07 - SOW Correct Tunnel Discrepancies - Rev 5-13-21.pdf
PDF 84 KB Posted
- Attached to
- Z2NB-- Project 667-18-101 Correct Tunnel Discrepancies Federal contract opportunity
- Solicitation number
- 36C25621R0158
About this file
This document outlines a statement of work and related federal contract opportunity for correcting discrepancies in an underground utility corridor tunnel at the Overton Brooks VA Medical Center in Shreveport, Louisiana. The statement of work requires replacing the main steam line expansion joints and high-pressure manifold valves, correcting ground water infiltration, inadequate lighting, inferior finishes, failing utility support structures, deteriorated and inadequate insulation, asbestos, and leaks in various utilities. The delivery date is 200 days from notice to proceed. The related federal contract opportunity is a 100% set-aside for service-disabled veteran-owned small businesses soliciting proposals to complete the work outlined in the statement of work and attachments. Proposals are due around August 15, 2021 and award is anticipated within 30 days thereafter. The period of performance is 200 calendar days from notice to proceed. The construction cost range is between $500,000 to $1 million.
View the file
Other files for this federal contract opportunity
Show all 24
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work Correct Tunnel Discrepancies
Project No. 667-18-101
Overton Brooks VAMC, 510 E. Stoner Ave, Shreveport, LA has a requirement to correct discrepancies in the underground utility corridor tunnel from the sub-basement of the main hospital (Building 1) to the Boiler Plant (Building 3). This project shall correct the following discrepancies to include, but are not limited to, ground water infiltration, inadequate lighting, inferior finishes, failing utility support structures, deteriorated and inadequate insulation, asbestos and leaks in the various utilities present in the tunnel. The main steam line expansion joints and the high-pressure manifold valves shall be replaced and require a scheduled full steam outage. This project requires phasing and all utility interruptions shall be coordinated with the COR. All work performed shall be as determined within this scope of work, project drawings, and specifications. All work shall be performed as specified herein and shall be in accordance with all applicable codes indicated in the Department of Veterans Affairs (VA) Design Manuals and any other applicable codes. The Contractor shall provide all necessary labor, materials, tools, equipment, licenses, permits, and services for completion of this project. The Contractor shall be responsible for all damages to persons or property occurring because of the Contractor’s fault or negligence. The Contractor shall be responsible for all materials delivered and work performed until completion and acceptance of the entire work.
WORK HOURS
Most of the work shall be accomplished between the hours of 7:00am to 4:30pm Monday through Friday (excluding federal holidays); however, the contractor may be required to accomplish some work after hours or on weekends to minimize disruption to hospital operations. All work shall be coordinated with the COR.
ACCESS
Access to the construction area shall be through the subbasement exterior mechanical room entrance (near loading dock) and through the scuttle hole in the boiler plant.
PERIOD OF PERFORMANCE
The delivery date for this contract shall be 200 days from Notice to Proceed.
The “VAMC Coordinator” and COR (Contracting Officer’s Representative) for this project is Archie Lanham at 318-990-4721, archie.lanham@va.gov mailto:archie.lanham@va.gov