Attachment 26 - RFIs - Technical Questions and Responses - REVISED.pdf

PDF 339 KB Posted

Attached to
36C77622B0029 - Replace Boilers - Leavenworth - Solicitation Federal contract opportunity
Solicitation number
36C77622B0029
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This document contains technical questions and responses related to a solicitation for replacing boilers at the Dwight D. Eisenhower VA Medical Center in Leavenworth, Kansas. The solicitation involves replacing four antiquated water tube boilers and associated piping and support systems with three new energy efficient fire tube boilers. Additional work includes replacing auxiliary systems in Building 39, fuel oil pump sets, condensate piping, a deaerator tank, condensate return tank, and adding a Continuous Blowdown Heat Recovery Package. It also requires asbestos abatement of piping to be replaced. The document addresses 55 questions received from potential offerors and the responses provided by the Department of Veterans Affairs to clarify requirements for the solicitation. Areas of inquiry include scope of abatement, equipment specifications, coordination with existing controls and fire alarm vendors, temporary facilities, and other construction details.

View the file

Other files for this federal contract opportunity

Other files attached to 36C77622B0029 - Replace Boilers - Leavenworth - Solicitation, newest first.
File Type Posted
36C77622B0029 0003.pdf PDF
36C77622B0029 0002.pdf PDF
Attachment 24 - RFIs - Technical Questions and Responses.pdf PDF
Attachment 21 - Asbestos Report.pdf PDF
Attachment 25 - Site Visit Attendance Sheet.pdf PDF
Attachment 22 - DDC for HVAC.pdf PDF
Attachment 23 - S-532 Drawing Sheet.pdf PDF
36C77622B0029 0001.pdf PDF
36C77622B0029_1.pdf PDF
Attachment 06 - Fire Protection - Drawings.pdf PDF
Attachment 08 - Mechanical - Part 1 - Drawings.pdf PDF
Attachment 09 - Mechanical - Part 2 - Drawings.pdf PDF
Attachment 12 - Security - Drawings.pdf PDF
Attachment 01 - General Information - Drawings.pdf PDF
Attachment 11 - Electrical - Part 2 - Drawings.pdf PDF
Attachment 15 - Specifications - Volume 3.pdf PDF
Attachment 16 - Boiler Plant - Drawing Sheet - M001.pdf PDF
Attachment 18 - Contractor Safety - Environmental Form.docx DOCX document
Attachment 19 - Wage Rates - Leavenworth KS 5-21-2022.pdf PDF
Attachment 20 - VHA Supplemental Contract Requirements for Combatting COVID-19 Updated 12-14-2021.docx DOCX document
Attachment 03 - Civil - Drawings.pdf PDF
Attachment 04 - Structural - Drawings.pdf PDF
Attachment 05 - Architectural - Drawings.pdf PDF
Attachment 10 - Electrical - Part 1 - Drawings.pdf PDF
Attachment 02 - Hazardous Materials - Drawings.pdf PDF
Attachment 07 - Plumbing - Drawings.pdf PDF
Attachment 13 - Specifications - Volume 1.pdf PDF
Attachment 14 - Specifications - Volume 2.pdf PDF
Attachment 17 - Limitations on Subcontracting - Construction.docx DOCX document
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C77622B0029 Replace Boilers Leavenworth: TECHNICAL QUESTIONS AND VA RESPONSE TRACKING SHEET

ITEM

NO.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

1. 7/21/2022 7/28/2022 Will all systems (MEP) to be made safe prior to mob?

Yes, see next question

2. 7/21/2022 7/28/2022 Will make safe be supplied by Owner (VA) / General Contractor (GC)

Both, VA and Contractor LOTO required.

3. 7/21/2022 7/28/2022 Will temp water / temp power be supplied by VA /

GC?

Yes

4. 7/21/2022 7/28/2022 Please confirm that any and all loose contents, furniture, materials not fixed or fastened mechanically will be removed from all work areas scheduled for demo / abatement?

VA will remove tools and furnishings

5. 7/21/2022 7/28/2022 Are any items scheduled to be replaced / demolished wanting to be salvaged by VA / GC?

Only those already identified – i.e., Emergency Generator.

