RENOVATE CANTEEN PLAZA VA Project No. 640-12-124P Palo Alto, CA VA Palo Alto Health Care System
02-06-13
SUSTAINABLE DESIGN REQUIREMENTS
01 81 11-1
SECTION 01 81 11
PART 1 - GENERAL
1.01 SUMMARY
A. This Section describes general requirements and procedures to comply with the Guiding Principles for Leadership in High Performance and Sustainable Buildings Memorandum of Understanding incorporated in the Executive Orders 13423 and 13514; Energy Policy Act of 2005 (EPA 2005) and the Energy Independence and Security Act of 2007 (EISA 2007).
1.02 OBJECTIVES
A. To maximize resource efficiency and reduce the environmental impacts of construction and operation, the Contractor during the construction phase of this project shall implement the following procedures:
1. Select products that minimize consumption of energy, water and non-renewable resources, while minimizing the amounts of pollution resulting from the production and employment of building technologies. It is the intent of this project to conform with EPA’s Five Guiding Principles on environmentally preferable purchasing. The five principles are:
a. Include environmental considerations as part of the normal purchasing process.
b. Emphasize pollution prevention early in the purchasing process.
c. Examine multiple environmental attributes throughout a product’s or service’s life cycle.
d. Compare relevant environmental impacts when selecting products and services.
e. Collect and base purchasing decisions on accurate and meaningful information about environmental performance.
2. Control sources for potential Indoor Air Quality (IAQ) pollutants by controlled selection of materials and processes used in project construction in order to attain superior IAQ.
3. Products and processes that achieve the above objectives to the extent currently possible and practical have been selected and included in these Construction Documents. The Contractor is responsible to maintain and support these objectives in developing means and methods for performing the work of this Contract and in proposing product substitutions and/or changes to specified processes.
4. Use building practices that insure construction debris and particulates do not contaminate or enter duct work prior to system startup and turn over.
1.03 RELATED DOCUMENTS
A. Section 01 74 19 CONSTRUCTION WASTE MANANGEMENT
B. Section 01 91 00 GENERAL COMMISSIONG REQUIREMENTS
1.04 DEFINITIONS
A. Agrifiber Products: Composite panel products derived from agricultural fiber
RENOVATE CANTEEN PLAZA VA Project No. 640-12-124P
01 81 11-2
B. Biobased Product: As defined in the 2002 Farm Bill, a product determined by the
Secretary to be a commercial or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products or renewable domestic agricultural materials (including plant, animal, and marine materials) or forestry materials
C. Biobased Content: The weight of the biobased material divided by the total weight of the product and expressed as a percentage by weight
D. Certificates of Chain-of-Custody: Certificates signed by manufacturers certifying that wood used to make products has been tracked through its extraction and fabrication to ensure that is was obtained from forests certified by a specified certification program
E. Composite Wood: A product consisting of wood fiber or other plant particles bonded together by a resin or binder
F. Construction and Demolition Waste: Includes solid wastes, such as building materials, packaging, rubbish, debris, and rubble resulting from construction, remodeling, repair and demolition operations. A construction waste management plan is to be provided by the Contractor as defined in Section 01 74 19.
G. Third Party Certification: Certification of levels of environmental achievement by nationally recognized sustainability rating system.
H. Light Pollution: Light that extends beyond its source such that the additional light is wasted in an unwanted area or in an area where it inhibits view of the night sky
I. Recycled Content Materials: Products that contain pre-consumer or post-consumer materials as all or part of their feedstock
J. Post-Consumer Recycled Content: The percentage by weight of constituent materials that have been recovered or otherwise diverted from the solid-waste stream after consumer use
K. Pre-Consumer Recycled Content: Materials that have been recovered or otherwise diverted from the solid-waste stream during the manufacturing process. Pre-consumer content must be material that would not have otherwise entered the waste stream as per Section 5 of the FTC Act, Part 260 “Guidelines for the Use of Environmental Marketing Claims”:
www.ftc.gov/bcp/grnrule/guides980427
L. Regional Materials: Materials that are extracted, harvested, recovered, and manufactured within a radius of 250 miles (400 km) from the Project site
M. Salvaged or Reused Materials: Materials extracted from existing buildings in order to be reused in other buildings without being manufactured
N. Sealant: Any material that fills and seals gaps between other materials
O. Type 1 Finishes: Materials and finishes which have a potential for short-term levels of off gassing from chemicals inherent in their manufacturing process, or which are applied in a form requiring vehicles or carriers for spreading which release a high level of particulate matter in the process of installation and/or curing.
