This document provides details for a federal contract solicitation to renovate behavioral health clinics at the VA Truman Memorial Veterans Hospital in Columbia, Missouri. The solicitation involves renovating approximately 9,706 square feet on the second floor and 5,089 square feet on the fourth floor to consolidate behavioral health services. The renovation will address patient flow and experience improvements and includes demolition and new construction of electrical, HVAC, plumbing, fire protection, data/voice, and interior finishes. The estimated price range for the project is $2,000,000 to $5,000,000. The North American Industry Classification System code is 236220 for general construction contractors up to $39.5 million. The performance period is up to 800 calendar days from notice to proceed to contract closeout. The solicitation will be set aside for Service-Disabled Veteran-Owned Small Businesses and utilize the best value low price technically acceptable source selection process. The solicitation package will be available on or around June 1, 2021 with proposals due on or around July 9, 2021.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7.

ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF

PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE

OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO:

Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERE

D CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendmen t, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED

STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF

CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF

SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 589A4-19-103 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth KS 66048 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth KS 66048 To all Offerors/Bidders

36C25521R0089

X X X July 28,2021 by 2:00PM CDT Relocate Behavioral Health, 589A4-19-103 A. This amendment provides the sign in list from the Pre-bid meeting.

B. This amendment extends the proposal due date to July 28, 2021 proposals are due by 2:00 PM CDT C. This amendment provides the questions and answers submitted for this project.

D. This amendment provides changes to Drawings: 1-G1100, 1-AE104, 1-AE107, 1-AE707, 1 AE110A, 1-AE110B, 1-AE110C, 1-AE110D,1-AE110E, 1-AE110F, 1-AF101 and 1-AF102 E.This amendment provides changes to the following specifications: 07 95 13; 08 71 00; 27 15 00; 27 52 23; 28 05 00;

28 13 00.

E. All other terms and conditions remain unchanged.

CONTINUATION PAGE

Project# 589A4-19-103 Renovate Behavioral Health Clinic Pre-Bid Questions and Answers

QUESTION #1: Will you be replacing technology during this as well?

ANSWER #1: Yes

QUESTION #2: Will you be replacing furniture during this as well?

ANSWER #2: Some items, yes. Furniture will be by the VA

QUESTION #3: Substitution Request for Locker/Partition product-Hiny Hiders?

ANSWER #3: The product does not meet specifications and is rejected for the following reasons:

No baked enamel finish shown in the new specification which is required by the standard VA spec.

Recycled content should be 30% according to the VA standard spec. The new spec only show 25%.

Bolt/fasteners types are different from the VA standard spec.

New spec didn’t specify U-shaped brackets for securing edges of panels as required by the VA standard spec.

New spec didn’t specify U-type door pulls as required by the VA standard spec.

New spec doesn’t have Class C flame spreading; only Class A & B.

QUESTION #4: There is a specification section for Window Shades 12 24 00, there is a head detail for window shades, however there is not a callout for window shades on any of the windows. I would assume that the two new windows get new shades and the existing windows get the existing shades removed for demo and re-installed when complete. Please confirm.

ANSWER #4: New shades need to be provided on the second floor and fourth floor. See Addendum #1 drawings for added notes to keynote #23 on sheet AE102, and keynote #14 on sheet AE104.

QUESTION #5: SSU-1/CU-1 is shown with a refrigerant piping run of around 160’-170’ feet long. When the piping gets this long, it can derate/reduce capacity of the system. Is this acceptable, or would it make more sense to install the CU on the roof outside of the 2nd floor work area? Please advise.

ANSWER #5: CU-1 location to be on the 1st floor roof on the Northwest corner outside of room A200 with access through A200A. 2

QUESTION #6: Need some info on Electrical sheets 1-E-500 and 1-E-501. The Electrical Panels say “Existing Panels. Any additional shall match Manufacturer.” Can you tell me what the Existing Panel Manufacturer is? Eaton Cutler Hammer. Square D, GE, Siemens ANSWER #6 : The majority of panels are Square D, there are a few GE panels as well.

QUESTION #7. Please advise if the designated SSHO and Competent Person role can be fulfilled by the site superintendent.

ANSWER #7: Yes, for the majority of the cases the SSHO can be the competent person. Each sub will need a competent person on site while work is performed - usually the sub’s super (i.e. electrical, HVAC, asbestos).

QUESTION #8. Will the SSHO be full time separate person?

ANSWER #8: The SSHO IS a full-time position and shall be onsite whenever work is being performed. They do NOT have to be a separate person; it can be the superintendent.

QUESTION #9.Please verify who is furnishing and installing patient lifts?

ANSWER #9: The VA will have a patient lift contract that will include the purchase and installation.

QUESTION #10.Specification 0550000 specifies ceiling mounted items, please verify who will furnish and install the Patient lift support steel or uni strut.

