20200702 Addendum 1.pdf

PDF 13 MB Posted

Attached to
Y1DB--552-18-102: Renovate TCU/ICU Space (VA-20-00027634)
Solicitation number
36C25020B0028
Issued by

About this file

This pre-solicitation notice announces a requirement by the Department of Veterans Affairs to renovate approximately 17,000 square feet of intensive care and transitional care unit space at the Dayton VA Medical Center. The project involves upgrading outdated IT systems and will be conducted according to drawings and specifications. Interested service-disabled veteran-owned small businesses are advised to monitor the Federal Business Opportunities website for release of the solicitation around March 20, 2020, with proposals due approximately 30 days later. The North American Industry Classification System code assigned is 236220. The small business size standard is $39.5 million. The service-disabled veteran-owned small business must perform a minimum of 15% of construction work. Bid, payment and performance bonds will be required. A mandatory site visit will be scheduled. Questions should be emailed by the deadline.

View the file

Other files

File Type Posted
36C25020B0028 0006.docx DOCX document
36C25020B0028 0005.docx DOCX document
Site Visit sign-in.pdf PDF
20200701 TCUICU 2nd Floor Room Names.pdf PDF
20200701 TCUICU 2nd Floor RCP.pdf PDF
PreBid RFIs Answers.pdf PDF
36C25020B0028 0004.docx DOCX document
Bid Opening Instructions.pdf PDF
36C25020B0028-0003000.docx DOCX document
36C25020B0028-0002000.docx DOCX document
36C25020B0028-0001000.docx DOCX document
36C25020B0028-0001001.pdf PDF
36C25020B0028-004.pdf PDF
36C25020B0028-009.pdf PDF
36C25020B0028-007.pdf PDF
36C25020B0028-005.pdf PDF
36C25020B0028-008.pdf PDF
36C25020B0028-002.pdf PDF
36C25020B0028-006.pdf PDF
36C25020B0028-003.pdf PDF
36C25020B0028-001.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3131 Newmark Drive Suite 200 Miamisburg, OH

JOHN POE A R C H I T E C T S 45342

A D D E N D U M 937 461 3290 jpa@johnpoe.com

Addendum #1

Project: TCUICU

DVAMC, 4100 West Third Street

Dayton, Ohio 45428

Date: 07/1/2020

To: Jenessa Regan

3140 Governor’s Place Blvd.- Suite 210

Kettering, Ohio 45409

Please provide a proposal for changing contract documents as indicated below. Proposal is due within 10 calendar days of receipt of the Bulletin.

This Bulletin is not a change order. If work described in this Bulletin involves a change in time or contract sum, provide on Change of Work Proposal for each line item, itemizing labor and material, overhead and profit price breakdown in accordance with the Specifications. Also include any time extensions, if required.

Lump sum labor and material prices will not be accepted. If subcontractors’ or suppliers’ prices are included in the prime contractor’s proposal, provide a copy of their quotation. If no response to a Bulletin is received within the time specified above, then the non-responding Contractor will be determined to not be affected by the change, and any rights for increased compensation or time extensions shall be waived.

THE DRAWINGS ARE REVISED AS FOLLOWS:

General Information:

1. N/A

Drawing Sheets:

2. G001, AF101-F, AF101-P, and AF101-W see sheet A101-N for revised breakout graphic for ICU (Door type J).

3. G101- Phasing sheet reissued in their entirety.

4. A101-D1- Dimension strings updated at PPS cabinet and ICU door locations. ICU Door (Door type J) breakout graphic revised. General Plan Note F revised to add 100 sf of drywall construction as required for patching existing rated construction.

5. A101-D2- Dimension strings updated at PPS cabinet and ICU door locations. ICU Door (Door type J) breakout graphic revised. General Plan Note F revised to add 100 sf of drywall construction as required for existing rated construction.

6. A101-D3- General Plan Note F revised to add 100 sf of drywall construction as required for existing rated construction.

7. Sheet A101-N Note 9.58 added to Infection Control Bedrooms. ICU Door (Door type J) breakout graphic revised. General Plan Note F revised to add 100 sf of drywall construction as required for existing rated construction. Remove Detail 1 and associated key notes.

8. Sheet A402- Elevation 28 modified for electronic lock.

9. Sheet A403-PPS Storage Cabinet revised to elevations 40 and 43 with annotations.

10. Sheet A404- PPS Storage Cabinet revised to elevations 44 and 46 with annotations.

11. Sheet A511- Casework Section B5 modified for electronic lock.

12. Sheet A512-PPS Storage Cabinet details revised.

13. Sheet A513- Revise note 5.32 to include structural steel as an option for the patient lift delegated design supports.

14. Sheet A601- Detail H6 detail revised. Toilet patient door and frame heights revised see revised schedule

Door frame details revised. Deduct Alt #1 & Deduct Alt #2 door schedule removed.

15. Sheet AF601-Finish PL-3, PR-1 added, AR-1 removed. Revisions made to room schedule. Window sills to be SS-3.

16. Sheet AS101-Sign Type graphics added to sheet. Some changes to assigned sign types. ICU Door

(Door type J) breakout graphic revised.

17. Sheet F901 – Furniture shown for reference only. Furniture to be provided by installed by VA. ICU door breakout graphic revised.

18. Sheet F902 Markerboard to be CP/CI Contractor Provided, Contractor Installed. ICU Door (Door type J) breakout graphic revised.

19. Sheet S001- Patient lift structure delegated design notes.

20. Sheet S100- Patient lift structure delegated design notes.

21. Sheet MP103- Revised room pressure monitoring and indication requirements.

22. Sheet M702- Revised room pressure monitoring and indication requirements.

23. Sheet E502- Camera Schedule – Refer to revised Camera Schedule. Camera 1 represents the cameras in the Patient Rooms. Refer to the drawings for quantities. Camera 2 is a security camera that requires license for the Milestone system.

Specifications:

1. Section 00 01 10 Revised – 07 42 33 Phenolic Wall Panels added under Division 07. 01 31 00.01 Web

Base Project Management- Specification section added under Division 1.

2. Section 01 31 00.01 Web Base Project Management- Specification section added.

3. Section 06 06 60 Plastic Fabrications- Section removed with removal of AR-1 from project.

4. Section 06 41 16 Plastic Laminate Clad Architectural Cabinets- Added paragraph 2.3.G Battery Powered

Electronic Cabinet Lock. Basis of design: KitLock 1000.

5. Section 07 42 33 Phenolic Wall Panels added

6. Section 08 42 43 Intensive Care Unit/ Critical Care Unit Entrances- Specification reissued in its entirety.

7. Section 08 71 11 Door Hardware- Section header revised. Remove “SHOP DRAWINGS, PRODUCT

DATA AND SAMPLES” and replace with “DOOR HARDWARE”.

8. Section 09 06 00 Schedule for Finishes- PL-3 added to 2.1 Division 06, Table A. Added 2.2 Division 7.

Table B removed from 2.3 Division 10.

