S06 - Att 1 Updates to Pages 3 and 11 of SOL 36C25226B0014.pdf

PDF 449 KB Posted

Attached to
Z1DA--Upgrade Fire Alarm System Construction 676-22-110
Solicitation number
36C25226B0014-1
Issued by

About this file

This is a Bid Schedule and Statement of Work for a federal construction contract to upgrade the fire alarm system at the VA Medical Center in Tomah, Wisconsin (Project #676-22-110).

The contractor must provide all labor, materials, equipment, qualified supervision, and related items necessary to complete the fire alarm system upgrade in accordance with federal, state, and local requirements, project specifications, and drawings. The contract is structured as an all-inclusive base bid (CLIN 0001) with no alternate bid items. The total project magnitude is estimated between $5,000,000 and $10,000,000. All work must be completed within 460 calendar days after receipt of the notice to proceed, broken down into three phases: pre-construction (20 calendar days for contractor work plus 60 days for VA review, totaling 80 days), campus work (350 calendar days for contractor work plus 10 days for VA review, totaling 440 days), and closeout (10 calendar days for contractor work plus 10 days for VA review, totaling 460 days). Award will be made to the responsible bidder submitting the lowest responsive bid; only one award will be made. If submitting as a joint venture, bidders must include a copy of the joint-venture agreement and printed proof of SBA small business status with their offer, or the bid will be rendered non-responsive. Prior to commencing construction, the contractor must submit an approved cost-loaded Critical Path Method construction schedule for approval by the Contracting Officer or Contracting Officer's Representative.

View the file

Other files

File Type Posted
36C25226B0014 0004.docx DOCX document
S06 - Att 2 Addendum No1 676-22-110 Upgrade Fire Alarm System 20260929.pdf PDF
S06 - Att 3 RFI Response A0003 Oct 6 2026.pdf PDF
36C25226B0014 0003.docx DOCX document
S06 - 36C25226B0014 0002.pdf PDF
S06 - Low Risk Locations - Upgrade Fire Alarm.pdf PDF
S06 - Infection Control 676-22-110 Upgrade Fire Alarm.pdf PDF
S06 - Site Visit Sign-in Aug 25 27-2026.pdf PDF
S06 - High-Highest Risk Locations - Upgrade Fire Alarm.pdf PDF
S06 - RFI Response A0001 Sep 3 2026.pdf PDF
S06 - Medium Risk Locations - Upgrade Fire Alarm 02.pdf PDF
36C25226B0014 0001.docx DOCX document
S02 - PART 3 - FIRE ALARM DEMO PLANS 20260421.pdf PDF
S02 - PART 5 - FIRE ALARM DEMO ONE-LINE DIAGRAMS 20260421.pdf PDF
S02 - PART 8 - FIRE ALARM NEW ONE-LINE DIAGRAMS 20260421.pdf PDF
S02 - PART 4 - FIRE ALARM DEMO PLANS 20260421.pdf PDF
S02 - PART 1 - GENERAL DRAWINGS 20260421.pdf PDF
S02 - Wage Determination WI20260011 Building Mod 1 20260518.pdf PDF
S02 - Bid Specifications_20260421.pdf PDF
S02 - PART 6 - FIRE ALARM NEW PLANS 20260421.pdf PDF
S02 - PART 7 - FIRE ALARM NEW PLANS 20260421.pdf PDF
S02 - 36C25226B0014.docx DOCX document
S02 - PART 9 - ELECTRICAL DRAWINGS 20260421.pdf PDF
S02 - PART 2 - CIVIL DRAWINGS 20260421.pdf PDF
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25226B0014

BID SCHEDULE

VA Construction Project Number: 676‐22‐110 Upgrade Fire Alarm System

While inclusion of the project magnitude $5,000,000 to $10,000,000 is no longer a mandatory element, the Government believes inclusion of this information assists prospective bidders in understanding the overall scale

0001 – All-Inclusive Base Bid: Contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with the specifications and drawings to complete Project # 676‐22‐110: Upgrade Fire Alarm System at Tomah VA Medical Center, Tomah, WI.

All work, starting with preconstruction phase through construction, ending in post-substantial completion is to be accomplished within four hundred and sixty days (460) calendar days after receipt of the notice to proceed.

CLIN 0001 All-Inclusive Base Bid: _______________________________

Alternate Bid Items noted in the design and specifications will not be used.

NOTICE TO BIDDERS: Award will be made to the responsible bidder, who submitted the lowest responsive bid.

A single award will be made on the Base Bid. Only one award will be made as a result of this solicitation.

NOTICE TO BIDDERS: Additional information regarding the general and specific scope of work is defined in the specifications and drawings.

NOTICE TO BIDDERS: If submitting a joint-venture (JV), bidders must include a copy of the joint-venture agreement within the bid package. All potential bidders are responsible for monitoring and downloading all amendments from Contract Opportunities at:

https://sam.gov/contracting

Joint Ventures (JVs) submitting a bid shall also submit printed proof of their SBA SBS and / or with their offer. JV offerors failing to submit this proof shall be rendered non-responsive outright and shall not be eligible for award.

NOTICE TO BIDDERS: An approved cost-loaded, Critical Path Method (CPM) construction schedule is required prior to commencement of construction. See specifications for details. CPM schedule shall be approved by the Contracting Officer or the Contracting Officer’s Representative. See specifications for details.

End of Section

36C25226B0014

Statement of Work

CONSTRUCTION STATEMENT OF WORK

Project Data:

a. Title: Upgrade Fire Alarm System

b. Location: VA Medical Center, Tomah, Wisconsin

c. Project #: 676‐22‐110

I. General Description:

Provide Construction Services for Project 676‐22‐110 Upgrade Fire Alarm System

II. Project Scope:

1. The contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with federal, state, and local authorities, project specifications, and drawings necessary to complete the construction of this project at the VA Medical Center, Tomah, Wisconsin.

2. All work shall be completed within 460 calendar days after receiving the notice to

Proceed (NTP).

3. See plans and specifications for further information.

III. Period of Performance:

1. The Pre-construction (kick-off) meeting will be held on a future, agreed-to-date (post award) and will coincide with the NTP.

CONSTRUCTION PERIOD OF PERFORMANCE CHART

(IN CALENDAR DAYS AFTER NTP)

Calendar

Days for the Work

VA Review Total days after

NTP

Level Complete

Pre-Construction 20 60 20 40 80

Campus work 350 10 400 440

Closeout 10 10 420 460

File details come from the government source that posted it. Updated .