ANSWER #10: The only reference to ceiling mounted items in 05 50 00 is for toilet stalls. As to patient lifts, this is part of the lift installation (VA contract).

QUESTION #11.Is the project taxable?

ANSWER #11: Awarded CG will be provided tax exempt forms.

QUESTION #12. Is there an Asbestos report applicable for this project?

ANSWER #12: There is a report. One area (A259) was identified has having mastic. It is unknown if this has been since removed. There are no other KNOWN items identified. Bid line item pricing is to be provided in the event that unknown items are encountered.

QUESTION #13. Is any portion of the area within the signage scope of work (Floors 2 & 4) a locked unit? Typically, these areas are provided an alternative material for the safety of the patients (Secure Spec).

ANSWER #13: There are no such areas within this project.

QUESTION #14. One the door schedule (1-AF101 & 1-AF102) it is saying that GL-1 is insulated glass but on the glazing spec it is saying that GL-1 is single pane laminated glass. Please clarify which glass type should be used.

ANSWER #14: GL-1 has been updated to be single pane laminated glass. See Sheet AF101 & AF102 Addendum #1 drawings.

QUESTION #15. Hardware set 5 is indicated to have double acting door hardware. The doors associated with hardware set 5 are 487 & 493. On the floor plan it is noted that these doors are supposed to have auto operators on them as well but there is no auto operator hardware in hardware set 5. Please confirm if these need auto operators?

ANSWER #15: a. No auto operators are required on these two doors. In the Addendum #1 drawings sheet AE104 Keynote #6 has been updated to state, “Provide Handwave Actuator (Overhead Door company of Central Missouri – basis of design or VA approved equal). Refer to door schedule sheet 1-AF102.” The hardware sets have been updated to state the above as well. See Addendum #1 door hardware spec.

QUESTION #16. Since this is behavioral health do special screws need to be used like torx screws and do the hinges need to have hospital tips on them? This is not indicated in any of the hardware spec.

ANSWER #16: No, there is no such requirement in this project.

QUESTION #17. Door 494 has comment on the door schedule that the doors needs to have delayed egress but there is no delayed egress hardware listed in hardware set 24. Please clarify if it does need delayed egress hard and which type.

• ANSWER #17: a. Delayed egress was added to hardware set 24. See Addendum #1 08 71 00 door hardware spec.

QUESTION #18.Door A200B has a note on the door schedule (1-AF101) about hardware set 116. What is that referring to?

ANSWER #18: Removed note regarding “SDO Hardware set 116”. See updated Addendum #1 drawings sheet 1-AF101.

QUESTION #19. It mentions the facility standard hand wave actuator in multiple hardware sets, what is the facility standard hand wave actuator?

ANSWER #19: Door hardware spec updated in Addendum #1 to state “Overhead Door Company of Central Missouri-Basis of Design or VA approved equal” for handwave actuator. Bidder has the responsibility to provide information that the product meets or exceeds specifications.

QUESTION #20. Drawing 1-AE707-detail 8 stair, please provide additional detail such as steel members sizes, or provide manufacturer basis of design if there is a specific manufacture preferred?

ANSWER #20: Note on sheet 1-AE707 in Addendum #1 drawings have been updated to state “New PHP systems/Design (Basis of design or VA approved equal) prefabricated steel roof access stairs and handrail”. The PHP Systems is a pre-engineered stair. Contractor will have to obtain field measurements, and call PHP or an equivalent manufacturer for pricing.

QUESTION #21. Drawing 1-AD103 note 1 remove and salvage furniture, equipment and fixtures? Will this be performed by the VA? If not, is there a list of furniture, equipment and fixtures that are to be salvaged? I think it was mentioned at the walk through everything was to be removed and thrown away in dumpsters, no salvage?

ANSWER #21: The VA should have removed everything prior to the area being turned over to the contractor. A walk through will be conducted with the COR and superintendent to verify/identify. Anything left after this walk through is the contractors for disposal.

QUESTION #22: Drawing 1-AD103 note 13, demo and replace expansion joint. Please provided specification and details for expansion joint.

ANSWER #22: Added spec section 07 95 13 expansion joint cover assemblies. See Addendum #1 specs.

QUESTION #23: AE110E keynote item #19 Rail accessory, please provide manufacturer and or details and specification for rail.

ANSWER #23: Note added to keynote #19 on sheet AE110E in Addendum #1 drawings to state “Welch Allyn-Basis of Design or VA approved equal”

QUESTION #24: Drawing 1-AE102 keynote 24, Patch, clean repair and level floors where needed. To what extent do the floors need to be leveled? Is it known if the floors are off by inches?

ANSWER #24: The bidder can assume a ¼” off level and bid labor materials based on that.

QUESTION #25: Drawing 1-AE102 keynote 12 demo replace expansion joint. Are we to demo and replace the entire length of building wing from column line 3.7 to column ?

ANSWER #25: Only expansion joint that is within the project area.

