SECTION 01 56 26
TEMPORARY FENCING
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Temporary construction fencing around construction, staging, and storage areas.
PART 2 PRODUCTS
2.1 TEMPORARY FENCING
A. Chain link, 2.1m (7 feet) minimum height.
B. Fence posts driven, in lieu of concrete bases, where soil conditions permit.
C. Plastic strip inserts, colored green so that visibility through the fence is obstructed.
1. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches).
D. Provide gates as required for access, including hasps and padlocks.
E. Bottom of fences shall extend to within 50 mm (2 inches) above grade.
PART 3 EXECUTION
3.1 FENCING INSTALLATION AND MAINTENANCE
A. Provide fencing before construction operations begins.
B. Ensure fence stability.
C. Stage equipment or materials out of public view with the exception of those items which are in support of ongoing Work on any given day.
D. Keep fence in state of good repair and proper alignment.
E. Remove fencing when directed by COR.
--- End of Section ---