Summary

This is a specification document for window shades for the Iowa City VA Medical Center 6th Floor renovation project (Project No. 636A8-22-001). The specification details requirements for cloth shades, vertical blinds, and venetian blinds, including complete installation with brackets, fittings, and hardware. The shades must match existing building standards for color and be suitable for clinical support spaces.

The contractor must provide light-filtering shade cloth composed of woven mesh fabric with 79% reinforced vinyl and 21% polyester core yarn, with 1 percent openness factor and railroaded orientation. Shades must pass NFPA 701 fire tests for flame propagation and demonstrate "No Growth" anti-microbial characteristics per ASTM G21 testing for specified fungi strains. The specification requires cordless roller shades with spring operating mechanisms, positive locking at half-turn increments, stainless steel components, and 305 mm (12 inch) extension beyond the window height. Fabrication must include extruded aluminum hem bars, metal eyelets, and stainless steel chain cords with 80 kg (175 pounds) breaking strength. Installation requires leveled rollers positioned high at window heads to prevent light infiltration, with extension brackets at mullions as necessary. The manufacturer must demonstrate minimum three years' experience with similar installations and provide a five-year warranty from installation date. Installation personnel must be trained and approved by the manufacturer. Submittals include 24-inch fabric samples, shop drawings, fire testing reports, and manufacturer literature. Final protection and cleaning per manufacturer instructions must be completed before Substantial Completion, with damaged shades replaced as approved by the Contracting Officer Representative.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

September 03, 2026 Project No 636A8-22-001 Iowa City VA Medical Center

Renovate 6th Floor for Clinical Support

08-01-17

12 24 00 - 1

SECTION 12 24 00 WINDOW SHADES

PART 1 - GENERAL

1.1 DESCRIPTION:

A. This section includes cloth shades, vertical blinds and venetian blinds. Provide window shades complete, including brackets, fittings and hardware.

1.2 RELATED WORK:

A. Color of shade cloth: to match existing building standard.

B. Section 01 00 00 GENERAL REQUIREMENTS, page 1 paragraph 1.3B

1.3 QUALITY ASSURANCE:

A. Manufacturer's Qualification: Submit evidence that the manufacture has a minimum of three (3) years’ experience in providing item of type specified, and that the blinds have performed satisfactorily on similar installations. Submit qualifications.

B. Submit qualifications for installers who are trained and approved by manufacturer for installation of units provided.

C. Electrical Requirements:

1. NFPA 70 Article 100.

2. Listed and labeled in accordance with UL 325.

3. Marked for intended use, and tested as a system.

4. Individual testing of components is not acceptable in lieu of system testing.

1.4 SUBMITTALS:

A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT

DATA, AND SAMPLES.

B. Samples:

1. Shade cloth, each type, 610 mm (24 inch) square, including cord and ring, showing color, finish and texture.

Renovate 6th Floor for Clinical Support

12 24 00 - 2

C. Manufacturer's literature and data; showing details of construction and hardware for:

Cloth and window shades

D. Shop Drawings: Provide fabrication and installation details for cloth shades, including shade cloth materials, their orientation to rollers, and their seam and batten locations.

E. Fire Testing: Submit report of flame spread and smoke developed during product material tests by independent testing laboratory.

F. Manufacturer’s warranty.

1.5 WARRANTY:

A. Construction Warranty: Comply with FAR clause 52.246-21, “Warranty of Construction”.

B. Manufacturer Warranty: Manufacturer shall warranty their window shades for a minimum of five (5) years from date of installation and final acceptance by the Government. Submit manufacturer’s warranty.

1.6 APPLICABLE PUBLICATIONS:

A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced to in the text by the basic designation only.

B. Federal Specifications (Fed. Spec.):

AA-V-00200B.............Venetian Blinds, Shade, Roller, Window, Roller, Slat, Cord, and Accessories

C. ASTM International (ASTM):

G21-13..................Determining Resistance of Synthetic Polymeric

Materials to Fungi

D. National Fire Protection Association (NFPA):

70-14...................National Electrical Code (NEC)

701-15..................Fire Tests for Flame Propagation of Textiles and Films

E. Underwriters Laboratories Inc. (UL):

325-06(R2013)...........Door, Drapery, Gate, Louver, and Window

Operators and Systems

Renovate 6th Floor for Clinical Support

12 24 00 - 3

PART 2 - PRODUCTS

2.1 CLOTH SHADES:

A. Light-Filtering Shade Cloth: Woven fabric, stain and fade resistant.

1. Weave: Mesh Woven of 2.54 mm )0.10 inches) thick opaque, extruded vinyl-coated polyester yarn consisting of approximately 79% reinforced vinyl and 21% polyester core yarn. Shadecloth shall be tensioned in the finishing range prior to heat setting.