http://www.ftc.gov/bcp/grnrule/guides980427
RENOVATE CANTEEN PLAZA VA Project No. 640-12-124P
01 81 11-3
P. Type 2 Finishes: “Fuzzy" materials and finishes which are woven, fibrous, or porous in nature and tend to adsorb chemicals offgas
Q. Volatile Organic Compounds (VOCs): Any compound of carbon, excluding carbon monoxide, carbon dioxide, carbonic acid, metallic carbides or carbonates, and ammonium carbonate, which participates in atmospheric photochemical reactions.
Compounds that have negligible photochemical reactivity, listed in EPA 40 CFR 51.100(s), are also excluded from this regulatory definition.
1.05 SUBMITTALS
A. Sustainable Design Submittals:
1. Alternative Transportation: Provide manufacturer’s cut sheets for all bike racks installed on site, including the total number of bicycle storage slots provided.
Also, provide manufacturer’s cut sheets for any alternative-fuel refueling stations installed on site, including fueling capacity information for an 8-hour period.
2. Heat Island Effect:
a. Site Paving: Provide manufacturer’s cut sheets for all impervious paving materials, highlighting the Solar Reflectance Index (SRI) of the material.
Also, provide cut sheets for all pervious paving materials.
3. Exterior Lighting Fixtures: Submittals must include cut sheets with manufacturer’s data on initial fixture lumens above 90° from nadir for all exterior lighting fixtures, and, for parking lot lighting, verification that the fixtures are classified by the IESNA as “full cutoff” (FCO); OR provide documentation that exterior luminaires are IDA-Approved as Dark-Sky Friendly by the International Dark Sky Association (IDA) Fixture Seal of Approval Program.
4. Irrigation Systems: Provide manufacturer’s cut sheets for all permanent landscape irrigation system components and for any rainwater harvesting system components, such as cisterns.
5. On-Site Renewable Energy Systems: Provide cut sheets and manufacturer’s product data for all on-site renewable energy generating components and equipment, including documentation of output capacity.
6. Measurement and Verification Systems: Provide cut sheets and manufacturer’s product data for all controls systems, highlighting electrical metering and trending capability components
7. Salvaged or Reused Materials: Provide documentation that lists each salvaged or reused material, the source or vendor of the material, the purchase price, and the replacement cost if greater than the purchase price.
8. Recycled Content: Submittals for all materials with recycled content (must include the following documentation: Manufacturer’s product data, product literature, or a letter from the manufacturer verifying the percentage of post-consumer and pre-consumer recycled content (by weight) of each material or product
a. An electronic spreadsheet that tabulates the Project’s total materials cost and combined recycled content value (defined as the sum of the post-consumer recycled content value plus one-half of the pre-consumer recycled content value) expressed as a percentage of total materials cost. This spreadsheet shall be submitted every third month with the Contractor’s Certificate and Application for Payment. It should indicate, on an ongoing basis, line items for each material, including cost, pre-consumer recycled content, post-consumer recycled content, and combined recycled content value.
RENOVATE CANTEEN PLAZA VA Project No. 640-12-124P
01 81 11-4
9. Regional Materials: Submittals for all products or materials expected to contribute to the regional calculation must include the following documentation:
a. Cost of each material or product, excluding cost of labor and equipment for installation
b. Location of product manufacture and distance from point of manufacture to the Project Site
c. Location of point of extraction, harvest, or recovery for each raw material in each product and distance from the point of extraction, harvest, or recovery to the Project Site
d. Manufacturer’s product data, product literature, or a letter from the manufacturer verifying the location and distance from the Project Site to the point of manufacture for each regional material
e. Manufacturer’s product data, product literature, or a letter from the manufacturer verifying the location and distance from the Project Site to the point of extraction, harvest, or recovery for each regional material or product, including, at a minimum, gravel and fill, planting materials, concrete, masonry, and GWB.
f. An electronic spreadsheet that tabulates the Project’s total materials cost and regional materials value, expressed as a percentage of total materials cost. This spreadsheet shall be submitted every month with the Contractor’s Certificate and Application for Payment. It should indicate on an ongoing basis, line items for each material, including cost, location of manufacture, distance from manufacturing plant to the Project Site, location of raw material extraction, and distance from extraction point to the Project Site.