6. 7/21/2022 7/28/2022 What is the max load in boiler room? Load Varies on season Summer – 4.6 KPH/Winter

-28 KPH

7. 7/21/2022 To perform work, various equipment to be utilized around perimeter of bldg.. 39, What are the known, or potential below grade utility / tunnel hazards exist?

Campus main steam tunnel at Northeast of Bldg.

39. Sewer and Natural Gas mains at Southeast of Bldg. 39

8. 7/21/2022 What weight restrictions / limitations (if any) should be considered?

Maximum vehicle load should be assumed to be HS-20. No heavy loading within 8’-0” of foundation walls with subgrade areas.

9. 7/21/2022 7/28/2022 Any restrictions / special requirements to consider prior to performing open flame cutting (torch / plasma cutting) on interior / exterior demo work?

Follow established VA Hot Work Permit requirements – will be provided.

10. 7/21/2022 7/28/2022 Please confirm if there is an independent liner inside of the chimney

Liner to remain

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

11. 7/21/2022 7/28/2022 Please confirm if there are any original drawings (structural, as built, etc.) for chimney, if so please provide.

The Boiler Chimney Stack is listed under the States’ Historic Preservation Plan as Building Number 139. It was constructed in 1932. The architect/builder was Custodi Construction Co., Inc. New York, Chicago. Foundation is concrete, structural system is masonry, and walls fireproof red tile, brick. This is all the information I have on the stack.

12. 7/21/2022 7/28/2022 Please confirm if there are any previous inspection reports for this chimney

None available

13. 7/21/2022 7/28/2022 Please confirm if the ACM is on the inside of the liner (if there is one), or limited to outer interior chimney lining (anulus)

Liner to remain

14. 7/21/2022 Please confirm if there is anything covering the brick which may make it difficult to remove the ACM

Boilers were operating at the time of the survey.

Destructive investigation of operating equipment and the interior of the stack was not conducted.

The interior of the stack was not entered and sampled by the environmental consultant.

15. 7/21/2022 7/28/2022 Please confirm if the step Irons located over the breeching are in usable condition

Cannot guarantee/confirm

16. 7/21/2022 Please confirm if there is a specific Geofoam required for this project.

Lightweight, capable of supporting 2 psi.

17. 7/21/2022 Please confirm elevation of the existing chimney door in relation to section 2 – Chimney modification section on drawing S-532

There are two (2) openings in the chimney:

breaching and top. Breaching opening/chimney door are the same opening and is located approximately 1’-6” above grade.

18. 7/21/2022 Can you provide bulk sampling / lab analysis report for ACM listed within RFP?

Bulk sampling results and lab reports are provided in the Mabbett Regulated Building Materials Survey Report for Building 39 dated January 18, 2021.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

19. 7/21/2022 Can you provide a detailed description / photos of the ACM material within Chimney, also is this material friable, or non-friable?

The interior of the stack was not entered or sampled by the environmental consultant.

20. 7/21/2022 Should the interior boiler refractory be assumed as

ACM?

Boilers were operating at the time of the survey.

The interior boiler refractor should be assumed to be ACM unless sample results prove otherwise.

21. 7/21/2022 7/28/2022 Regarding the temporary trailer for facility staff. Will portable toilets be acceptable? in lieu of a trailer with a restroom in it? A trailer would be provided still but without the restroom.

Available toilets are accessible to Staff within adjoining buildings. Portables will be required for Contract Personnel.

22. 7/21/2022 7/28/2022 There will be a few penetrations in the roof. Is there a roof warranty currently on the building? If there is a roof warranty, who holds the warranty?

No warranty

23. 7/21/2022 7/28/2022 Who is the current controls (BMS) vendor for this building? Is there a particular person to coordinate with?

Hayes Cleveland – POC is John Fry

24. 7/21/2022 7/28/2022 Who is the current fire alarm vendor for this building? Is there a contact person for coordination purposes?

Siemens has the contract. VA’s POC is our Life Safety person, DJ Adams

25. 7/21/2022 7/28/2022 Is the existing boiler plant a 24/7 operating plant? Yes, high pressure requirements

26. 7/21/2022 7/28/2022 Is there a preferred seismic company? No

27. 7/21/2022 Clarify BIM Coordination requirements. Question is not specific and cannot answer.

28. 7/21/2022 7/28/2022 How much abatement is required for the stack? Is it the entire stack or where the tie ins are at?

Only where enclosing stack top and base entry.