9. Section 09 30 13 Ceramic Porcelain Tile- Remove paragraph 3.14.

10. Section 10 15 00 Signage- 2.1/A Remove “at end of this section” from sentence.

11. Section 10 26 00 Basis of Design for handrail: Acrovyn HRB-10CN (6.25”H)

12. Section 10 26 00 Basis of Design for crash rail: Acrovyn SCR-48N (6”H)

13. Section 10 28 00 Toilet Accessories- Revise section 2.4 Grab Bar as indicated below:

a. 2.4/B: Remove nylon coated as material option.

b. D/1/b- Remove nylon coated as material option.

14. Section 10 51 61 Built-In Combination Locks- Omit specification

15. Section 11 73 00 Ceiling Mounted Patient Lifts- Specification replaced in its entirety.

Attachments: G101, A101-D1, A101-D2, A101-N, A402, A403, A404, A511, A512, A513,A501, A601, AF601, AS101, F901, F902, S001, S100, MP103, M702,E502, Section 01 31 00.01, Section 07 42 33, Section 08 42 43, Section 09 60

00, Section 11 73 00

Copy To: File

End of Bulletin

PHASING LEGEND

Temporary Construction Barrier and door.

Temporary door to have 45 min raiting.

Hardware to have closer and and panic hardware on owner occupied side. Reuse existing door and hardware where possible.

Ensure all accessibility requirements are met.

Extend wall from floor to deck. See A601 for wall types. Wall type T1.0, typical.

Area of renovation.

Owner-Occupied Area. No work to be performed by Contractor this phase.

Owner-Occupied Area. Minimal to no architectural work in current phase. PME work may be required. See PME drawings for additional phasing requirements. Work to be performed by Contractor during off-hours (9pm - 5am). Coordinate off-hour work with

COR.

Existing walls as construction barrier between phases.

1.06

1.06

1.07

1.07

1.081.091.09

1.10

1.11

1.10

1.13

1.13

1.07

1.07

1.031.04 1.05

1.12 1.12

1.07

1.041.03

1.13

1.14

1.071.07

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

PHASING PLANS

G101

DWTH

17005.00

552-18-102

Dayton Ohio

A. Temporary partitions are suggested locations. Coordinate final location in field with C.O.R. Temporary partition locations are approximate and may need to be adjusted to meet project requirements.

B. Verify all conditions in the field prior to fabrication, erection and construction.

C. Any work done on adjacent floors to be completed and cleaned by end of second shift.

D. Coordinate phase completion and start-up with requirements as set forth by the C.O.R. to maintain daily operations to near as normal as possible.

E. Coordinate location of job dumpster with the C.O.R. so as to disrupt daily operations as little as possible.

F. Coordinate access to all phases of construction, deliveries, and debris removal with the C.O.R.

G. Temporary door locations and sizes are as required by the General Contractor. Doors will interfere with daily operations as little as possible. Confirm all locations with the C.O.R. Maintain all emergency egress paths.

H. Existing HVAC, medical gases, sprinklers and water supply to be maintained throughout as required during each phase of construction.Coordinate phasing with Mechanical and Plumbing contractor. Support and protect all lines during each phase of construction. See MEPDrawings.

J. Provide and maintain negative air pressure at all construction.

Coordinate with HVAC contractor. See HVAC plans for duct locations.

K. Extend all temporary partitions to structural deck above.

L. Existing power to occupied areas must be maintained throughout as required during each phase of construction.Coordinate phasing with Electrical Contractor. Coordinate power turnover with requirements as dictated by the C.O.R. See Electrical Drawings.

M. Coordinate construction sequence with C.O.R. so that only one side (not less than 48") of any corridor in use is obstructed at any one time in order to maintain required egress.

N. Coordinate all work involving the generation of excessive noise so as to occur during normal operating hours, 0700 to 1500 daily.

Activities to occur during this time include, but are not limited to saw cutting, jack hammering, hammer drilling and core drilling. If there is any question as to whether an operation should occur during this time the Contractor will contact the C.O.R.

P Relocate lights and sprinkler heads as required at temporary partitions.

Q. See phasing plan for location of construction barriers. Contractor to install firestop for up to 100 penetrations and 100 SF of existing, unfirestopped penetrations through existing construction barriers.

Contractor to also install up to 100 sf of drywall as required to provide adequate construction barrier.

GENERAL PHASING NOTES

N Scale: 3/32" = 1'-0"

PHASING PLAN - PHASE I

N Scale: 3/32" = 1'-0"

PHASING PLAN - PHASE II

1.03 Contractor access.

1.04 Staff/patient access.

1.05 Maintain access to waiting room.

1.06 See mechanical and structural drawings for detailed information regarding relocation of supply ductwork in this area.

1.07 Owner emergency egress. Keep path of egress clear at all times.

1.08 Relocate pneumatic tube station before work starts in Room 3B164. System shall be non-operational for no more than 10 days.

1.09 Construct corridor walls (Construction barrier) prior to removal of Storage room interior walls. (See keynote 1.10).

1.10 Remove interior walls after corridor walls have been

completed.(See keynote 1.09) Construction barrier moves to corridor walls.

1.11 Contractor to coordinate with COR and staff for interuptions in pneumatic station access.

1.12 No owner access this door.

1.13 Temporary door providing owner egress. Contractor to provide 3'-6 active door with 1'-6 inactive leaf.

1.14 Temporary door providing contractor egress. Contractor to provide 3'-6" door.

PLAN NOTES

Revision s

Date

7 100% For Bid 03.09.2020

F

1.2

EDCBA

1.5

2.2

3.2

3.1

2.1

E8

3.05

9 1/2"

10' - 9 5/8"

1' - 9 5/8"

/8

/4

/8

RESTROOM

3B123a

S2.0S2.0

RESTROOM

3B124a

ANTE

ROOM

3B123b

BED ROOM

3B125

CORRIDOR

C3-19

TOILET,

FEMALE

3B126

TOILET,

MALE

3B128

CORRIDOR

C3-17

CONTROL

CENTER

C3-15

MED ROOM

3B119

ELECTRICAL

CLOSET

3B144

BED ROOM,

INFECTION

CONTROL

3B124

STORAGE

3B164

STORAGE

3B145

RESTROOM

3B125a

RESTROOM

3B135a

BED ROOM,

BARIATRIC

3B135

BED ROOM,

INFECTION

CONTROL

3B137

RESTROOM

3B137a

RESTROOM

3B138a

A N

T E

R O

O M

B b

A N

T E

R O

O M

B b

BARIATRIC,

INFECTION

CONTROL

3B138

BED ROOM

3B140

UTILITY

ROOM,

CLEAN

3B130

CLEAN

LINEN

3B139

SOILED

UTILITY

3B152

NOURISHMENT

3B153

CORRIDOR

C3-20

RESTROOM

3B140a

RESTROOM

3B142a

ALCOVE

TRAY

STORAGE

3B141a

BED ROOM

3B142

CONTROL

CENTER

C3-25

BED ROOM

3B160

ALCOVE,

WHEELCHAIR

3B171

R E

S T

R O

O M

B a

RESTROOM

3B159a

BED ROOM

3B159

CORRIDOR

C3-26

MED ROOM

3B154

NURSE

WORKROOM

3B151

STORAGE

3B149

OFFICE

3B150

STORAGE

3B148

HAC

3B155

STORAGE

3B168

OFFICE

3B147

BREAK

ROOM

3B146

OFFICE

3B117

NURSE

WORKROOM

3B114

S .0

S1.1

S1.1

S .0

S1.1-N

S1.1-N

S1.1

S .1

S1.1

S1.1

S1.1

S2.0

S2.0S2.0

S2.0

S2.0

S2.0S2.0

S1.1

S2.0

S1.0-F

S1.1

S1.1

S2.0

S2.0

S1.1 S2.0

S2.0

S2.0

S1.0-F S1.0-F

S1.0-F

4' - 5 1/2"

