01 14 16
COORDINATION WITH OCCUPANTS
PART 1 GENERAL
(Not Used.)
PART 2 PRODUCTS
(Not Used.)
PART 3 EXECUTION
3.1 AVOIDANCE OF INTERUPTION
0. No utility service such as water, gas, steam, sewer, electricity, fire protection, or communications systems may be interrupted without prior approval of COR.
0. Reduction of Noise: Minimize noise using every action possible. Perform noise-producing work in less sensitive hours of the day or week as directed by the Construction Project Manager/COR. Work may be required to occur outside of normal working hours.
1. Use shields or other physical barriers to restrict noise transmission.
2. Provide soundproof housings or enclosures for noiseproducing machinery.
3. Use efficient silencers on equipment air intakes.
4. Use efficient intake and exhaust mufflers on internal combustion engines that are maintained so equipment performs below noise levels specified.
5. Line hoppers and storage bins with sound deadening material.
6. Conduct truck loading, unloading, and hauling operations so that noise is kept to a minimum.
-- End of Section –