29. 7/21/2022 01 00 00 1.3-A.32 requires a pipe stress analysis, signed and sealed by a PE with a current license in the state of PA. Confirm PA is required and not KS.

State of Kansas.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

30. 7/21/2022 23 09 23 was not included with the specifications. There are air-side controls and process water pump controls amongst other 23 09 23 controls that are required. Please provide specification and advise who the proprietary controls contractor is.

Please see attached specification 23 09 23. The contractor shall coordinate with the facility, for the existing controls contractor information.

31. 7/21/2022 7/28/2022 Chemical Treatment for Temporary Boilers: Please confirm the Government will provide chemicals for the temporary boilers.

The VA will; however the contractor shall coordinate with the facilities’ existing chemical feed contractor (see specification 23 50 11).

32. 7/21/2022 The scissor lift skid (MP-101C) states to see plumbing drawings. The plumbing drawings do not provide any information on this skid. Is this skid to be new? Please provide specs.

Optimus hydraulic lift table, model Lift5K manufactured by Bishamon Industries Corporation or approved equal.

33. 7/21/2022 7/28/2022 Please provide a spec and details for the 14’x7’ enclosure that goes around the booster pump system.

Enclosure shall be Hotbox HA087172085 or approved equal.

34. 7/21/2022 7/28/2022 Please confirm flue gas economizers are not required. They are not

35. 7/21/2022 How long should the Contractor assume the temporary boilers are required for this project? Will the Government pay the monthly costs for the temporary boilers if it goes over this duration?

This will be based upon the contractor’s projected construction schedule.

36. 7/21/2022 Please confirm the metal fabricator must be AISC certified per 01 45 35 2.1-B and 05 12 00 1.5-B. This typically limits steel contractor competition.

The VA shall respond as to whether they will accept waiving AISC certification. However, we certainly recommend AISC certification as it guarantees a level of quality in fabrication and erection particularly where the fabrication and connections are critical in the integrity of the structure/frame. The VA concurs with this requirement.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

37. 7/21/2022 7/28/2022 The boiler manufacturers typically want down payments at receipt of PO, receipt of submittals, equipment release, etc. Will the Government pay for these down payments, or does the Contractor need to figure a loan in their estimate to front the costs?

Yes

38. 7/21/2022 Please confirm the Government will provide all fuel oil for the temporary boilers and for tuning and commissioning the new boilers.

The contractor is responsible for tuning and commissioning the new boilers. The VA will supply the fuel oil for the temporary boilers.

39. 7/21/2022 Please confirm the Contractor shall hire the Commissioning Firm per 01 91 00 1.8-B.3.

Yes

40. 7/21/2022 Please confirm the Contractor shall include a dedicated SSHO in their bid. This is separate from the Site Superintendent.

Yes, during construction operations per the contract documents.

41. 7/21/2022 Please confirm the Contractor shall hire a firm like Multivista to meet the Photographic Documentation requirements per 01 00 00 1.25.

The requirements are noted in 1.25 Photographic Documentation.

42. 7/21/2022 Please provide a basis of design manufacturer for the anti-ram bollards (detail 2/S-530 and civil drawing C- 102). Please confirm these shall be a delegated design.

Gibraltar G-1000. This is a delegated design item by a professional engineer in the State of Kansas

43. 7/21/2022 7/28/2022 Please confirm the Contractor shall hire a firm like BEI to provide the Boiler Plant Safety Device Testing.

Yes

44. 7/21/2022 7/28/2022 Is the Contractor to hire the Certified Boiler Inspector, or the Government?

Contractor

45. 7/21/2022 Spec 23 52 39, para 2.1.D calls for a minimum fireside heating surface of 5 square feet per boiler horsepower while the Fire Tube Steam Boiler schedule on drawing MP-701 lists a fireside heating surface of 2404 square feet (which is only 3.43 sq ft per boiler horsepower).

Which is correct?

5 square feet

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

46. 7/19/2022 The roof trusses appear to be 24” on center. The drawings call for 24” exhaust stacks to penetrate the roof. Due to snow load and the lack of bracing on the bottom side of the trusses; is there any guidance on how the roof should be penetrated, boxed out, etc?

Roof joists appear to be at 1’-6” o.c. with girders at 4’-0”, verify all dimensions in field. Provide framing around openings as shown in detail 1/S- 522.