2. Orientation on Shadeband: Railroaded.

3. Openness Factor: 1 percent.

4. Fire-Test-Response Characteristics: Passes NFPA 701 small and large-scale vertical burn. Submit report for testing of shade cloth materials identical to products provided.

5. Drive-End Location: Right side of inside face of shade.

6. Shade Cloth Anti-Microbial Characteristics: ‘No Growth’ per ASTM G21 results for fungi ATCC9642, ATCC9677, and ATCC9645.

7. Cordless Shades: Provide roller containing spring operating mechanism sized to accommodate shade size indicated in construction documents. Provide with positive locking mechanism that can stop shade movement at each half-turn of roller and with manufacturer’s standard pull.

a. Pole: Manufacturer’s standard type in length required to make operation convenient from floor level and with hook for engaging pull.

2.2 MATERIALS:

A. Stainless Steel: ASTM A240/A240M.

B. Extruded Aluminum: ASTM B221M (B221).

C. Cords for Cloth roller shades: #10 stainless steel chain having not less than 80 kg (175 pounds) breaking strength.

2.3 FASTENINGS:

A. Zinc-coated or cadmium plated steel or stainless steel fastenings of length and type recommended by manufacturer. Except as otherwise specified, provide fastenings for installation with various structural materials as follows:

Renovate 6th Floor for Clinical Support

12 24 00 - 4

Type of Fastening Structural Material

Wood screw Wood

Tap screw Metal

Case-hardened, self-tapping screw in pre-drilled hole

Solid masonry, concrete

Toggle bolts Hollow blocks, gypsum wallboard, plaster

2.4 FABRICATION:

A. Fabricate cloth shades to fit measurements of finished openings obtained at site.

B. Cloth Shades: Rolling type, constructed of shade cloth mounted on rollers. Provide shade cloth with plain sides, and with hem at bottom to accommodate weight bar.

1. Provide separate shades for each individual sash within opening.

Provide shade length that exceeds height of window by 305 mm

(12 inches) measured from head to sill, in addition to material required to make-up hem:

a. Provide rollers with spindles, nylon bearings, tempered steel springs, and other related accessories required for positive action.

b. Provide rollers of diameter and wall thicknesses required to accommodate operating mechanisms, weights, and widths of shadebands indicated without deflection.

c. Provide rollers with permanently lubricated drive-end assemblies and idle-end assemblies designed to facilitate removal of shadebands for service.

d. Secure shade cloth to rollers to prevent wrinkling or folding, and online parallel to axis of rollers so that shade hangs plumb.

e. Secure shade cloth with zinc-coated steel or stainless steel machine screws spaced not over 228 mm (9 inches) on centers.

f. Do not attach shade cloth to rollers with tacks.

Renovate 6th Floor for Clinical Support

12 24 00 - 5

g. Provide hem bar of extruded aluminum for entire width of shade band. Heat seal hem bar on all sides to prevent removal.

h. Provide eyelets with clear openings large enough to accommodate cords, without cutting into cloth when set.

i. Provide cords of sufficient length to permit shades to be drawn to bottom of opening with ends looped and held with cord rings.

Attach cords to hems through metal eyelets in center of slats in bottom hems.

PART 3 - EXECUTION

3.1 INSTALLATION:

A. Measure openings before fabrication. Do not scale construction documents.

B. Cloth Shades: Mount window shades on end of face brackets, set on metal gussets, or casing of windows as required. Provide extension face brackets where necessary at mullions. In existing buildings, provide brackets similar to those on existing windows.

1. Locate rollers in level position as high as practicable at heads of windows.

2. Install shades to prevent infiltration of light over rollers.

3. Where extension brackets are necessary for alignment of shades, provide metal lugs, and rigidly anchor lugs and brackets.

4. Place brackets and rollers so that shades do not interfere with window and screen hardware.

5. Shade installation methods not specifically described, are subject to approval of Contracting Officer Representative (COR).

3.2 ADJUSTING:

A. Adjust shades to operate smoothly, free from binding or malfunction throughout entire operational range.

3.3 CLEANING AND PROTECTION:

A. Clean shade surfaces after installation, according to manufacturer’s written instructions.

October 12, 2023 Revision A2 (add) Project No 636-804

Iowa City VA Medical Center Relocate Women's Health Clinic & Specialty Clinics

1-15-2021

14 24 01-6

B. Provide final protection and maintain conditions that ensure that shades are without damage or deterioration at time of Substantial

Completion.

C. Replace damaged shades that cannot be repaired, in a manner approved by COR before time of Substantial Completion.

- - - E N D - - -