About this file

This is Amendment 004 to Solicitation 36C25926R0082, issued by the Department of Veterans Affairs Network Contracting Office NCO 19 on September 23, 2026, for Project 635-21-139, Repair Parking Garage 1 Deficiencies. The amendment extends the proposal submission deadline to October 5, 2026, at 11:30 AM CDT and provides responses to a second set of questions with supporting documentation. All proposals must be emailed to Christina Beeler-Blackburn at Christina.beelerblackburn@va.gov. The scope involves comprehensive repairs to Parking Garage 1 located at 921 NE 13th Street, Oklahoma City, Oklahoma 73104, adjacent to the Oklahoma City VA Medical Center.

The work encompasses parking striping and signage, ADA compliance sidewalk repairs, suicide prevention installation, a new stairwell on the south side, and updates to civil, architectural, electrical, lighting, wayfinding, low voltage, and structural systems. The contractor must provide third-party commissioning and maintain Level 1 ICRA infection control precautions while working in the first-floor hallway adjacent to active patient and staff areas. The contract period is 270 calendar days after Notice to Proceed, with construction limited to Monday through Friday, 7:30 AM to 3:30 PM, excluding federal holidays. The contractor must comply with applicable codes including OSHA, NFPA 101, NFPA 70, and VA standards, maintain a Site Superintendent with a 30-hour OSHA card, and ensure all employees complete minimum 10-hour OSHA construction safety training. The base line item pricing is provided on a lump sum basis with the NAICS code 236220 (Commercial and Institutional Building Construction) and PSC Z2DA (Repair or Alteration of Hospitals).

View the file

Other files

File Type Posted
36C25926R0082 Amend 0007.pdf PDF
36C25926R0082Amend 0006.pdf PDF
019100-2022-04 general comissioning requirements.docx DOCX document
635-21-139 Questions and Responses 3.docx DOCX document
280800-2016-11 comissioning of electronic and security systems.docx DOCX document
36C25926R0082 Amend 0005.pdf PDF
635-21-139 Questions and Responses 2.docx DOCX document
055000-2.0_Metal Fabrications-SD_ASI_ACG_VA.pdf PDF
055000-6.0_Metal Fabrications-Suicide Fence-SD_ASI_ACG.pdf PDF
36C25926R0082 0003.docx DOCX document
2nd Site Visit Meeting Doc_635-21-139 Repair Parking Garage 1.docx DOCX document
36C25926R0082 0002.docx DOCX document
635-21-139 2nd Site visit Sign in sheet 08-25-2026.pdf PDF
S06- 36C25926R0082 0001.docx DOCX document
Terracon Project No. 03235201 Rev 1 VAMC Parking Garage Stair Tower GEO ENG RPT 12-19-2024 - signed.pdf PDF
S04- 635-21-139 Site Visit Sign in sheet 07-29-2026.pdf PDF
Site Visit Meeting Doc_635-21-139 Repair Parking Garage 1.docx DOCX document
635-21-139 Questions and Responses.docx DOCX document
36C25926R0082_1.docx DOCX document
S02-3-10-2021 Past Performance Questionnaire_Blank_Fillable PDF.pdf PDF
S22 LOS Certification 852.219-75_JAN 2023 DEVIATION.docx DOCX document
Site Map for site visit 635-21-139.pdf PDF
635-21-139 OKC PARKING GARAGE Combined Drawings.pdf PDF
S02 - Prime and Sub Contractor Construction Breakdown.xlsx XLSX spreadsheet
00-Specifications 635-21-139.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25926R0082 Amendment 004

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 7

0004 09-23-2026

635-21-139

36C259

Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111

36C259

Department of Veterans Affairs Network Contracting Office

NCO 19

6162 South Willow Drive, Suite 300 Greenwood Village CO 80111

To all Offerors/Bidders

36C25926R0082

07-23-2026

X

X X

** HOUR & DATE for Receipt of Offers is EXTENDED to: 10-05-2026 11:30 AM CDT

See CONTINUATION Page

See attached page 2.

CONTINUATION PAGE

AN AMENDMENT TO SOLICITATION 36C25926R0082 POSTED ON SEPTEMBER 23, 2026.

The purpose of this amendment is as follows:

A) Post responses to 2nd set of questions and supporting documentation.

B) Post updated SOW (changes in Blue font).

C) Extend proposal due date. Proposals due on October 5, 2026 @ 11:30 AM CST.

D) All proposals will be emailed to Christina Beeler-Blackburn via Christina.beeler-blackburn@va.gov.

All other terms and conditions remain the same.