47. 7/21/2022 7/28/2022 Regarding the temporary trailer for facility staff. Will portable toilets be acceptable in lieu of a trailer with a restroom in it? A trailer would be provided still but without the restroom.

Yes. Staff has restrooms within the adjoining building envelop to use.

48. 7/21/2022 7/28/2022 There will be a few penetrations in the roof. Is there a roof warranty currently on the building? If there is a roof warranty, who holds the warranty?

No warranty

49. 7/21/2022 7/28/2022 Who is the current controls (BMS) vendor for this building? Is there a particular person to coordinate with?

Hays Cleveland – John Fry

50. 7/21/2022 7/28/2022 Who is the current fire alarm vendor for this building? Is there a contact person for coordination purposes?

Siemens has the contract. VA’s POC is our Life Safety person, DJ Adams

51. 7/21/2022 7/28/2022 Is the existing boiler plant a 24/7 operating plant? Yes

52. 7/21/2022 7/28/2022 Is there a preferred seismic company? No

53. 7/21/2022 7/28/2022 Clarify BIM Coordination requirements. Question is not specific and cannot answer.

54. 7/21/2022 7/28/2022 How much abatement is required for the stack? Is it the entire stack or where the tie ins are at?

Just where the tie ins are.

55. 7/18/2022 7/28/2022 Due to the number of VA projects bidding around the same date, would it be possible to get an extension of the bid date? Thank you for your consideration.

No objections from the VA

56. 7/21/2022 7/28/2022 What location will be able to be used for?

a. Dumpster location

Best Location during demo would be the existing roll up door

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

57. 7/21/2022 7/28/2022 b. Lay down area I would recommend in proximity of Building 37.

There is a paved area in front of the building for a contractor trailer and may be adequate power to tie into from the building. Highly recommend chain-link fencing off laydown area for security purposes.

58. The table in 1.1B of Section 02 82 11 lists quantities for the amounts of asbestos-containing materials to be abated; however, during the site visit it appeared that some of these quantities may be incorrect (e.g., there appears to be much more than 100 ft of piping below 6” in diameter, and the stack does not appear to have an asbestos lining). Section 1.1.B.1 says the Contractor should satisfy themselves that the amounts are correct, but this would take several hours and result in Contractors bidding on different amounts. Can you please confirm the quantities?

Not all <6” pipe insulation contains ACM. Bulk sampling results and lab reports are provided in the Mabbett Regulated Building Materials Survey Report for Building 39 dated January 18, 2021.

The interior of the stack was not entered or sampled by the environmental consultant.

59. 7/21/2022 7/28/2022 Should asbestos remediation firms use the Laborer (Common or General) wage rate? On some Davis-Bacon jobs we use the Laborer worker classification, but on other jobs we are told to use the Asbestos Worker / Heat & Frost Insulator rate. The Asbestos Worker / Heat & Frost Insulator rate isn’t provided on General Decision Number: KS20220034 04/08/2022, so we think we should use the Laborer rate, but want to confirm.

Recommend reaching out to Titan Abatement for a real time labor rate.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

60. 7/21/2022 7/28/2022 Section 02 82 11 has several requirements that exceed OSHA, EPA or KDHE requirements or are not required at all (e.g., having a Contractor Professional Industrial Hygienist, triple layer walls/ceilings/floors in the decontamination facilities, double layered containment walls, erecting secondary barriers and walkways each day, double layers of lockdown encapsulant, having both the VPIH and Contractor monitor air outside the containment and doing two clearances of the containment, requiring fire retardant sheeting, negative air machine gauges/warning device/daily verification requirements, numerous documentation requirements, air test requirement, etc.). Together, these will add tens of thousands of dollars of incremental cost to the project without corresponding benefit. Is the VA sure they want to include these requirements in the spec?

Question is not specific and cannot answer.

61. 7/21/2022 7/28/2022 Part 3.2.D.1. of Section 02 82 11 says it will list where Amosite is present, but it does not. Can you please clarify if any Amosite is present? If so, where and in what quantities?

Recommend reviewing the Asbestos Report dated 9-18-2020 provided (survey), conducted by ENCON International. I will provide a copy in this response.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

62. 8/2/2022 Section 01 91 00 references 3rd party testing for a number of division 26, 27, and 28 systems however the individual technical specifications do not require 3rd party testing. Please advise if any 3rd party testing is required, and if so, what technical specification sections require 3rd party testing, and if the VA, the GC, or the Electrical Contractor is responsible for hiring that firm.