10. Outdoor Air Delivery Monitoring: Provide manufacturer’s cut sheets highlighting the installed carbon dioxide monitoring system components and sequence of controls shop drawing documentation, including CO2 differential set-points and alarm capabilities.
11. Exterior Paints and Coatings: Submittals for all field-applied paints and coatings, which have a potential impact on ambient air quality, must include manufacturer’s MSDSs or other manufacturer’s Product Data highlighting VOC content.
12. Composite Wood and Agrifiber Binders: Submittals for all composite wood and agrifiber products (including but not limited to particleboard, wheatboard, strawboard, agriboard products, engineered wood components, solid-core wood doors, OSB, MDF, and plywood products) must include manufacturer’s product data verifying that these products contain no urea-formaldehyde resins.
13. Seating: Provide manufacturer’s product data verifying that all seating products meet the requirements of one of the following:
a. Greenguard certification
14. Mercury in Lighting: Provide manufacturer’s cut sheets or product data for all fluorescent or HID lamps highlighting mercury content.
15. Lighting Controls: Provide manufacturer’s cut sheets and shop drawing documentation highlighting all lighting controls systems components.
16. Blended Cement: It is the intent of this specification to reduce CO2 emissions and other environmentally detrimental effects resulting from the production of portland cement by requiring that all concrete mixes, in aggregate, utilize blended cement mixes to displace portland cement as specified in Section 03 30 00, CONCRETE typically included in conventional construction. Provide the following submittals:
a. Copies of concrete design mixes for all installed concrete
b. Copies of typical regional baseline concrete design mixes for all compressive strengths used on the Project
c. Quantities in cubic yards of each installed concrete mix
RENOVATE CANTEEN PLAZA VA Project No. 640-12-124P
01 81 11-5
17. Green Housekeeping: Provide documentation that all cleaning products and meet the VOC limits and content requirements of this specification section.
B. Project Materials Cost Data: Provide a spreadsheet in an electronic file indicating the total cost for the Project and the total cost of building materials used for the Project, as follows:
1. Not more than 60 days after the Preconstruction Meeting, the General Contractor shall provide to the Owner and Architect a preliminary schedule of materials costs for all materials used for the Project organized by specification section.
Exclude labor costs and all mechanical, electrical, and plumbing (MEP) systems materials and labor costs. Include the following:
a. Identify each reused or salvaged material, its cost, and its replacement value.
b. Identify each recycled-content material, its post-consumer and pre-consumer recycled content as a percentage the product’s weight, its cost, its combined recycled content value (defined as the sum of the post-consumer recycled content value plus one-half of the pre-consumer recycled content value), and the total combined recycled content value for all materials as a percentage of total materials costs.
c. Identify each regional material, its cost, its manufacturing location, the distance of this location from the Project site, the source location for each raw material component of the material, the distance of these extraction locations from the Project site, and the total value of regional materials as a percentage of total materials costs.
d. Identify each biobased material, its source, its cost, and the total value of biobased materials as a percentage of total materials costs. Also provide the total value of rapidly renewable materials (materials made from plants that are harvested in less than a 10-year cycle) as a percentage of total materials costs.
e. Identify each wood-based material, its cost, the total wood-based materials cost, each FSC Certified wood material, its cost, and the total value of Certified wood as a percentage of total wood-based materials costs.
2. Provide final versions of the above spreadsheets to the Owner and Architect not more than 14 days after Substantial Completion.
C. Construction Waste Management: See Section 01 74 19 “Construction Waste Management” for submittal requirements.
D. Sustainable Design Progress Reports: Concurrent with each Application for Payment, submit reports for the following:
1. Construction Waste Management: Waste reduction progress reports and logs complying with the requirements of Section 01 74 19 ”Construction Waste Management.”
1.06 QUALITY ASSURANCE
A. Preconstruction Meeting: After award of Contract and prior to the commencement of the Work, schedule and conduct meeting with Owner, Architect, and all Subcontractors to discuss the Construction Waste Management Plan, and all other Sustainable Design Requirements. The purpose of this meeting is to develop a mutual understanding of the Project’s Sustainable Design Requirements and coordination of the Contractor’s management of these requirements with the Contracting Officer and the Construction Quality Manager.