4 1/4"

6' - 7 3/8" 4 7/8"

7 7/8"

4 1/4" 5' - 3 3/8"4

/4

/4

/8

/4

/4

S1.0-F

/8

/4

/4

/8

/8

/8

120°

13' - 6 7/8" 1' - 0 1/8" 2' - 0"

120°

3' - 0 1/8" 13' - 7 3/8"

4 1/2" 4' - 2" 3' - 11 1/8" 4' - 4 7/8"

4 7/8"

4' - 4 7/8" 3' - 11 1/2" 4' - 2 1/8" 4 1/2" 8' - 0 1/2" 9" 8' - 0 1/2"

5' - 4 1/8"

4 1/4"

11"

4 1/4"

120° 120° 120°

1' - 9 5/8" 4' - 5 3/4" 3' - 4 1/2" 4 7/8" 3' - 10"

ALIGN

/8

/8

/8

/4

/8

/4

0°

/2

/2

/2

/4

/2

/4

A L

IG

N

ALIGN

14' - 4 3/4"

4 7/8"

6' - 2"

4 7/8"

2' - 6 1/2" 4' - 5 1/8" 2' - 6 1/2"

4 7/8"

S1.0-F

ALIGN

ALIGN

ALIGN

ALIGN

ALIGN1

/2

/2

/8

/2

/8

/8

/8

/4

/8

/8

/2

/2

/4

/8

7' - 5 3/8" 3' - 11 3/4"

1' - 9 5/8"

4' - 8 3/8" 3' - 11 1/8" 3' - 8 5/8" 4 1/2"

8' - 0 1/2" 9" 8' - 0 1/2" 4 1/2" 4' - 0 7/8" 3' - 11 1/8"

4 7/8"

2' - 10 5/8"

4 7/8"

4' - 4 1/8"

4 7/8"

3' - 11 1/8" 3' - 5 3/8" 4 1/2" 8' - 0 1/2" 11 5/8"

/8

/8

/8

/8

/2

/2

2' - 2 1/2"

ALIGN S2.0

ALIG

N

S2.0S2.0

/2

S2.0

1' - 9 5/8" 12' - 1 1/8"

/8

/8

S2.0S2.0

2' - 6" 6 1/8" 13' - 5 3/8"

/2

/8

/4

/8

/4

/4

5' - 3 3/8"

1' - 7 1/2"

/4

13' - 5 3/4" 10 3/4" 2' - 2"

M

IN

/8

/8

/8

/4

/8

/2

5' - 5 1/4"

4 1/4"

11"

4 1/4"

1' - 7 1/2"

S2.0S2.0

4 7/8"

3' - 0 1/8" 13' - 1 1/2"

/2

/8

/4

/8

/8

/8

6'

9'

/8 " 1'

/8

4' - 7 7/8" +/-

/4

/8

8' - 0" MIN.

135°

/8

/4

/8

/8

/8

/8

ALIGN

/8

S2.0S2.0

S2.0

/2

/8

"4

/8

ALIGN

ALIGN

2' - 8 7/8"

/2

" 10' - 0 5/8"

13' - 4 3/4"

4'

/8

3'

0"

4"

6'

1/

4"

3'

0"

1/ 2"

2' - 0 5/8"

ALIGN

ALIGN

ALIGN ALIGN ALIGN

45°

6' - 4 7/8"

ALIGN

BEDROOM -

RESIDENT

ON-CALL

3B161

S2.0S2.0

9"

3' - 6"

CORRIDOR

3C-27

S1.0-F

S1.0-F

S1.0-F

S1.0-F

S1.0-F

S1.0-F

S1.0-F

E1.0

E1.0

E1.0

S1.0-N

4 1/2"4 1/2" 4 1/2"4 1/2"

AREA A

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

ENLARGED DIMENSION PLAN

A101-D1

DWTH

17005.00

552-18-102

Dayton Ohio

N Scale: 1/4" = 1'-0"

ENLARGED DIMENSION PLAN A GENERAL NOTES

A. All dimensions are taken to face of gypsum wallboard or unit masonry.

B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.

C. All wood blocking to be fire retardent treated.

D. All partitions shall be type 'S1.0' unless noted otherwise.

E. See enlarged plans for additional notes.

F. See code plan for existing rated construction. Firestop all new penetrations to maintain integrity of existing rated construction.

Additionally, firestop up to a maximum of 100 penetrations and/or 100 SF of existing, unfirestopped penetrations through existing rated construction. Contractor to also install up to 100 sf of drywall construction for existing rated construction.

N.T.S.Scale:

Key Plan

Revision s

Date

8 Addendum #1 06.02.2020

FEDCBA B3 B6 C5 E1

3.2

4.1

4.7

5.3

4.2

3.1

D2C6

3.05

4.6

OFFICE

3B120

CORRIDOR

C3-18

BED ROOM

3B121

RESTROOM

3B121a

ALCOVE,

WHEELCHAIR

3B165

RESTROOM

3B122a

BED ROOM

3B122

ALCOVE

CRASH

CART

3B166

RESTROOM

3B110a

NOURISHMENT

3B115

BED ROOM,

INFECTION

CONTROL

3B123

CORRIDOR

C3-19

CONTROL

CENTER

C3-15

NURSE

WORKROOM

3B114

CLEAN

LINEN

3B116

COMM

CLOSET

3B111

OFFICE

3B117

BREAK

ROOM

3B146

OFFICE

3B147

CORRIDOR

C3-23

STORAGE

3B168

HAC

3B155

STORAGE

3B106

BED ROOM,

BARIATRIC

3B110

BED ROOM

3B108

RESTROOM

3B108a

ALCOVE

WHEELCHAIR

3B112

BED ROOM

3B105

RESTROOM

3B105a

CONSULTATION

ROOM

3B102

RESTROOM

3B158a

BED ROOM

3B158

CORRIDOR

C3-26

BED ROOM

3B159

UTILITY

ROOM,

CLEAN

3B109

SOILED

UTILITY

3B107

S2.0

S2.0

S2.0

S1.1

S1.1

S1.1

S2.0

S1.1

S1.1

S2.0

S1.1

S2.0

S2.0

S2.0

S2.0

S2.0

S2.0

S2.0

S1.1

S1.1

S2.0S2.0

S2.0

S2.0

S2.0S2.0

S1.0-F

/8

0°

/2

/2

/8

/8

/8

/4

/8

/4

/8 " 4

/8

/8

/8

/8

7' - 7 3/8" 3' - 11 3/4" 1' - 9 5/8"

