36C26118B0042 Amendment 0004 Request for Information Questions 2-15 answered under Amendment 0003
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE
OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
BY
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 00004 01-14-2018 640-18-1-5281-0013 640-12-124P Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Sierra Nevada Health Care System 975 Kirman Avenue Reno
NV
89502-2597 Department of Veterans Affairs VA Sierra Pacific Network (VISN 21) VA Sierra Nevada Health Care System 975 Kirman Avenue Reno
NV
89502-2597 To all Offerors/Bidders
36C26118B0042 12-04-2017
X X X 640-18-1-5281-0013 X The purpose of this amendment is to provide responses to Request for Information (RFI's).
The request for information (RFI) deaadline is Thursday, January 25, 2018 at 3:00 PM Pacific. Questions received after that date may not be answered.
All other terms and conditions shall remain unchanged.
Question 16 Paragraph 2.04 in spec section 129300 mentions a drain cover by Urban Accessories. However, I do not see these shown on the plans to identify quantity and also if they are OFOI, OFIC, or CFCI. Will the VA please clarify.
Answer 16 - Delete Paragraph 2.04 and any associated drain cover (by Urban Accessories) scope.
Question 17 - Paragraph 2.02 in spec section 129300 mentions surface mounted benches that are furnished and installed by the contractor. However, section 2 on sheet LP2.1.1 refers to the same Bench but states that it is OFCI. Will the VA please clarify?
Answer 17 - Delete OFCI note on Section 2 / LP2.1.1. All benches are CFCI.
Question 18 – Request to know the current light poles to be removed/recycled according to drawing E1.1 and C2.1.
Answer 18 - Response: Contractor shall be responsible to remove and dispose as required.
Question 19 - Lighting requirements in the drawing E0.1 list Bega as the manufacture for the lighting schedule. However, there is no quaintly identified in the lighting schedule. Can you please clarify quantity required for each item?
Answer 19 - Contractor shall count the quantity of each light fixture type per drawings E2.1, E2.2 and E2.3.
Question 20 - In the spec section 2. 10 DIVISON 26 – ELECTRICAL lists the manufacture exterior finishing, however KIM doesn’t not have MFR part number. Where can we find the quantity for each item listed in this section.
| A. SECTION 26 56 00, SITE LIGHTING Type and Component |
| Exterior Finish |
| Manufacturer |
| Mfg. Name/No. |
| C, In-grade |
| Manufacturer’s Polyester |
| Kim |
Answer 20 - KIM in-grade up-light is not needed. See the latest drawing set.
Type C is deleted. See drawing E0.1 for the updated fixture type D and type F spec.
Question 21 (similar to previous question, just re-stating) What size is needed for the Urban Accessories OPCB drain cover, What type of frame is needed? (new concrete, existing concrete, paver), Quantity needed?, What is the load rating?
Answer 21 - Delete Paragraph 2.04 and any associated drain cover (by Urban Accessories) scope.
Add additional as necessary: Delete OFCI note on Section 2 / LP2.1.1. All benches are CFCI.