days after the contract receives the Notice to Proceed (NTP).
0.00 JB ______-$1.5____________ _________$8.5_________
DEDUCT 1:
Includes all work in CLIN 0001 (base work) but REMOVES exterior thin concrete and metal panel system change to EIFS system on exterior envelope system.
IF enough funds are not available for CLIN 0001, this line item may be awarded.
0.00 JB _______-$1.2___________ ___________$7.3_______
DEDUCT 2:
Includes all work in CLIN 0001 but REMOVES all work in DEDUCT 1 and Eliminates 280 S.F. of storage space.
If enough funds are not available for CLIN 0001 & CLIN 0002, this line item may be awarded.
0.00 JB __________-$0.8________ _________$6.5_________
DEDUCT 3:
Includes all work in CLIN 0001 But REMOVES all work in DEDUCTS 1 and 2 and eliminates the conference room, staff locker room and staff lounge, 600 S.F.
If enough funds are not available for CLIN 0001, CLIN 0002, & CLIN 0003, this line item may be awarded.
0.00 JB __________-$0.5________ _______$6.0___________
DEDUCT 4:
Includes all work in CLIN 0001 but REMOVES all work in DEDUCTS 1,2, and 3 and Eliminates 425 S.F. of office space.
If enough funds are not available for CLIN 0001, CLIN 0002, CLIN 0003, & CLIN 0004, this line item may be awarded.
PLEASE NOTE:
Bidders should provide the unit price for each corresponding line item in column 1, as well as the total amount of the bid In column 2.
Bidders should also understand that each deduct includes the previous deduction, as well as the current deduction when factoring the total bid amount. As an example, deduct 4 would include a deduction of $0.5, as well as the cumulative total of ALL previous deductions as well. This would mean that the bid for line item 0005 (deduct 4) would be $6.0.
| A.3 PRICE/COST SCHEDULE |
| ITEM INFORMATION |