/8

/4

/2

/2

/2

/2

/8

/8

/8

/2

/2

/2

A L

IG

N

120°

ALIGN

120°

/8

/8

120°

ALIGN

ALIGN

A L

IG

N

ALIGN

6' - 3 1/8"

6' - 7 7/8"

4 7/8"

5' - 4 1/2" 6' - 7"

ALIGN

CORRIDOR

C3-12

OFFICE

3B103

/8

/8

/8

/8

7' - 2 1/2"

/8

/4

/8

/2

S2.0

2' - 10 7/8" 5' - 10 1/2" 3' - 7 3/8" 3' - 11 1/8" 3' - 11 1/4" 4 1/2" 8' - 0 1/2" 9" 8' - 0 1/2" 4 1/2" 2' - 3 3/4" 3' - 11 1/8"

4 7/8"

5' - 4" 1' - 3" 8' - 0 1/2" 4 1/2" 5' - 8 7/8" 3' - 11 1/8" 2' - 7 1/8"

4' - 0 7/8"

4 1/4"

8 1/2"

4 1/4"

5' - 4 5/8"

4 7/8"

3' - 9" 13' - 3 3/4"

1' - 0 1/8"

/4

/4

11' - 9 7/8"

1' - 10 1/2"

2' - 10 1/2"

/8

/8

/8

S2.0

1' - 10" 3' - 6"

5' - 3 3/4"

4 1/4"

8 1/2"

13' - 11 7/8" 4' - 9" 4 7/8"

1' - 7 1/8"

5' - 3 3/8" 1' - 0 3/4"

/8

/8

ALIGN

/8

M

IN

/4

/4

/4

/4

/8

/2

/2

/4

/8

/2

5' - 5 5/8" 2' - 2 1/2"

2' - 0"

13' - 10 3/4"

/4

3 5/8"

17' - 11"

11' - 7 1/8"

1' - 9 5/8"

/4

7' - 0"

SCRUBS

3B106a

3'

6"

4'

1"

9"

S2.0S2.0S2.0

S2.0 S2.0

S2.0

AREA B

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

ENLARGED DIMENSION PLAN

A101-D2

DWTH

17005.00

552-18-102

Dayton Ohio

N Scale: 1/4" = 1'-0"

ENLARGED DIMENSION PLAN B

GENERAL NOTES

A. All dimensions are taken to face of gypsum wallboard or unit masonry.

B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.

C. All wood blocking to be fire retardent treated.

D. All partitions shall be type 'S1.0' unless noted otherwise.

E. See enlarged plans for additional notes.

F. See code plan for existing rated construction. Firestop all new penetrations to maintain integrity of existing rated construction.

Additionally, firestop up to a maximum of 100 penetrations and/or 100 SF of existing, unfirestopped penetrations through existing rated construction. Contractor to also install up to 100 sf of drywall construction for existing rated construction.

N.T.S.Scale:

Key Plan

Revision s

Date

8 Addendum #1 06.02.2020

F

1.2

EDCBA B3 C5 E1

1.5

2.2

3.2

4.1

5.3

4.2

3.1

2.1

D2

4.65

C2 C6

5.2

E9E8

3.05

4.6

CONSULTATION

ROOM

3B102

OFFICE

3B103

OFFICE

3B120

BEDROOM -

RESIDENT

ON-CALL

3B161

CORRIDOR

C3-12

CORRIDOR

C3-14

CORRIDOR

C3-18

CORRIDOR

C3-19

CORRIDOR

C3-20

CORRIDOR

3C-27

CORRIDOR

3C-9

BED ROOM

3B121

RESTROOM

3B121a

RESTROOM

3B122a

BED ROOM

3B122

BED ROOM,

INFECTION

CONTROL

3B123

RESTROOM

3B123a

RESTROOM

3B124a

BED ROOM

3B125

RESTROOM

3B125a

BED ROOM

3B142

RESTROOM

3B142a

RESTROOM

3B140a

BED ROOM

3B140

BARIATRIC,

INFECTION

CONTROL

3B138

RESTROOM

3B138a

RESTROOM

3B137a

BED ROOM,

INFECTION

CONTROL

3B137

BED ROOM,

BARIATRIC

3B135

BED ROOM

3B160

BED ROOM

3B158

BED ROOM,

BARIATRIC

3B110

BED ROOM

3B105

RESTROOM

3B105a

RESTROOM

3B110a

NOURISHMENT

3B115

STORAGE

3B145

RESTROOM

3B158a

RESTROOM

3B135a

ANTE

ROOM

3B137b

ANTE

ROOM

3B138b

VESTIBULE

3B104

BED ROOM

3B108

RESTROOM

3B108a

ALCOVE,

WHEELCHAIR

3B165

ALCOVE

CRASH

CART

3B166

ALCOVE

TRAY

STORAGE

3B141a

ALCOVE

WHEELCHAIR

3B112

AREA OF DEDUCT ALTERNATE

AREA OF DEDUCT ALTERNATE

A405

A

A405

B

140a 142a

108a 105a110a

137a

A101-N

124a

A401

B

160a

CORRIDOR

C3-26

BED ROOM

3B159

RESTROOM

3B159a

RESTROOM

3B160a

122a

121a

125a

135a

110 108 105

142140138137135

159a

137c

137b 138b

138c

158a

NURSE

WORKROOM

3B114

CLEAN

LINEN

3B116

CONTROL

CENTER

C3-15

COMM

CLOSET

3B111

OFFICE

3B147

CORRIDOR

C3-17

BREAK

ROOM

3B146

CORRIDOR

C3-23

HAC

3B155

MED ROOM

3B154STORAGE

3B149

NURSE

WORKROOM

3B151

SOILED

UTILITY

3B152

CLEAN

LINEN

3B139

UTILITY

ROOM,

CLEAN

3B130

TOILET,

FEMALE

3B126

MED ROOM

3B119

STORAGE

3B168

NOURISHMENT

3B153

STORAGE

3B106

SOILED

UTILITY

3B107

UTILITY

ROOM,

CLEAN

3B109

OFFICE

3B117

TOILET,

MALE

3B128

ELECTRICAL

CLOSET

3B144

STORAGE

3B148

OFFICE

3B150CORRIDOR

C3-22

CONTROL

CENTER

C3-25

STORAGE

3B164

CORRIDOR

C3-27

139 152

109111

116 107

A401

C

BED ROOM,

INFECTION

CONTROL

3B124

ANTE

ROOM

3B124b

ALCOVE,

WHEELCHAIR

3B171

ANTE

ROOM

3B123b123b

124b

123c

124c

A

A

A

A

A

A A A A A

A

A

A

AAA

B

C

D

F

E

A401

D

G

F902

TYP.

