This is a contractor fee schedule for telecommunications and network infrastructure installation services. The schedule itemizes 45 line items encompassing materials, labor, and equipment rental. Materials include various cables (Cat6A Riser and Plenum rated, Cat6e, RG6 Coaxial, and 2-Strand OS2 Single Mode Fiber Armored), conduit and raceway systems (3/4" Conduit, 3/4" EMT, LD10 Raceway), and installation hardware (Hilti Hangers and shots). The schedule also specifies networking components such as jacks from Systimax and Leviton, patch panels (24-port and 48-port Cat6), faceplates in various configurations (2-port through 8-port), surface mount boxes, and specialty items including Blounder Tongue equipment (BTFIBT-1550-10, BTFRDA-54A-1000-FA, BTFOC-116U-SA, BTFRPF-4, BT-QAM-PRO), APC Single Mode Pigtails, F-Connectors, firestop sleeves, and consumables.

The pricing structure includes unit pricing for most materials (indicated by quantity of "1" or "lf" for linear feet) with blank columns for contractor-supplied unit prices. Labor is priced on a per-hour basis and lift rental on a per-day basis, with pricing fields left blank for contractor completion. The schedule specifies that the contractor will perform cable pulling, termination, and certification of completed work. The document does not include completion dates, award dates, or other contractual terms.

View the file

Other files

File Type Posted
36C25226R0013 0001.docx DOCX document
36C25226R0013_1.docx DOCX document
S02 Att 1j. OIT Horizontal Cable Requirements.pdf PDF
S02 Att 10 Financial Disclosure 578-26-007.docx DOCX document
S02 Att 1i. Contractor Parking.pdf PDF
S02 Att 4 Pre-construction Risk Assessment.pdf PDF
S02 Att 1f. Dig Permit SOP Form.pdf PDF
S02 Att8 VAAR 852.219-75 Certification 578-26-007.docx DOCX document
S02 Att 11 Subcontractor Info Consent 578-26-007.docx DOCX document
S02 Att 1m. Infection Control Barrier Sample.pdf PDF
S02 Att 1e. Cutting Welding and Other Hot Work.pdf PDF
S02 Att 1 SOW 578-26-007 IDIQ Cabling 2025.08.12.docx DOCX document
S02 Att 1d. Safety and Health During Construction Activities.pdf PDF
S02 Att 1h. Contractor Badging - Fingerprint Request Form 2025 (1).pdf PDF
S02 Att 12 Seasonal Influenza Vaccination Program 2020.08.10.pdf PDF
S02 Att 1a. Hines VA Campus Site Plan.pdf PDF
S02 Att 1l. Asbestos Survey Glossary when applicable.pdf PDF
S02 Att 9 Contractor EMR Safety Info 578-26-007.docx DOCX document
S02 Att 1c. Pre-Construction Checklist Rev 07.27.2021.pdf PDF
S02 Att 1h. Contractor Badging - Fingerprint Request Form 2025.pdf PDF
S02 Att 1b. Hines Underground Utility Plan.pdf PDF
S02 Att 1k. Fire Protection Code Reviews.pdf PDF
36C25226R0013_2.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor fee schedule

# Material Qty (LF) $ 1 BerkTek Cat6A Riser Rated Cable lf 2 Cat6A Plenum Blue Cable lf 3 RG6 Coaxial cable lf 4 LD10 Raceway 8' Sections lf 5 3/4" Conduit lf 6 3/4" Conduit lf 7 3/4" EMT lf 8 White Cat6e Cable lf

1 2-Strand OS2 Single Mode Fiber Armored 1 2 Systimax Cat6 Jack Black 1 3 Systimax Cat6 Jack Ivory 1 4 Cat6A Jacks 1 5 Hilti Hangers 1 6 Hilti shots 1 7 Leviton 24 Port Jack panels 1 8 Leviton Cat6A Jacks 1 9 Leviton black blanks 1

10 Leviton 1 Port surface Mount box 1 11 24 port Cat6 Patch Panel 1 12 48 port Cat6 Patch Panel 1 13 2 Port Faceplates 1 14 Ivory 2 Port Surface Mount Boxes 1 15 Single Gang Back Boxes 1 16 Wall phone faceplate (empty) 1 17 Cat32 J-Hooks 1 18 Cat32 J-Hooks w/Beam Clamps box 1 19 Blounder Tongue BTFIBT-1550-10 1 20 Blounder Tongue BTFRDA-54A-1000-FA 1 21 Blounder Tongue BTFOC-116U-SA 1 22 Blounder Tongue BTFRPF-4 1 23 Blounder Tongue BT-QAM-PRO 1 24 APC Single Mode Pigtails 1 25 F-Connectors 1 26 F-Connector Faceplates 1 27 Single 1 Port Surface Mount Box 1 28 2 Port Ivory Surface Mount Box 1 29 2 Port Ivory Faceplate 1 30 4 Port Ivory Faceplate 1 31 Leviton 2 Port Faceplates 1 32 Leviton 4 Port Faceplates 1 33 Leviton 6 Port Faceplates 1

Contractor fee schedule 34 Leviton 8 Port Faceplates 1 35 Leviton Slim Cat6A 7 ft. Patch Cords 1 36 Smooth Penetrators lots 1 37 Hilti Hangers Large lots 1 38 Hilti Shots lots 1 39 Storage container 1 40 Systimax 24 Port Angeled Panels 1 41 2U Hinged Wall Bracket 1 42 3/4" Bushing 1 43 2" Firestope Sleeves 1 44 Firestop putty cases 1 45 Consumables 1

Labor Per hour

Lift Rental Per day

The contractor will pull, terminate & certify the work done.