A.1 STATEMENT OF WORK

Project 635-21-139, Repair Parking Garage 1 Deficiencies

OBJECTIVE:

The purpose of the project is to address the defects and deficiencies of the existing Parking Garage 1. The contractor shall furnish all equipment, materials, labor, supervision, and quality control to perform work for VA Project 635-21-139 Repair Parking Garage 1 Deficiencies located East of the VA Medical Center main building at the corner of NE 13th street and N. Kelly Avenue, Oklahoma City, Oklahoma 73104.

SCOPE OF WORK:

This summary is not intended to be all inclusive and does not absolve the contractor of responsibility to address the defects and deficiencies of the Parking Garage 1 consistent with the contents of the specs and/or drawings.

• Bidders are responsible for the entirety of the project scope described in the contract documents (drawings and specifications) and shall submit RFI’s on any conflicts between drawings and specifications immediately that may impact bids.

• Bidders are responsible for all work specified or shown in the bid documents including the Statement of Work, Drawings, and Specifications.

• Work includes but is not limited to the following: Parking striping and signage, fixing a sidewalk that is not ADA compliant, installing suicide prevention, providing a new stairwell on the south side of the parking garage.

• Civil, architectural, electrical, lighting, wayfinding, low voltage, and structural systems are included in this project.

• Contractor will provide 3rd party commissioning for the project.

• Contractor will ensure level 1 ICRA precautions are in place as they work in the first-floor hallway as the adjacent areas will remain in use for patients and staff.

The contractor shall comply with all requirements listed in the project solicitation including the construction drawings, the project specifications, and all solicitation amendments as may be issued. These documents will be followed during construction and shall be considered project requirements.

The areas adjacent to the proposed addition shall be continuously occupied by the OKC VAMC.

The Contractor shall implement phasing to ensure that the construction will not impact or impede the VAMC’s mission to care for the Veterans.

The contractor shall provide quality control of all work conducted and the individual appointed shall be competent and educated/experienced in the field of work this scope encompasses.

Codes and Standards: The Contractor shall follow all applicable codes and standards to this type of work including but not limited to Health Care System Memorandums (HCSM), OSHA Guidelines, NFPA 101, NFPA 70, Lock-out-Tag-out, and Rules of Station.

Period of Performance:

• 270 calendar days after Notice to Proceed (NTP).

Task Management:

Engineering shall identify a Contracting Officer’s Representative (COR). The COR will provide technical assistance and clarification required for the performance of this contract, participate in project meetings, review invoices, and receive deliverables. After contract award, the Contracting Officer will appoint a COR and issue a COR appointment letter stating the authority for the COR. The contractor will receive a copy of the written appointment.

The Dept. of Veterans Affairs (VA) requires strict adherence to the Code of Federal Regulations 29, Part 1926. This includes the requirement that the prime contractor have a “Competent Person” known as site superintendent on the job at all times (must have a 30-hour OSHA card), and that all contractor and subcontractor employees have received a minimum of ten (10) hours of OSHA construction safety training. Documentation of these requirements shall be submitted and approved prior to performing the work. The “Site Superintendent” will be the responsibility of the Prime contractor and cannot be further delegated.

Storage and Security:

Contractor shall be responsible for storage and security of the project site at East of the VA Medical Center main building (921 NE 13th Street, Oklahoma City, Oklahoma 73104) at the corner of NE 13th street and N. Kelly Avenue, Oklahoma City, Oklahoma 73104. Contractor shall request Contracting Officer approve use bonded and insured off-site storage locations and COR shall access to view off-site stored materials and equipment.

Parking:

Contractor’s personnel can park within project site, park on the fourth floor of the Parking Garage or utilize street parking in the neighborhood. Contractor shall not utilize adjacent parking lot for The Cathedral of Our Lady of Perpetual Help. Oklahoma City VA Medical Center shall not waive or make reimbursement for parking violations of the Contractor’s personnel under any circumstances.

Work Hours:

Construction shall be performed during normal working hours Monday – Fridays from 7:30 am to 3:30 pm excluding federal holidays unless requested and approved by the COR and 14-day notice is required. Federal holidays include:

New Year's Day January 1st

Martin Luther King's Birthday Third Monday in January

President's Day Third Monday in February

Memorial Day Last Monday in May

Juneteenth June 19th

Independence Day July 4th

Labor Day First Monday in September

Columbus Day Second Monday in October

Veterans Day November 11th

Thanksgiving Day Fourth Thursday in November

Christmas Day December 25th

When a holiday falls on a Sunday, the following Monday shall be observed as a legal holiday.

When a holiday falls on a Saturday, the preceding Friday is observed as a legal holiday by U.S.

Government agencies. Also, included, would be any other day specifically declared by the President of the United States of America to be a National Holiday.