F902

ALCOVE

CRASH

CART

3B141

130a

146a

106a

WAITING

ROOM

3B101

CONFERENCE

ROOM

3B100

SCRUBS

3B106a

G

G

14.04

8.14 8.14 8.14

8.14

8.14

8.14

8.14

8.14

8.14 8.14

8.14

8.14

8.14 8.14

8.15

3' - 10"

1.01

1.01

1.01

1.01

1.01 1.01

1.01

1.01

1.01

1.01

1.01

11.0211.03

11.02

11.02

11.02

11.02

11.02

11.02

11.02

11.03

11.02

11.02

11.02

11.02

11.02

123a

138a

8.14

8.14

11.03

8.14

9.52

9.52

F902

F902

SIM.

F902

SIM.

F902

SIM.

10.41

10.41

10.41

10.41

8.30 Typ.

8.30 Typ.

8.30

Typ.

8.30

Typ.

8.30

Typ.

8.30

8.30

Typ.

Typ.

8.30 8.30

Typ. Typ.

10.41

9.58

9.58

9.58 9.58

PLAN AREA

DCB

3.1

2.1

CORRIDOR

C3-14

NOURISHMENT

3B115

ALCOVE

WHEELCHAIR

3B112

BREAK

ROOM

3B179

OFFICE,

PHYSICIAN

3B117

OFFICE

3B174

COMM

CLOSET

3B111

UTILITY

ROOM,

CLEAN

3B109

STORAGE,

GENERAL

3B147

KITCHEN,

MISC

3B180

STORAGE,

STRETCHER/

WHEELCHAIR

3B107

UTILITY

ROOM,

SOILED

3B106

UTILITY

ROOM,

SOILED

3B182

CORRIDOR

C3-23

UTILITY

ROOM,

CLEAN

3B155

HAC

3B148

MED PREP

3B154

TOILET

3B181OFFICE

3B149

OFFICE

3B150

LINEN

ROOM,

SOILED

3B152

NOURISHMENT

3B151

NOURISHMENT

3B175

MED PREP

3B176

UTILITY

ROOM,

SOILED

3B178

CORRIDOR

C3-17

CORRIDOR

C3-22

UTILITY

ROOM,

CLEAN

3B130

STORAGE

3B129A

OFFICE

3B177

TOILET,

MALE

3B128

TOILET,

FEMALE

3B126

ELECTRICAL

CLOSET

3B144

TOILET

3B139

CONTROL

CENTER

C3-15

CONTROL

CENTER

C3-25

A406

A

A406

B164

107 106109111

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18 8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.18

8.10

8.10

8.14

8.14

8.14

14.04

10.41 10.24

10.41

DCB

3.1

2.1

CORRIDOR

C3-14

NOURISHMENT

3B115

ALCOVE

WHEELCHAIR

3B112

UTILITY

ROOM,

SOILED

3B106

STORAGE,

STRETCHER/

WHEELCHAIR

3B107

UTILITY

ROOM,

CLEAN

3B109

COMM

CLOSET

3B111

OFFICE

3B174

KITCHEN,

NOURISHMENT

3B175

MEDICATION

PREP.

3B176

OFFICE,

PHYSICIAN

3B117

OFFICE

3B177

UTILITY

ROOM,

SOILED

3B178

TOILET,

FEMALE

3B126

TOILET,

MALE

3B128

STORAGE

3B129A

TOILET,

CONGREGATE

3B139

UTILITY

ROOM,

CLEAN

3B130

ELECTRICAL

CLOSET

3B144

BREAK

ROOM

3B179

KITCHEN,

MISC

3B180

STORAGE,

GENERAL

3B147

HOUSEKEEPING

AID CLOSET

3B148

OFFICE

3B149

OFFICE

3B150

NOURISHMENT

3B151

LINEN

ROOM,

SOILED

3B152

TOILET

3B181

MEDICATION

PREP.

3B154

UTILITY

ROOM,

CLEAN

3B155

UTILITY

ROOM,

SOILED

3B182

CONTROL

CENTER

C3-15

CORRIDOR

C3-17

CORRIDOR

C3-22

CORRIDOR

C3-23

CONTROL

CENTER

C3-25

111 109 107

A406

A

A406

B

14.04

8.10

8.10

8.148.148.14

10.24

10.41

10.41

1/2"

/2

7.65

10.25

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

NOTE PLANS

A101-N

DWTH

17005.00

552-18-102

Dayton Ohio

GENERAL NOTES

A. All dimensions are taken to face of gypsum wallboard or unit masonry.

B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.

C. All wood blocking to be fire retardent treated.

D. All partitions shall be type 'S1.0' unless noted otherwise.

E. See enlarged plans for additional notes.

F. See code plan for existing rated construction. Firestop all new penetrations to maintain integrity of existing rated construction.

Additionally, firestop up to a maximum of 100 penetrations and/or 100 SF of existing, unfirestopped penetrations through existing rated construction. Contractor to also install up to 100 sf of drywall construction for existing rated construction.

N Scale: 1/8" = 1'-0"a

NOTE PLAN - BASE BID

N N.T.S.Scale:

KEY PLAN

1.01 No architectural work this area.

7.65 Cont. sealant.

8.10 Refer to Base Bid Door Schedule for details about this door.

8.14 Electronic card reader.

8.15 Push button door operator.

8.18 New door leaf in existing frame. Reuse existing hardware. Field verification required.

8.30 Install solid surface window sill per detail 1/A101-N.

9.52 Coordinate final size of chase with plumbing contractor.

9.58 Construct room to limit the passage of air. Ensure that gypsum wall board is fitted tight and sealed to deck above and floor slab providing a continuous barrier. Seal drywall construction at perimeter and corners. Seal all penetrations created by Architectural and MEPFS items including, but not limited to, ducts, wall outlets, conduit, and pipes.

10.24 Remove and replace existing fire extinguisher cabinet.

10.25 Solid surface window sill.

10.41 Semi-recessed fire extinguisher cabinet.

11.02 Standard headwall. See Elevation 1/A513 for details.

11.03 Bariatric headwall. See Elevation 4/A513 for details.

14.04 Relocated pneumatic tube system. Refer to phasing plans for scheduling information.

PLAN NOTES

N Scale: 1/8" = 1'-0"2

NOTE PLAN - DEDUCT ALTERNATE #1

N Scale: 1/8" = 1'-0"3

NOTE PLAN - DEDUCT ALTERNATE #2

Revision s

Date

8 Addendum #1 06.02.2020

7 100% For Bid 03.09.2020

TYP. WINDOW SILL REPLACEMENT DETAIL

sodell Callout Remove Window Sill replacement covered by Detail S3

RB-1

CG-1

CG-2

FWP-1FWP-1

FWP-1

PL-1

SS-2

RB-1

NC

A

3' - 7 3/4"

B5

12.41

6.09

2'-0" 3'-0" 3'-0" 2"

2'-0" 3'-0" 3'-0" 2"

W1 W1 W1

B3B1B2

F

PL-1

SS-2

PL-1

RB-1

RB-1

P-1 E

RR

PL-1

3"2'-9"3'-0"1'-9"

3"2'-9"3'-0"1'-9"