No 3rd party testing is required in any of divisions 26, 27 and 28.

63. 8/2/2022 Section 26 05 11 allows for work on energized equipment. It is our experience at the VA that manhole entry with energized cables or work on energized equipment is strictly not allowed. Please confirm that all work in manholes or equipment with existing cables will require and outage and all cables to be de energized prior to entry into that manhole.

This is incorrect if proper protocols are followed.

64. 8/2/2022 8/3/2022 Please confirm that all drawings will be provided to the contractor in native (REVIT or CAD) format so that coordination and shop drawings, including equipment rooms, conduit routing, as built, etc. can be completed per 01 33 23.

Yes, they are available

65. 8/2/2022 Section 26 05 13.3.5 requires MV Conductors to be fire taped in manholes and pull boxes. Please confirm if this includes any existing cables encountered without fire tape. Also please confirm that each conductor should be taped and bundling of the circuit conductors under 1 wrap of tape is not allowed.

Fire tape applies to new work. If any existing cables are found to be inadequately taped, then this would be a change. Each conductor shall be individually taped. A single wrap of tape is not allowed for the bundle of circuit conductors.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

66. 8/2/2022 Please confirm if hi pot is testing is an acceptable alternative to the VLF And Tan Delta testing outlined in 26 05 13.3.7. This has been allowed at other VA facilities due to the damage risk associated with VLF testing.

Yes

67. 8/2/2022 Electrical conductor materials are specified throughout the division 26 spec as copper only. Due to the high volatility in the current commodity market, is the expectation for the electrical contractors to include assumed escalation costs? Or should they include the cost at which they can buy copper at today, and if/when the price increases the government will modify the contract for the increased cost?

Yes, make the assumption.

68. 8/2/2022 Confirm feeders to building 18 and 64 from Switch S5A are existing to remain and not part of this contract scope of work.

Confirmed.

69. 8/2/2022 Detail 4 and 5 on sheet E504 both state that they apply to the conduit from new MH39A to the transformer room. Is the intent to have (1) spare 2" from the room and (1) spare 5" from the switch out to MH39A? Also confirm that (1) of the 2" conduits is for power from the building to a sump pump, and (2) light fixtures in

MH39A.

Correct. Confirmed.

70. 8/2/2022 Confirm that detail 4 and 5 conduit configurations can adjusted to be (2) wide in lieu of (2) high if desired by the contractor.

Duct bank configuration may be adjusted. (2) high was shown due to congestions of underground utilities in the roadway.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

71. 8/2/2022 Detail 10 note 1 on sheet E502 states that this detail applies to both steam and MV manholes. I am seeing electrical connections to a MV manhole, but I do not see any electrical connections indicated to a steam manhole. If there is a steam manhole, please indicate circuiting, and fixture types if required.

No steam manholes for this project. Detail applies to new manhole MH39A.

72. 8/2/2022 Detail 4 on E504 calls for (2) 5" conduits from MV switch and new HH#1 and E602 calls for (2) 4" conduits. Please advise which is correct.

(2) 5"C is to be used per Detail 4/E-504.

73. 8/2/2022 What type of conduit is allowed for use in the electric shop, boiler plant, and building 39A? The spec is vague on this and there is a mixture of EMT and RMC throughout the spaces.

RMC shall be used when conduit is exposed and subject to physical damage, or where specifically called out for on drawings or specs. Otherwise, EMT is acceptable.

74. 8/2/2022 ES100 Indicates new duct installed between existing switch 5A and existing manhole #12. Please confirm if there are existing stubbed beyond the existing pad into the correct compartment of switch 5A. If not please advise on how we are to make this conduit connection.

Verified, there are stub out.

Construction Phasing Note #5 on sheet ES101 anticipates an outage for the installation of the duct bank from Switch 5A to MH#12. Installation method for the duct bank shall fall under means and methods. Work shall be completed during off-hours. Coordinate work with the VA.