RENOVATE CANTEEN PLAZA VA Project No. 640-12-124P
01 81 11-6
B. Construction Job Conferences: The status of compliance with the Sustainable Design
Requirements of these specifications will be an agenda item at all regular job meetings conducted during the course of work at the site.
PART 2 - PRODUCTS
2.01 PRODUCT ENVIRONMENTAL REQUIREMENTS
A. Site Clearing: Topsoil shall be provided by the Contractor from on-site material which has been stockpiled for reuse. Off-site borrow should only be used when on-site sources are exhausted. Chip and/or compost on site all vegetated material identified for removal.
B. Do not burn rubbish, organic matter, etc. or any material on the site. Dispose of legally in accordance with Specifications Sections 01 74 19.
C. Exterior Lighting Fixtures:
1. All exterior luminaires must emit 0% of the total initial designed fixture lumens at an angle above 90° from nadir and/or meet the requirements of the Dark Sky certification program.
2. Exterior lighting cannot exceed 80% of the lighting power densities defined by ASHRAE/IESNA Standard 90.1-2004, Exterior Lighting Section, without amendments.
3. No lighting of building facades or landscape features is permitted.
D. Herbicides and Pest Control: Herbicides shall not be permitted, and pest control measures shall utilize EPA-registered biopesticides only.
E. Landscape Irrigation: Use water-efficient landscape and irrigation strategies, including water reuse and recycling, to reduce outdoor potable water consumption by a minimum of 50 percent over that consumed by conventional means (plant species and plant densities).
Water-Conserving Fixtures: Plumbing fixtures and fittings shall use in aggregate at least 20% less water than the water use baseline calculated for the building after meeting the Energy Policy Act of 1992 fixture performance requirements.
F. Appliances and Equipment: All materials and equipment being installed that falls under the Energy Star or FEMP programs must be Energy Star or FEMP-rated. Eligible equipment includes motors, and more. Refer to each program’s website for a complete list.
G. The IPMVP provides guidance on situation-appropriate application of measurement and verification strategies.
H. Salvaged or Reused materials: There shall be no substitutions for specified salvaged and reused materials and products.
1. Salvaged materials: Use of salvaged materials reduces impacts of disposal and manufacturing of replacements.
I. Recycled Content of Materials:
1. Provide building materials with recycled content such that post-consumer recycled content value plus half the pre-consumer recycled content value constitutes a minimum of 30% of the cost of materials used for the Project, RENOVATE CANTEEN PLAZA VA Project No. 640-12-124P
01 81 11-7 exclusive of all MEP equipment, labor, and delivery costs. The Contractor shall make all attempts to maximize the procurement of materials with recycled content.
a. e post-consumer recycled content value of a material shall be determined by dividing the weight of post-consumer recycled content by the total weight of the material and multiplying by the cost of the material.
b. Do not include mechanical and electrical components in the calculations.
c. Do not include labor and delivery costs in the calculations.
d. Recycled content of materials shall be defined according to the Federal
Trade Commission’s “Guide for the Use of Environmental Marketing Claims,” 16 CFR 260.7 (e).
e. Utilize all on-site existing paving materials that are scheduled for demolition as granulated fill, and include the cost of this material had it been purchased in the calculations for recycled content value.
f. The materials in the following list must contain the minimum recycled content indicated:
Category Minimum Recycled Content
Compost/mulch 100% post-consumer
Asphaltic Concrete Paving 25% post-consumer
Cast-in-Place Concrete 6% pre-consumer
CMU: Gray Block 20% pre-consumer
Steel Reinforcing Bars 90% combined
Structural Steel Shapes 90% combined
Steel Joists 75% combined
Steel Deck 75% combined
Steel Fabrications 60% combined
Steel Studs 30% combined
Steel Roofing 30% post-consumer
Aluminum Fabrications 35% combined
Rigid Insulation 20% pre-consumer
Batt insulation 30% combined
J. Biobased Content:
1. For products designated by the USDA’s BioPreferred program, provide products that meet or exceed USDA recommendations for biobased content, so long as products meet all other performance requirements in VA master specifications. For more information regarding the product categories covered by the BioPreferred program, visit http://www.biopreferred.gov
- - - E N D OF SECTION - - -