Correct Tunnel Discrepancies RFIs.docx

DOCX document 18 KB Posted

Attached to
Z2NB-- Project 667-18-101 Correct Tunnel Discrepancies Federal contract opportunity
Solicitation number
36C25621R0158
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 16

About this file

This document contains a request for information (RFI) related to a federal contract opportunity to correct tunnel discrepancies at the Overton Brooks VA Medical Center. The RFI addresses questions about welding and inspection requirements, safety protocols around barriers and walkways, acceptable coating materials, fastening methods, submittal and reporting software, and points of contact. Responses provide clarification on welding certification and inspection needs, allow waiving of barriers where unsafe, accept alternate coating and fastening materials, and confirm submittal software and contracting officer contact information. The related federal contract opportunity posting specifies a 100% small business set-aside for service-disabled veteran-owned small businesses (SDVOSB) to correct tunnel discrepancies at the Overton Brooks VA Medical Center through request for proposal procedures. Offerors must be registered and verified as SDVOSBs, with proposals due around August 15, 2021 and contract award anticipated around 30 days later. The performance period is 200 calendar days with a construction cost between $500,000 and $1,000,000 and NAICS code 236220.

View the file

Other files for this federal contract opportunity

Other files attached to Z2NB-- Project 667-18-101 Correct Tunnel Discrepancies, newest first.
File Type Posted
Correct Tunnel Discrepancies - RFI 02.docx DOCX document
36C25621R0158 0005.docx DOCX document
AD103 ADD 1.pdf PDF
36C25621R0158 0004.docx DOCX document
36C25621R0158 0003.docx DOCX document
667-18-101 - Tunnel Project - Sign In Sheet 08.10.2021.pdf PDF
02 82 13_13 GLOVEBAG ASBESTOS ABATEMENT - Revised 08-11-2021.pdf PDF
02 82 11 TRADITIONAL ASBESTOS ABATEMENT - Revised 08-09-2021.pdf PDF
36C25621R0158 0002.docx DOCX document
36C25621R0158 0001.docx DOCX document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY SURVEY (1).docx DOCX document
Exhibit B Past and Present Performance Questionnaire.docx DOCX document
07 - SOW Correct Tunnel Discrepancies - Rev 5-13-21.pdf PDF
EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY v2.docx DOCX document
EXHIBIT E SURETY FORM.docx DOCX document
General Decision Number LA20210031 Mod 2 dated June 18 2021.docx DOCX document
15 - ACM Survey - Correct Tunnel Discrepancies.pdf PDF
14 - ICRA - Correct Tunnel Discrepancies - Preliminary.docx DOCX document
12 - DRWGS - Correct Tunnel Discrepancies.pdf PDF
36C25621R0158_1.docx DOCX document
15 - Class II Precautions - Correct Tunnel Discrepancies - Preliminary.docx DOCX document
Revised 7-22-21_667-18-101_Construction Documents_Specs.pdf PDF
21_M201R - REVISED 07.20.21.pdf PDF
Show all 24

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI #:01 Correct Tunnel Discrepancies

1. Specification requirements in Section 05 12 00 & 05 50 00 in the VA CFM.VA.Gov/til/Spec.asp-08 require all steel to be fabricated and welded by an ASCHE Certified Fabricator and Welders. Will these requirements apply to this Project?

WELDS AND WELDERS SHALL CONFORM TO AWS. REFER TO SPECIFCIATION.

1. Project Specifications provided by the Structural Engineer require a Contractor furnished Special Inspector. Can the limits of this requirement be provided by the VA?

WELDING INSPECTION IS REQUIRED PER DESIGNERS INSTRUCTIONS.

1. Will Radiographic Testing be required? If so can the VA identify the areas and limits?

Structurally radiographic testing will not be required.

1. SOW require the use of Secondary Barriers and Walkways placed along the working areas. Many steam line areas are not insulated or jacketed. The specified materials used in these Barriers cannot come in contact with the steam piping without melting. Will the Barriers be required in this project?

It is understood that this project is within a utility tunnel with steam pipework, where environmental conditions may not be conducive to safe placement of plastic barriers and walkways, given the presence of heat generating infrastructure. Where specific safety concerns, such as those outlined in this question, preclude the use of secondary construction barriers and walkways from being installed, the AOR shall allow this project requirement to be waived. These secondary barriers and walkways are typically required within work zones in order to safeguard life and avoid injuries during construction, however, in cases where it is unfeasible to install such barriers due to specific safety concerns which would be exasperated by their placement, the requirement shall be waived. At no time should a prescribed safety precaution cause more hazardous conditions due to its inclusion. The General Contractor remains wholly responsible for construction means and methods, including the safety of the work zone and workers within that zone; waiving requirements for barriers and walkways (by the AOR) does not lessen the Contractor’s responsibilities for job site safety. CONTRACTOR SHALL SUBMIT FOR AOR REVIEW ALL SAFETY PROTOCOLS TO BE FOLLOWED WITHIN THE WORK AREA, AND IN LIEU OF SECONDARY BARRIERS AND WALKWAYS WHERE UNFEASIBLE, TO DEMONSTATE THAT THE CONTRACTOR IS NONETHELESS SAFEGAURDING LIFE AND AVOIDING INJURY AS BEST AS ABLE GIVEN THE UNIQUE INTERIOR ENVIORNMENT.

1. Specifications require the Structural Steel to be painted and also touched up with galvanized repair compound. The products that are specified for these areas are volatile and create a safety hazard inside a Confined Space. Can other products be used such as materials compounded with 100% Solids?

Submit other products for review and approval.

1. In lieu of welding clips and anchors inside the Tunnel, can the brackets and steel beams be slot bolted?

This is acceptable with galvanized brackets, beams, nuts, bolts, and washers.

1. Will Engineered Structural Steel Shop Drawings be required for this project?

Yes

1. Will the VA allow a single individual to act as the Quality Control Manager (QCM), Site Safety & Health Officer (SSHO), and on-site Superintendent (Super) for the prime contractor on this project?

Yes, unless at any time during the performance period the contractor’s appointed individual fails to fulfill the role of each of the position requirements.

1. Will the government accept the use of Procore Project Management software as the primary submittal and data tracking tool for this project? The software is compatible with the VA’s networks and is currently in use at many VA locations.

Yes, Procore is acceptable.

1. The CO for this project, Kaitlyn West has two different email addresses in the instructions. Are we to use the addresses listed under each section or is this an error? If so, please provide the correct address.

Kaitlyn West email is Kaitlyn.West1@va.gov.