S06 - 695-22-103 SOW Revised Oct 3rd 2022.pdf

PDF 843 KB Posted

Attached to
Z1DA--Replace Building 6 A-Wing Roof Project# 695-22-103 Clement J. Zablocki VA Medical Center, Milwaukee, WI
Solicitation number
36C25222B0031
Issued by

About this file

This document is a scope of work for Project #695-22-103 to replace the roof on Building 6 A-Wing at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The project involves removing the existing asphalt shingles down to the sheathing, replacing up to 20% of rotten sheathing boards, and installing a new asphalt roof system including underlayment, ice dam protection, drip edge, ridge vent, asphalt shingles, and new copper flashing around chimneys and pipe penetrations. The scope also includes removing the existing lightning protection system and installing a new system, removing all aluminum gutters and downspouts and installing new gutters and downspouts, repairing soffits, fascia boards and trim with new wood as needed and painting, and adding a new roof hatch for future roof access. The project is to be completed within 455 calendar days of the notice to proceed in six phases, with submittals, reviews, pre-construction activities, construction, and closeout. The contracting agency is the Department of Veterans Affairs.

View the file

Other files

File Type Posted
36C25222B0031 0008.docx DOCX document
S06 - 695-22-103 SOW Revised Oct 18 2022.pdf PDF
36C25222B0031 0007.docx DOCX document
S06 - Wage Determination effective 10.14.22.pdf PDF
S06 - Second Pre-Bid Site Visit Notes_695-22-103.pdf PDF
36C25222B0031 0006.docx DOCX document
S04 - Second Site-Visit Sign-In Roster_10.7.22.pdf PDF
S06 - Wage Determination effective 8.5.2022.pdf PDF
36C25222B0031 0005.docx DOCX document
S06 - Asbestos Report.pdf PDF
36C25222B0031 0004.docx DOCX document
S06 - Drawings AD101 _ AE101.pdf PDF
S06 - 00 01 10 - TABLE OF CONTENTS with spec sections.pdf PDF
36C25222B0031 0003.docx DOCX document
36C25222B0031 0002.docx DOCX document
S06 - 695-22-103 Site Visit roster 8.15.22.pdf PDF
36C25222B0031 0001.docx DOCX document
S02 - 6a - 695-22-103 DrawingsPart-3.pdf PDF
S02 - 6a - 695-22-103 DrawingsPart-1.pdf PDF
S02 - Wage Determination effective 7.15.22.pdf PDF
S02 - 6a - 695-22-103 DrawingsPart-4.pdf PDF
S02 - 6a - 695-22-103 DrawingsPart-2.pdf PDF
S02 - 695-22-103 Firestop_SoleSourceJustification_Executed.pdf PDF
36C25222B0031_2.docx DOCX document
S02 - 6a - 695-22-103 DrawingsPart-5.pdf PDF
S02 - 6b - 695-22-103 Specifications.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Clement J. Zablocki VA Medical Center

Replace Building 6 A-Wing Roof

Project 695-22-103

Scope of Work

March 8, 2022

Revised October 4, 2022

US Department of Veterans Affairs

Clement J. Zablocki VA Medical Center

5000 W. National Ave.

Milwaukee, WI 53295-0001

STATEMENT OF WORK

Prepared by:

Facility Management Division

ACCOMPANYING 36C25222B0031 0005

PROJECT NO: 695-22-103

PROJECT NAME: Replace Building 6 A-Wing Roof

I. General Description:

Provide Construction Services for Project#: 695-22-103 to Replace Building 6 A-Wing Roof.

II Project Scope:

1. General Description:

Provide Construction Services for Project #695-22-103, Replace Building 6 A-Wing Roof.

Contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with the specifications and drawings to complete Project # 695-22-103 Replace Building 6 A-Wing Roof at Clement J. Zablocki VA Medical Center, 5000 West National Avenue Milwaukee, WI.

A. This project includes removing existing asphalt shingles down to the existing sheathing.

Twenty percent or less of the sheathing boards field identified as rotten to be removed and replaced with new boards to match. A new asphaltic roof system to be applied. This includes underlayment, ice-dam protection, drip edge, ridge vent and asphalt shingles.