QUESTION #26: The current system is a Siemens Design Modular Voice system. Is this to be an extension of that system?

ANSWER #26: Yes

QUESTION #27: The specifications indicate “Guarantee Period Services”. In the past, the VA has chosen to not include that in the project specification as it adds additional cost to the project and that scope is covered under the VA Fire Alarm Service Agreement. Should we exclude the section 283100, 1.6 Guarantee Period Services?

ANSWER #27: There is NO “Guarantee Period Services”. Not in this section nor any other. Specifications will be updated accordingly.

QUESTION #28: There is not any detection in the corridors. This would be required by code. Should we include corridor detection?

ANSWER #28: Smoke detectors will be added. Refer to Addendum 001 supporting documents for locations and quantity of new detectors.

QUESTION #29: On plan sheet 1-MH500, there are 6 VAV boxes shown as “existing” in the notes. However, this is not called out on any of the plan sheets showing the demo or new installation. Are these VAV’s existing or new? Please advise.

• ANSWER #29: • On sheet 1-MH500 in the Single Duct Air Terminal Unit Schedule notes “Existing First Floor VAV box” under the Perimeter Supplemental Heat Link column. This indicates the new second floor box will be linked to the existing first floor box for perimeter heat. This work is shown on the control drawings.

MECHANICAL/ELECTRICAL/TECHNOLOGY ADDENDUM # 1

MECHANICAL:

SPECIFICATION ITEMS

1. None.

DRAWING ITEMS

1. Drawing 1-MP101: a. ADD CU-1 to the Northwest corner on the first floor roof outside of Room A200.

b. REVISE the refrigerant piping for the adjusted equipment location.

c. REFER to the attached drawing.

2. Drawing 1-MP102: REMOVE refrigerant and suction piping as indicated on attached drawing.

3. Drawing 1-MP103: REMOVE CU-1 and refrigerant and suction piping as indicated on attached drawing.

4. Drawing 1-MP300: a. REMOVE detail 5.

b. ADJUST the numbering of the Exterior Wall Penetration detail.

c. REFER the attached drawing.

ELECTRICAL:

SPECIFICATION ITEMS

2. Section 28 31 00: DELETE section 1.6 - GUARANTY PERIOD SERIVCES.

DRAWING ITEMS

5. Drawing 1-E-000 - ELECTRICAL COVERSHEET: ADD fire alarm door hold smoke detector.

6. Drawing1-EP101 - LEVEL 02 - ELECTRICAL POWER: a. ADD automatic door operator connections.

b. ADD fire alarm door hold smoke detectors.

c. ADD keynote #2.

d. ADD electrical connection for condensing unit CU-1 and associated fused disconnect switch.

7. Drawing 1- EP102 - LEVEL 04 - ELECTRICAL POWER: a. ADD automatic door operator connections.

b. REMOVE electrical connection for condensing unit CU-1 and associated fused disconnect switch.

8. Drawing 1-FA101 - LEVEL 02 - FIRE ALARM: a. ADD smoke detectors.

b. REMOVE two (2) corridor audio/visual devices.

9. Drawing 1-FA102 - LEVEL 04 - FIRE ALARM: ADD smoke detectors.

10. Drawing 1-E-300 - ELECTRICAL DETAILS: REVISE 1/1-E-300.

11. Drawing 1-E-500 - ELECTRICAL SCHEDULES: a. REVISE kVA load on panel PLP2-L4-208VN circuit 31.

b. ADD circuit 36, 40 and revise circuit information.

c. REVISE E-CONNECT AND STARTER SCHEDULE FDS-30-208 description.

12. Drawing 1-E-501 - ELECTRICAL SCHEDULES: REVISE kVA load and description on panel LP4-L4-120VN circuit 12, 14.

TECHNOLOGY:

SPECIFICATION ITEMS

1. Section 271500: DELETE article 3.3 MAINTENANCE.

2. Section 275223: a. ADD the following note to page 1: “THIS SECTION FOR REFERENCE ONLY. THE SYSTEM IS VA PROVIDED AND INSTALLED. GC IS RESPONSIBLE ONLY FOR INSTALLING BACKBONE (CONDUIT AND BACKBOXES)”.

b. DELETE article 4.2 paragraphs B.4 and C.

3. Section 280500: DELETE article 1.20 WARRANTY.

4. Section 283100: DELETE article 1.6

END OF MECHANICAL/ELECTRICAL/TECHNOLOGY ADDENDUM # 1

See attached document: List of Attachments.

See attached document: ATTENDANCE ROSTER.

See attached document: 05 Architectural Addendum _1 - Narrative -updated.

See attached document: 03 2021-0716 Addendum _1 Columbia BH-Vol 1 Specs.

See attached document: 04 2021-0716 Addendum _1 Columbia BH-Vol 2 Specs.

See attached document: 02 Renovate Behavioral Health Addendum _1 Drawings 7.16.21 UPDATED.