Z2FB--NRM 640-24-116 | Repair Aquatic Center, Palo Alto Bldg 530
Solicitation number
36C26124R0053
Issued by

About this file

This document is an amendment to Solicitation 36C26124R0053 for the repair of the Palo Alto Aquatic Center (Building 530). The purpose of the amendment is to respond to Requests for Information (RFIs) from offerors.

The key details are:

  • This is not a design-build project; the contractor will be required to provide engineering services to replace building elements in-kind and restore MEP equipment to serviceable condition.
  • Mold mitigation shall comply with VA standards, and any unforeseen conditions or recommendations from the industrial hygienist's report will be addressed through the change order process.
  • Commissioning is required for the HVAC systems, heat reduction unit, and pool equipment. The contractor will provide pre-functional and functional testing, with VA O&M personnel advising on existing equipment.
  • The testing, adjusting, and balancing scope is for the existing HVAC systems and 3 new exhaust fans only.
  • The scope of work is limited to the Statement of Work and Bid Items/Tasks 1 through 35. Requirements in the specifications beyond this may not be part of the contract.

View the file

Other files

File Type Posted
36C26124R0053 0004.pdf PDF
07 54 23 - Thermoplastic Polyolefin Roofing TPO.pdf PDF
RM 117 revised Photograph Library 28 Jun 2024.pdf PDF
Rev SOW 6.28.2024 Aquatic Center.pdf PDF
07 22 00 - Roof and Deck Insulation.pdf PDF
07 92 00 - Joint Sealants.pdf PDF
07 60 00 - Flashing and Sheet Metal.pdf PDF
36C26124R0053 0003.pdf PDF
07 54 23 - Thermoplastic Polyolefin Roofing.pdf PDF
36C26124R0053 0001.pdf PDF
FINAL SOW B530 Rev 052224.pdf PDF
Exhibit 4 B530 Specifications Rev 052324_Part1.pdf PDF
DIVISION CONSTRUCTION COSTS- Repair Aquatic Center 640-24-116.docx DOCX document
Exhibit 5 B530 Drawings Rev 052324_Part2.pdf PDF
Wage Determination CA20240018 4.26.24.pdf PDF
Exhibit 5 B530 Drawings Rev 052324_Part1.pdf PDF
Evaluation Report.docx DOCX document
CONTRACTOR CERTIFICATION REGARDING SAFETY AND ENVIRONMENTAL.docx DOCX document
Key Personnel Attachment for Evaluation 02.docx DOCX document
36C26124R0053 Repair Aquatic Center.pdf PDF
S02 - RFI Form.docx DOCX document
Photo Library.pdf PDF
Exhibit 4 B530 Specifications Rev 052324_Part3.pdf PDF
S02 - Past Performance Questionnaire.docx DOCX document
Exhibit 5 B530 Drawings Rev 052324_Part3.pdf PDF
ILSM - B530 Aquatic Center - 03.21.24.pdf PDF
Palo Alto Campus Map Site Visit.pdf PDF
Exhibit 4 B530 Specifications Rev 052324_Part2.pdf PDF
Exhibit 5 B530 Drawings Rev 052324_Part4.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 3

06/14/2024

640-24-2-5209-0001

640-24-116

Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Sierra Nevada Healthcare System 975 Kirman Avenue Reno, NV 89502

Proposals have been authorized to be sent electronically and shall be emailed to samantha.henderson@va.gov.

To all Offerors/Bidders

36C26124R0053

05-31-2024

X

X X

X 1

The purpose of amendment 0002 is to:

a) Respond to RFIs, see responses on page 2.

Charee Harris Contracting Officer

RFI NO. Information Being Requested Response to RFI:

001 The statement of work paragraph 2.1 states “The intent is to select a qualified contractor to provide all engineering….” Is this project a Design Build Project? I assume it is not.

Specifically, what engineering will the contractor be required to provide?

This is not a Design Build Project. No design engineering is required.

Engineering services are as required to replace building elements in kind and restore MEP equipment to serviceable condition.

002 Task 2: Mold Mitigation Bullet Point #1 states:

“Engage certified industrial hygienists to produce a detailed report with findings on the extent and type of mold infestation.” I assume the Hygienist’s report will contain recommendations as to how to treat and mitigate the mold issue. The work tasks presumably are the contractual mold mitigation means. If the report has additional/different mold mitigation scope of work, I presume this will be treated as a change to the contract. Please confirm.

Mold mitigation shall comply with VA standards and guidelines as stated in Task #2. If unforeseen conditions are encountered, or the Hygienist report recommends actions other than described in the SOW, they should be reported to the COR for further action as appropriate.

003 In statement of work paragraph Task 11 & 25 in the Matrix; the Action is to Commission the HVAC System and to Commission the Heat Reduction Unit per Section 01 00 00 and Section 01 91 00.

Is the commissioning limited to the HVAC Systems and the Heat Reduction Unit per task #11 and #25 and Section 23 08 00, Commissioning of HVAC Systems?

This does not include the pool equipment.

Section 23 08 00 seems to limit Commissioning to the “HVAC Systems construction throughout the construction period.”

Or is Commissioning far-reaching, onerous, and extensive as per the Matrix on pages 45 through 62 in Section 01 91 00?

Secondly, if all the HVAC systems are to be commissioned are the VA O& M personnel going to be primary in the pre- functional and

Commissioning is required for all existing HVAC and Mechanical systems.

Commissioning is also required for pool systems installed or repaired under this contract.

Commissioning activities are as described in the SOW and Specifications.

Activities specific to LEED certification are not required.

The Contractor is to provide pre-functional and functional testing during commissioning. VA O&M Engineering personnel can advise on equipment functional testing of all the existing HVAC systems per paragraph 3.1, Commissioning and Responsibility Matrix? I assume they are the experts in the operations of the existing HVAC systems. Please advise.

operation as needed.

004 Please confirm the Testing, Adjusting and Balancing scope of work is for the existing HVAC systems and the 3 new exhaust fans only.

Please provide the rest of the Mechanical drawings for Bldg. 530. We need to see the Air distribution plans that show each grill, registers, etc.

Yes, confirmed.

See Drawings, MEP section, for reference mechanical drawings. The drawings included in the solicitation package is the information available. Contractor site verification is required to confirm information in drawings.

005 Is the scope of work limited to the Statement of Work and Bid Items/Tasks 1 through 35?

The reason I ask this is because there are items in the specifications and Development Construction Documents for PAD B530 Aquatics Center Reports that may not be part of the Statement of Work and Bid Items/Tasks 1 through 35.

For example, see the attached excerpt from Section 13 11 06 paragraphs 2.13 and 2.14 where a new carbon dioxide storage system and flow meters are called out. There is nothing like this in the statement of work or bid items/tasks.

Tasks required are defined by the SOW. Specifications may cover work not specifically required by this contract.

File details come from the government source that posted it. Updated .