Due to this being a historical structure, new copper flashing to be used around the chimneys and pipe penetrations. The existing lightning protection to be removed to perform new work and to be replaced with a new lightning protection system that ties into the existing grounding location. All aluminum gutters and downspouts to be removed. Areas of the soffit, fascia, and trim where damage and rot have been identified to be demolished and patched with new wood members to match existing. All soffits, fascia boards, and trim to receive a new coat of paint. Once the fascia boards are repaired, new aluminum gutters and downspouts to be installed. A roof hatch to also be added to the roof to allow for future roof access for maintenance. Install of the hatch will require cutting and reframing of existing rafters.

This project shall be completed within Four Hundred Fifty-Five (455) days once NTP is issued.

• Start: Limited Notice to Proceed issued

• Phase 0: Preliminary Work Phase. Provide submittals for equipment and materials.

Award subcontracts for work specified in contract. Order equipment once submittals have been approved. Full NTP will be issued based on longest item lead-time.

• Phase 1: Notice to Proceed Issued. Pre-construction (kick-off) Meeting is anticipated to be scheduled on the effective date identified in the Notice to Proceed (NTP).

• Phase 2: Pre-Construction Period duration is NTP + 60 calendar days (not to exceed).

o Within the first 30 calendar days (not to exceed NTP + 30) of this period the contractor shall submit

▪ Accident Prevention Plan INCLUDING: Certificates, Licenses, and Training Documents.

▪ Construction Schedule

▪ Environmental Protection Plan

▪ Schedule a review meeting with the COR and VA Safety to discuss

Accident Prevention Plan and Construction Schedule

▪ Construction Phasing Plan INCLUDING: Sub task work plans o Within 60 calendar days (not to exceed NTP + 60) the contractor shall submit the following (as applicable per the specification requirements):

▪ Logistics Plan.

▪ Construction Security Plan.

▪ Construction Phasing Plan.

▪ Submittal Registry.

▪ Activity Hazard Analyses.

▪ Schedule of Values.

▪ Existing Conditions Survey.

▪ Infection Control Plan.

▪ Quality Control Plan.

▪ Environmental Protection Plan.

▪ Document Submissions.

▪ Demolition Debris Management Plan.

▪ Certificates, Licenses, and Training Documents.

▪ Obtain PIV badges.

• Phase 3: Pre-Construction Period duration is NTP + 60 calendar days (not to exceed). Within this period the contractor shall submit the following (as applicable per the specification requirements):

1. Logistics Plan.

2. Construction Security Plan.

3. Construction Phasing Plan.

4. Submittal Registry.

5. Accident Prevention Plan.

6. Activity Hazard Analyses.

7. Construction Schedule.

8. Schedule of Values.

9. Existing Conditions Survey.

10. Infection Control Plan.

11. Quality Control Plan.

12. Environmental Protection Plan.

13. Document Submissions.

14. Demolition Debris Management Plan.

15. Certificates, Licenses, and Training Documents.

16. Obtain PIV badges.

• Phase 4: Pre-Construction VA Review Period. Phase 4 is anticipated to be 30 calendar days and shall be completed no later than NTP + 90 calendar days. Within this period the VA shall complete all review and approvals of contractor Pre- Construction submittals.

• Phase 5: Construction Period – Phase duration is anticipated to be 320 days; to be completed no later than NTP + 410. All applicable documentation listed in Phase 2 and any necessary submittals required to mobilize must be approved by the COR prior to commencing work. No demolition or construction shall be started without COR review and approval of those items listed in the Pre-Construction Period unless authorized in writing by the COR or the CO. Should naturally occurring weather delays occur, the contractor shall restart construction immediately once conditions permit.

• Phase 6: Construction Closeout Period duration is NTP + 455 calendar days. The contractor shall provide all required materials to include the following within 45 days of completion of Phase 5.

1. Inspection and Approval by the COR and/or the CO.

2. Final Approval and Beneficial Occupancy when applicable.

3. Warranties documents and O&M Manuals.

4. As-built drawings and record submittals.

5. Staff training when applicable.

6. Waste Reports.

7. Existing Conditions Re-survey.

8. Release of Claims.

-- End SOW --