Delivery Location:

All work related to this contract shall be performed at the Parking Garage 1 located East of the VA Medical Center main building (921 NE 13th Street, Oklahoma City, Oklahoma 73104) at the corner of NE 13th street and N. Kelly Avenue, Oklahoma City, Oklahoma 73104

Payment Information:

The contractor shall provide the following payment information for VA use. It must be an exact match with the information under the contract number in the Contract Registration (not the contractor’s company or individual representative’s registration) as well as with the information under the contractor’s DUNS number in the System Award for Management http://www.SAM.gov. Mismatched information will result in rejected invoice.

a. Company Name – Legal Business Name and DBA (Doing Business As) Name

b. Mailing Address – Contact and Address Information http://www.sam.gov/

c. Remittance Address – Remit To Address Information

d. Employer’s Identification Number – Federal Tax ID

e. DUNS (Data Universal Numbering System)

CODES, STANDARDS AND EXECUTIVE ORDERS:

VA has adopted the latest edition of the following codes and standards as a minimum for all projects performed in the modernization, alteration, addition, or improvement of its real property and the construction of new structures. VA design Manuals and Master Specifications specify other codes and standards that VA follows on its projects:

VA Directives, Design Manuals, Master Specifications, VA National CAD Standard Application Guide, and other Guidance on the Technical Information Library (TIL) (http://www.cfm.va.gov/til/).

PG-18-1 Master Construction Specifications

PG-18-3 Design and Construction Procedures

PG-18-4 Standard Details and CAD Standards

VA BIM Manual V2.2

PG-18-5 Equipment Guide List

H-18-8 VA Seismic Design Handbook

PG-18-9 Space Planning Criteria

PG-18-10 Design Manuals (by discipline)

PG-18-12 Design Guides (graphical, by function)

PG-18-13 Barrier Free Design Guides

PG-18-14 Room Finishes, Door, and Hardware Schedules (consult COR for local standards)

PG-18-15 Minimum Requirements for A/E Submissions

PG-18-17 Environmental Compliance Manual

H-7545 VA Cultural Resource Management

VA Handbook 0056, Sustainable Building Program

VA Directive 0056, Sustainable Building Program

VA Directive 0055, VA Energy and Water Management Program

NFPA 101 Life Safety Code http://www.cfm.va.gov/til/

NFPA National Fire Codes

International Building Code (IBC) and all other International Code Series (IPC, IMC, IECC, IFGC, etc.) when applicable or referenced in VA Design documents/ guides.

Occupational, Safety and Health Administration (OSHA) Standards.

National Electrical Code (NEC)

Safety Code for Elevators and Escalators, American Society of Mechanical Engineers (ASME) A 17.1.

ASME Boiler and Pressure Vessel Code

ASME Code for Pressure Piping

Architectural Barriers Act Accessibility Standards (ABAAS) including VA supplement, Barrier Free Design Guide (PG-18-13)

Building Code Requirements for Reinforced Concrete, American Concrete Institute and Commentary (ACI 318)

Manual of Steel Construction, Load and Resistance Factor Design Specifications for Structural Steel Buildings, American Institute of Steel Construction (AISC)

Energy policy Act of 2007 (EPAct)

DOE Interim Final Rule: Energy Conservation Standards for New Federal, Commercial and Multi-Family High-Rise Residential Buildings and New Low-Rise Residential Buildings, 10 CFR Parts 433, 434 and 435.

Federal Leadership in High Performance and Sustainable Buildings: Memorandum of Understanding (MOU)

Executive Order 13423: Strengthening Federal Environmental, Energy, and Transportation Management.

The Provisions for Construction and Safety Signs. Stated in the General Requirements Section 01010 of the VA Master Construction Specification.

Ventilation for Acceptable Indoor Air Quality – ASHRAE Standard 62.1- 2013.

Safety Standard for Refrigeration Systems – ASHRAE Standard 15 – 2016.

A.2 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBER

DESCRIPTION OF

SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

1.00 JB __________________ __________________

Base Line item: Repair Parking Garage 1 Deficiencies

PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries POP: 270 calendar days after NTP

GRAND TOTAL __________________

A.3 LIST OF ATTACHMENTS

See attached document: 055000-2.0_Metal Fabrications-SD_ASI_ACG_VA.

See attached document: 055000-6.0_Metal Fabrications-Suicide Fence-SD_ASI_ACG.

See attached document: 635-21-139 Questions and Responses 2.

A.1 STATEMENT OF WORK
A.2 PRICE/COST SCHEDULE
ITEM INFORMATION

A.3 LIST OF ATTACHMENTS