PL-1

P-1

SS-2

PL-1

RB-1

W1 W1 W2

B1B3B4

F

E

RF

MV

PL-1

3' - 0"3 3/8"

W3

OC1

P-1

SD

PT

P-8

RB-1

PM

BP

P-8

RB-1

SB

11.02

22.08

MEMT

HS

CG-1

P-8

RB-1

MB

TR1

11.08

P-8

RB-1

WC

A

SD

PT

P-8

RB-1

GB

TR1

WC

PM

SB

P-8

RB-1

P-811.02

22.08BP

ME

MT

CG-1

RB-1

P-8

PL-1

P-1

W1 W1

UR

OC1

12.10

2" 3' - 6" 3' - 3"

2" 3' - 6" 3' - 3"

B1

PL-1

SS-2

RB-1 RB-1

PL-1

2" 3' - 0" 2' - 9" 1' - 6"

2" 3' - 0" 2' - 9" 1' - 6"

W1W1W1

B3 B1 B2

PL-1

P-1

SS-2

PL-1

RB-1

F

E

PL-1

12.15

12.15

UR

OC1

" PL-1

P-1

PL-1

SS-2

RB-1

3' - 0"2' - 6"2"

2" 2' - 3" 3' - 3" 12.10

W1W1

B1

PL-1

RB-1

RF

P-1

PL-1

SS-2

1'-9" 2'-9" 2"

W1

B1

W2

B1

MV

2" 3' - 0" 1' - 9" 2' - 9" 2"

PL-1PL-1

W3

EQ EQ

NCSS-2

P-1

RB-1

B5

C

W1W1

B2B3 B1

CMF

E

2" 3'-0" 3'-0" 1'-6" 2"

PL-1

SS-2

PL-1

RB-1

2" 3' - 0" 1' - 6" 3' - 0" 2"

W3

IM

PL-1

2 3/8" 2'-9" 1'-3" 2'-9" 2 3/8"

SS-2

P-1

IM

CM

2 3/8" 2' - 9" 1' - 3" 2' - 9" 2 3/8"

PL-1PL-1

PL-1

RB-1

F

E

W1 W1 W3

B2B3 B1

RF SS-2

P-1

MV

2 3/4" 3' - 3" 3' - 6" 2"

1' - 9" 1' - 9" 2"

?PL-1

PL-1

W3 W2

B1 B1

EQUIPMENT TAG

WINDOW OPENING

DOOR OPENING

FINISH DESIGNATION

X

XX

SIGNAGE TAG

TOILET ACCESSORY TAGX

X

TAG LEGEND

TR1

GB

SD

PT

P-8

RB-1

PM

SB

P-8

RB-1

22.08

11.03

BB

ME

MB

MT

HS

RB-1

P-8

CG-1

11.08

2" 2"

1' - 3"

10.06

10.09

10.08

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

INTERIOR ELEVATIONS

A402

MWTH

17005.00

552-18-102

Dayton Ohio

Scale: 1/4" = 1'-0"28

TYP. NURSE STATION

Scale: 1/4" = 1'-0"20

3B119 MED ROOM

Scale: 1/4" = 1'-0"24

3B146 BREAK ROOM

Scale: 1/4" = 1'-0"26

3B154 MED ROOM

Scale: 1/4" = 1'-0"29

TYP. PATIENT ROOM

Scale: 1/4" = 1'-0"30

TYP. PATIENT ROOM

Scale: 1/4" = 1'-0"31

TYP. PATIENT ROOM

Scale: 1/4" = 1'-0"38

TYP. PATIENT SINK

Scale: 1/4" = 1'-0"32

TYP. INFECTION CONTROL ROOM

Scale: 1/4" = 1'-0"33

TYP. INFECTION CONTROL ROOM

Scale: 1/4" = 1'-0"34

TYP. INFECTION CONTROL ROOM

Scale: 1/4" = 1'-0"21

3B119 MED ROOM

Scale: 1/4" = 1'-0"27

3B154 MED ROOM

Scale: 1/4" = 1'-0"25

3B154 MED ROOM

Scale: 1/4" = 1'-0"23

3B153 NOURISHMENT

Scale: 1/4" = 1'-0"39

TYP. NURSE WORKROOM

GENERAL INT. ELEVATION NOTES

A. See Sheet AF101-F for Floor Finish Plan.

B. See Sheet A511 for Casework Details.

C. See Sheet AF601 for Room Finish Schedule.

D. See Sheet AF601 for Finish Materials Legend.

E. Provide tile substrate as follows: All Restrooms, HAC will receive Water-resistant gyp. board. Kitchen will receive Gyp. board.

F. Coordinate with owner and verify owner-provided equipment.

G. See Sheet A501 for Drop Down Grab Bar Details.

H. See Sheet F902 for Equipment Schedule.

I. See Sheet AS101 for Signage Schedule.

PLAN NOTES

6.09 Stile Plate.

10.06 Aluminum signage standoff post, 1" diameter and 2 1/2" long.

10.08 Back painted glass markerboard. Mount with standoffs.

10.09 Printed lines on markerboard surface.

11.02 Standard headwall. See Elevation 1/A513 for details.

11.03 Bariatric headwall. See Elevation 4/A513 for details.

11.08 Markerboard. See A/A402.

12.10 End panel. Plastic laminate over 3/4" plywood.

12.15 Filler panel. Plastic laminate over 3/4" plywood. Match finish to adjacent cabinet.

12.41 Battery powered electronic keypad cabinet lock, vertical throw.

22.08 Dialysis box. See Plumbing Drawings.

Scale: 1/4" = 1'-0"22

3B153 NOURISHMENT

Scale: 1/4" = 1'-0"18

3B115 NOURISHMENT

Scale: 1/4" = 1'-0"19

3B115 NOURISHMENT

Scale: 1/4" = 1'-0"35

TYP. BARIATRIC ROOM

Scale: 1/4" = 1'-0"36

TYP. BARIATRIC ROOM

Scale: 1/4" = 1'-0"37

TYP. BARIATRIC ROOM

Scale: 1" = 1'-0"A

MARKERBOARD

GFE: GOVERNMENT FURNISHED AND INSTALLED EQUIPMENT

GFE/CI: GOVERNMENT FURNISHED EQUIPMENT, CONTRACTOR INSTALLED

CP/CI: CONTRACTOR PROVIDED, CONTRACTOR INSTALLAED

SUPPLIER/INSTALLER LEGEND

EQUIPMENT SCHEDULE

T a g

Description S u p p lie r

In s ta lle r

W id th

D e p th

H e ig h t

M o u n ti n g L o c a ti o n

OT Overbed Table GFE

PM Physiological Monitor GFE/CI

PR Printer - Desktop GFE 18" 18" 9"

PT Paper Towel Dispenser GFE/CI 42" A.F.F. TO BOTTOM

RF Refrigerator GFE

RR Rapid Response Cart GFE 18" 18" 36"

SB Sharps Box GFE/CI 19" 7" 15" 60" A.F.F. TO TOP

SD Soap Dispenser GFE/CI 42" A.F.F. TO BOTTOM

SE ScrubEx GFE 52" 16 1/2" 78"

