About this file

This document is Amendment 0004 to Solicitation 36C26224R0013_1, the AE MATOC IDIQ (NCO 22) Solicitation issued by the Department of Veterans Affairs Veterans Health Administration, Veterans Integrated Service Network 22 (VISN 22).

The amendment incorporates changes in response to Request for Information (RFI) #0004. The key updates include confirming that projects provided for evaluation must be 100% completed design projects within the last 3 years, and extending the proposal due date from October 14, 2024 to October 15, 2024 at 12PM PST to accommodate a federal holiday. The overall solicitation seeks qualified Service-Disabled Veteran-Owned Small Businesses (SDVOSBs) to provide multi-discipline architectural and engineering design services on an indefinite-delivery, indefinite-quantity (IDIQ) contract with a 5-year period of performance and a $45M contract ceiling. The anticipated task order range is $2,500 to $5M, with NAICS codes 541310, 541320, and 541330 applicable.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

2025-AE-IDIQ

36C262 Veteran Regional Procurement Office Network Contracting Office 22 Carl T. Hayden Veterans' Administration 650 East Indian School Road Phoenix AZ 85012-1839 Veteran Regional Procurement Office Network Contracting Office 22 Carl T. Hayden Veterans' Administration 650 East Indian School Road Phoenix AZ 85012-1839 To all Offerors/Bidders

36C26224R0013 09-05-2024

X X X October 15, 2024, 12PM PST The purpose of this modification is to incorporate the changes associated with the Government's responses to Request for Information (RFI) #0004. See below page 2, RFI #0004 for more details.

Request for Information (RFI) Number 0004

AE MATOC IDIQ FY25

Solicitation# 36C26224R0013_1 RFI Due Date: September 20, 2024 01 October 2024 Note: The following responses represent the Government’s current responses. All previous responses are obsolete.

RFI Number
Date
Question
Answer

AMENDMENT 002 QUESTIONS.

(For Reference)

0015.
9/12/2024
Do projects required in Factor 2 need to be completed or 80% complete?
All provided projects shall be 100% completed projects.
RFI Number
Date
Question
Answer
001.
9/30/2024
Can you please confirm if the 100% for the projects are to be Design or Construction Completed? In reference to question 0015.
Projects need to be 100% completed for Design projects. Additionally, these projects should be within the last three (3) years.
002.
10/01/2024
We noticed that the new deadline for submissions is on a federal holiday (October 14th). Would the Government consider pushing the deadline one additional day to accommodate for the holiday?
Thank you. We apologize for the oversight, the deadline will be pushed by a day to Tuesday, October 15, 2024 12PM PST.

image1.jpeg