75. 8/2/2022 Please provide fuel oil consumption rates of existing generator so we can include appropriate fuel in our bid per temporary electrical equipment note 3 on sheet E600

Existing Generator is a standby diesel 150kW Caterpillar D150-8. Fuel consumption at 100% load with fan is 11.3 gph.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

76. 8/2/2022 Detail 4 on E504 call for ducts to be schedule 80 however specification section 260541.2.4.b states schedule 40 for encased ducts. Please advise which should be included in our bid.

Schedule 80 shall be utilized per Details 4 and 5 on E-504.

77. 8/2/2022 please provide sump pump schedule and piping drawings on the plumbing plans for sump pumps required for the electrical and or steam manholes

Sump Pump: Little Giant 4-E-34-NR Series, epoxy die cast aluminum housing, 1/12 HP submersible pump. 115V, 60HZ, 3.5 amps with 6’ cord. 10 GPM at 14 FT.HD.

Refer to sheet C-102 for connection of sump pump drain line.

78. 8/2/2022 8/3/2022 Electrical demolition note 2 on E-002 states that the facility will be operational during the course of construction. However, at the site visit it was explained that all personnel will be relocated out of the office area, building 39, and building 39A during the construction period. Please confirm that the office area, building 39, and building 39A will be vacant during the course of construction and the only area in building 39 that needs to stay active is the electric shop.

The Boiler Plant Proper will be completely vacated by the Boiler Plant Personnel.

With the exception to the Electrical Shop, no personnel will be actively within Building 39/39A.

There are some areas within Building 39 that would need to remain active, such as the Security Room, IT Rack, FACP, etc. as noted in the Temporary Equipment Notes on sheet ES100.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

79. 8/2/2022 The equipment located in electrical room 208 scheduled for removal however is too large to fit thru the existing man doors that appear to be out of scope. Please confirm how this equipment is to be removed from the building and confirm if the housekeeping pad needs to be demoed as well.

Refer to Sheet ED102A, key note #1 indicating disassembly of equipment for removal.

Existing housekeeping pad to remain. Contractor shall extend the pad as needed to provide a level surface for equipment working space per NEC 110.26.

80. 8/2/2022 Is there any need for a temporary fire alarm or fire suppression system to be installed for coverage of the electric shop while the remaining building is shut down for construction activities?

See Temporary Equipment Notes on sheet ES100.

See Phasing Notes on Sheet E-604.

81. 8/2/2022 Are there any plans available that show existing building expansion joints or new planned expansion joints?

Existing building does not contain expansion joints.

82. 8/2/2022 Section 01 91 00 references COBIE and BIM. Please confirm if it is the contractor’s responsibility to provide a full BIM coordination model and COBIE information with in that model.

Confirmed

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

83. 8/2/2022 Reference general electrical note 57 on E002. Please confirm that the entire building electrical system meets the definition of an emergency system as defined in NEC

700.2. If so, NEC 700.10 requires exposed conduit for

emergency systems to be labeled in intervals not to exceed 25' in addition to the equipment and devices.

This would be all conduit in building 39. Is there a desired label that the VA would like for us to carry in our estimate or will doubling the amount of labels per note 56 and add the verbiage "emergency system" work?

Modify note 56 as 25' interval with "Emergency System" added to label. Label for emergency system conduits shall be white with red letters.

84. 8/2/2022 Confirm the manhole details 9, 10, and 11 provided on sheet E502 are only applicable to the (1) new manhole 39A and not any existing man holes.

85. 8/2/2022 Will a coordination study and arch flash analysis per 26 05 73 (both normal and emergency) be required for the temporary power equipment indicated on sheet E600?

Yes. The temporary equipment will require servicing/adjusting during its usage, especially considering the duration.

86. 8/2/2022 Power is not indicated for the 2000gal temporary fuel oil tanks to support 96 hr run time of temp generator.

Please confirm what is required here.

Assume a 20A/3P breaker and feeder to temporary distribution panel TEMP-MDP.

Exact circuit requirements shall be coordinated with actual equipment.

87. 8/2/2022 Is a fuel spill containment system required for the temporary generator fuel oil tank? Anticipated size is 2000 gallons.

Provide double wall fuel oil tank.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

88. 8/2/2022 39HVL1 and 2 are noted as 12,470V. Confirm they should be 4,160V but rated for up to 15KV.

Confirmed. The VA had specifically requested that the equipment be rated for 15kV.