SR Shredder Box GFE 22" 15" 35"

SW Open Shelf - Warmer GFE 28" 15" 36"

TM Telemetry Monitor GFE/CI 21" 3" 15"

TR1 Trash Can - Lidded GFE 18" 18" 30"

TR2 Trash Can - Small GFE 18" 18" 18"

TS Tray Storage Cart GFE 42" 72" 36"

UR Undercounter Refrigerator GFE 36" 24" 34"

WC Wall Clock GFE/CI

EQUIPMENT SCHEDULE

T a g

Description S u p p lie r

In s ta lle r

W id th

D e p th

H e ig h t

M o u n ti n g L o c a ti o n

HS Hand Sanitizer GFE/CI 5" 3" 8" 50" A.F.F. TO TOP

IM Ice Machine GFE/CI

IV IV Pole GFE 18" 19" 54"

LB Patient Lift - Bariatric CP/CI 60" 2" 12"

LC Linen Cart GFE 24" 20" 35 3/4"

LP Patient Lift - Typical GFE 60" 2" 12"

LS Linen Storage GFE 60" 28" 36"

MB Marker Board, 15x24 CP/CI

MD Medicine Destruction Box GFE/CI 18" 10" 14"

ME Monitor - eICU GFE/CI

MT Monitor - TV GFE/CI VARIES - SEE ELEVATION

MV Microwave GFE

NC Nurse Charting Terminal GFE/CI

OC1 OmniCell GFE 86" 24 1/2" 77 5/8"

OC2 OmniCell GFE 76 1/4" 24 1/2" 77 5/8"

OC3 OmniCell GFE 51 1/2" 24 1/2" 77 5/8"

OS Open Shelf GFE 36" 18" 36"

EQUIPMENT SCHEDULE

T a g

Description S u p p lie r

In s ta lle r

W id th

D e p th

H e ig h t

M o u n ti n g L o c a ti o n

GFE

Mobile Pedestal GFE 15" 18" 25 3/8"

AL Alex Automated Linen GFE 72" 30" 84"

BB Patient Bed - Bariatric GFE

BC Bed Camera Monitor GFE/CI 21" 3" 15"

BP Patient Bed - Typical GFE

BT Blue Tarp Storage Cart GFE 60" 26" 36"

BW Blanket Warmer GFE 22" 30" 36"

CB Cabinet - Staff CP/CI 24" 18" 36"

CC Crash Cart GFE 40" 24" 36"

CM Coffee Maker GFE

CP Copy/Print/Fax GFE 30" 38" 36"

CU Cabinet - Patient CP/CI 24" 12" 30"

FE Fire Extinguisher CP/CI

GB Glove Box GFE/CI 11 1/2" 4 1/4" 22 1/2" 80" A.F.F. TO TOP

HB Headwall - Bariatric CP/CI 136" 4" 96"

Revision s

Date

8 Addendum #1 06.02.2020

122 123 124 125

FWP-1FWP-1 FWP-1FWP-1FWP-1

FWP-1FWP-1FWP-1 FWP-1FWP-1 FWP-1FWP-1FWP-1

RB-1

CG-2CG-2

CG-1 CG-1

CG-2 CG-2

CG-2 CG-1

A402

Sim

P-1 P-1

P-1 P-1

A.1 A.1

123b 124b

A A A A

A

A512

NCNCNCNCNC

B5 B5 B5 B5 B5CG-1CG-1 A.1A.1

23.0423.0426.03 26.03

26.03

26.03

26.03 A A

A A A

PR-1

PR-1

PR-1

PR-1

PR-1

PR-1

PR-1

PR-1

PR-1

PR-1

CG-3 HR-1

CR-1

RB-2 SS-1 RB-1

HR-2

CR-2

RB-1

RWC-1

RWC-2

P-2 P-2

P-5

P-2

9.27F F C

OPEN OPEN OPEN

CG-1

EG-1

CG-3

CORRIDOR

C3-17

CORRIDOR

C3-14

ALCOVE

3B166

CORRIDOR

C3-20

M

120128

D C

RWC-2

CG-1CG-1

P-1

KI

116 111 109 107

HR-1

CR-1

HR-1 CR-1 RB-2SS-1 RB-1 RWC-1 RWC-1

P-5

P-2 P-2

9.27 C C C C

OPEN OPEN

CORRIDOR

C3-19

CORRIDOR

C3-26

RB-2

B

106a

CG-3

8.14 8.14 C

105 108 110

CG-1 CG-2CG-1 CG-1

CG-2 CG-2

CG-1 CG-1

FWP-1FWP-1FWP-1FWP-1FWP-1FWP-1FWP-1FWP-1FWP-1

RB-1 RB-1

A402

Sim

P-1

FWP-1 FWP-1

P-1

P-1 CA.1

OPEN

EG-1 EG-1

OPEN

NOURISHMENT

3B115

CORRIDOR

C3-187

A512

B5 B5 B5

NC NC NC

AAA

10.41

PR-1

PR-1

A

26.03

A

PR-1

PR-1

26.03

PR-1

PR-1

A

26.03

EQUIPMENT TAG

WINDOW OPENING

DOOR OPENING

FINISH DESIGNATION

X

XX

SIGNAGE TAG

TOILET ACCESSORY TAGX

X

TAG LEGEND

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

INTERIOR ELEVATIONS -

CORRIDORS

A403

MWTH

17005.00

552-18-102

Dayton Ohio

Scale: 1/4" = 1'-0"40

CORRIDOR

Scale: 1/4" = 1'-0"41

CORRIDOR

Scale: 1/4" = 1'-0"42

CORRIDOR

Scale: 1/4" = 1'-0"43

CORRIDOR

GENERAL INT. ELEVATION NOTES

A. See Sheet AF101-F for Floor Finish Plan.

B. See Sheet A511 for Casework Details.

C. See Sheet AF601 for Room Finish Schedule.

D. See Sheet AF601 for Finish Materials Legend.

E. Provide tile substrate as follows: All Restrooms, HAC will receive Water-resistant gyp. board. Kitchen will receive Gyp. board.