89. 8/2/2022 39-MXFRM to 39MCB1 and 2 are indicated as a bus connection. Talking to the vendors this will be standalone pieces of equipment that will we require cable and conduit bussing between them. Please confirm cable/conduit type and size required from the transformer to each MCB.

EMT conduit is acceptable. Cable per specifications. Ensure sufficient lugs available on transformer secondary. Cables shall be terminated into Two-hole long barrel compression lugs. Feeder length shall not exceed 10' per NEC 240.21(C)(2).

To 39-MCB1, provide (2) 3"C, each with (4) 350kcmil + (1) 2/0G.

To 39-MCB2, provide (3) 2/0 + (1) 4G in 2"C.

If these connections can’t be made, a bussed connection would be required and the two MCB’s would be housed as a switchboard section.

90. 8/2/2022 We do not believe the new generator will fit through door201. In lieu of rigging through the louver opening would it be possible to scheduled door 201 the same size as 202B or add an additional door the same size as 202B could be added to the east exterior wall of room 201 to allow installation and removal of this new generator.

Enlarging door 201 to the size of door 202B: the substation would be in the way (unless the generator is rigged before installation of the pad and substation).

A larger door 201 would eliminate wall space in room 201 which will be utilized for equipment space.

An additional exterior door east of room 201 would interfere with the existing stack.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

91. 8/2/2022 Keynote 1 indicates metering equipment and states it to have capabilities of communication with a VA centralized remote metering station. Please provide information on what is required here and what capabilities are needed to communicate to the centralized metering station. If a specification is the best way to provide that information, then please provide.

There is not a centralized meter station currently, but the meter should have comm capabilities for future connection. Comm shall be via modbus.

This is in additional to the requirement that the meter communicate with the SCADA system.

92. 8/2/2022 Keynote 12 on sheet EP102A indicates the feeders back to the transformer room should be routed above "false ceiling" it was noted at the walk thru that this is a hard ceiling and appears to be in accessible. Please advise on the intent here. Should the general contractors include ceiling demo and replacement for this area? If not how is this accessible to run conduit?

There is attic space and access above the electrical shop.

93. 8/2/2022 Confirm location or designation of feed water skid shown fed from EMDP circuit 9.

Please verify this state’s, EMDP circuit #9. the EMDP panels are what feeds the Hospital.

Feed water skid consists of the three FWP’s shown on sheet EP101B below the D/A tank.

Refer to sheet EP101B keynote #4.

94. 8/2/2022 Confirm location of 39-T-EWST shown fed from EMDP circuit 8

Please verify this state’s, EMDP circuit #9. the EMDP panels are what feeds the Hospital.

Transformer is located near the pump pit, south of column line “A”. See sheet EP101C.

DATE

QUESTION

RECEIVED

DATE

QUESTION

ANSWERED

QUESTION GOVERNMENT RESPONSE

95. 8/2/2022 In regard to the above ground storage tank, the drawings list a 60,000-gallon tank, whereas the specification lists 80,000 gallon minimum capacity.

Please clarify.

60,000 gallon above ground storage tank shall be installed per drawings. Basis of design: Highland HighDRO Water Storage Tank, mild carbon steel single wall insulated tank.

96. 8/2/2022 The specification for painting indicates that the tank is to be zinc metalized inside and aluminum metalized outside. This is not a system that has been seen before for a tank of this kind. Typically, the tank is painted inside and out per AWWA D100/102. Please clarify.

The tank is prefabricated and delivered painted by the manufacturer with touch paint included.

Please clarify the specification section referenced in question.

97. VA Leavenworth KS, MO. Replace boilers Please advise if the designated SSHO and Competent Person role can be fulfilled by the site superintendent?

Refer to Specification 01 35 26 Section 1.7

98. Will the SSHO be full time separate person? Refer to Specification 01 35 26 Section 1.7

99. Is the project taxable? Yes

100. Will submittal exchange be provided by the architect or

GC?

The GC. Typically using Newforma or Procore for submittal exchange.

101. Specification Section 01 00 00 – General Requirements:

Paragraph 1.25 identifies professional photographic documentation. Please confirm that this has to be completed by a commercial photographer.

The requirements are noted in 1.25 Photographic Documentation.

102. LEED is called out a few times throughout the specifications. Is this a LEED project?

No, this project is not a LEED project.

103. Specification 102310 interior window wall, is there a basis of design or manufacturer?

No.

ITEM