F. Coordinate with owner and verify owner-provided equipment.

G. See Sheet A501 for Drop Down Grab Bar Details.

H. See Sheet F902 for Equipment Schedule.

I. See Sheet AS101 for Signage Schedule.

PLAN NOTES

8.14 Electronic card reader.

9.27 Gypsum board soffit.

10.41 Semi-recessed fire extinguisher cabinet.

23.04 Room pressure monitor.

26.03 Sconce light. Mount to HPL phenolic panel.

GFE: GOVERNMENT FURNISHED AND INSTALLED EQUIPMENT

GFE/CI: GOVERNMENT FURNISHED EQUIPMENT, CONTRACTOR INSTALLED

CP/CI: CONTRACTOR PROVIDED, CONTRACTOR INSTALLAED

SUPPLIER/INSTALLER LEGEND

EQUIPMENT SCHEDULE

T a g

Description S u p p lie r

In s ta lle r

W id th

D e p th

H e ig h t

M o u n ti n g L o c a ti o n

OT Overbed Table GFE

PM Physiological Monitor GFE/CI

PR Printer - Desktop GFE 18" 18" 9"

PT Paper Towel Dispenser GFE/CI 42" A.F.F. TO BOTTOM

RF Refrigerator GFE

RR Rapid Response Cart GFE 18" 18" 36"

SB Sharps Box GFE/CI 19" 7" 15" 60" A.F.F. TO TOP

SD Soap Dispenser GFE/CI 42" A.F.F. TO BOTTOM

SE ScrubEx GFE 52" 16 1/2" 78"

SR Shredder Box GFE 22" 15" 35"

SW Open Shelf - Warmer GFE 28" 15" 36"

TM Telemetry Monitor GFE/CI 21" 3" 15"

TR1 Trash Can - Lidded GFE 18" 18" 30"

TR2 Trash Can - Small GFE 18" 18" 18"

TS Tray Storage Cart GFE 42" 72" 36"

UR Undercounter Refrigerator GFE 36" 24" 34"

WC Wall Clock GFE/CI

EQUIPMENT SCHEDULE

T a g

Description S u p p lie r

In s ta lle r

W id th

D e p th

H e ig h t

M o u n ti n g L o c a ti o n

HS Hand Sanitizer GFE/CI 5" 3" 8" 50" A.F.F. TO TOP

IM Ice Machine GFE/CI

IV IV Pole GFE 18" 19" 54"

LB Patient Lift - Bariatric CP/CI 60" 2" 12"

LC Linen Cart GFE 24" 20" 35 3/4"

LP Patient Lift - Typical GFE 60" 2" 12"

LS Linen Storage GFE 60" 28" 36"

MB Marker Board, 15x24 CP/CI

MD Medicine Destruction Box GFE/CI 18" 10" 14"

ME Monitor - eICU GFE/CI

MT Monitor - TV GFE/CI VARIES - SEE ELEVATION

MV Microwave GFE

NC Nurse Charting Terminal GFE/CI

OC1 OmniCell GFE 86" 24 1/2" 77 5/8"

OC2 OmniCell GFE 76 1/4" 24 1/2" 77 5/8"

OC3 OmniCell GFE 51 1/2" 24 1/2" 77 5/8"

OS Open Shelf GFE 36" 18" 36"

EQUIPMENT SCHEDULE

T a g

Description S u p p lie r

In s ta lle r

W id th

D e p th

H e ig h t

M o u n ti n g L o c a ti o n

GFE

Mobile Pedestal GFE 15" 18" 25 3/8"

AL Alex Automated Linen GFE 72" 30" 84"

BB Patient Bed - Bariatric GFE

BC Bed Camera Monitor GFE/CI 21" 3" 15"

BP Patient Bed - Typical GFE

BT Blue Tarp Storage Cart GFE 60" 26" 36"

BW Blanket Warmer GFE 22" 30" 36"

CB Cabinet - Staff CP/CI 24" 18" 36"

CC Crash Cart GFE 40" 24" 36"

CM Coffee Maker GFE

CP Copy/Print/Fax GFE 30" 38" 36"

CU Cabinet - Patient CP/CI 24" 12" 30"

FE Fire Extinguisher CP/CI

GB Glove Box GFE/CI 11 1/2" 4 1/4" 22 1/2" 80" A.F.F. TO TOP

HB Headwall - Bariatric CP/CI 136" 4" 96"

Revision s

Date

8 Addendum #1 06.02.2020

RWC-1

CR-1

RB-2 CG-3

HR-2

CR-2

RB-1

SS-1RB-1

RWC-2

RWC-1RB-1

P-2 P-2

P-5P-1 C C

OPEN OPEN

CORRIDOR

C3-20

CORRIDOR

C3-27

9.27

106 1551028

CG-1

EG-1BB

P-2 E

HR-1CG-3

I

135 137

137c 138c

138 140 142

FWP-1

CG-2CG-1 CG-2 CG-1 CG-1 CG-2

CG-2 CG-2

FWP-1 FWP-1FWP-1 FWP-1FWP-1FWP-1FWP-1FWP-1FWP-1 FWP-1FWP-1FWP-1

A402

Sim

RWC-2

P-1

P-1 P-1

P-1P-1

A.1A.1

P-1

RWC-2

EG-1EG-1EG-1

A A A A A

A512

B5 B5 B5 B5 B5

NC NC NC NC NC

RB-1

FWP-1

23.0523.0523.04 23.04

FWP-1

PR-1

PR-1

PR-1

PR-1

PR-1

PR-1 PR-1

PR-1

PR-1

PR-1

A A A A A

26.03 26.03 26.03 26.03 26.03

CR-2

HR-2

164139152

RB-1

CG-1 CG-3

P-2

HR-1

CR-1

RB-2SS-1

RB-1

RWC-2

RWC-1RB-1

P-5

P-2

9.27 C C C C C

OPEN OPEN

OPEN

EG-1EG-1

CORRIDOR

C3-19

NOURISHMENT

3B153

CORRIDOR

C3-26

M

130a

F

8.148.14 8.14

K

8.14

3C-27 160 159 158

CG-1 CG-2

FWP-1FWP-1FWP-1 FWP-1FWP-1FWP-1 FWP-1FWP-1FWP-1

RB-1

A402

Sim

CG-1 CG-1

CG-2

CG-2

CG-1

P-1 P-1

P-1 P-1P-1

A.1

103 8

P-1

A A A

A512

C C

B5 B5

NC NC NC

B5

8.148.14

F K

PR-1

PR-1

PR-1

PR-1

PR-1

PR-1

AAA

26.03

26.03 26.03

8 8

EQUIPMENT TAG

WINDOW OPENING

DOOR OPENING

FINISH DESIGNATION

X

XX

SIGNAGE TAG

TOILET ACCESSORY TAGX

X

TAG LEGEND

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

INTERIOR ELEVATIONS -

CORRIDORS

A404

MWTH

17005.00

552-18-102

Dayton Ohio

Scale: 1/4" = 1'-0"45

CORRIDOR

Scale: 1/4" = 1'-0"46

CORRIDOR

Scale: 1/4" = 1'-0"47

CORRIDOR

Scale: 1/4" = 1'-0"44

CORRIDOR

GENERAL INT. ELEVATION NOTES

A. See Sheet AF101-F for Floor Finish Plan.

B. See Sheet A511 for Casework Details.

C. See Sheet AF601 for Room Finish Schedule.

D. See Sheet AF601 for Finish Materials Legend.

E. Provide tile substrate as follows: All Restrooms, HAC will receive Water-resistant gyp. board. Kitchen will receive Gyp. board.

F. Coordinate with owner and verify owner-provided equipment.

G. See Sheet A501 for Drop Down Grab Bar Details.

H. See Sheet F902 for Equipment Schedule.

I. See Sheet AS101 for Signage Schedule.

PLAN NOTES

8.14 Electronic card reader.

9.27 Gypsum board soffit.

23.04 Room pressure monitor.

23.05 Room pressure sensor.

26.03 Sconce light. Mount to HPL phenolic panel.

GFE: GOVERNMENT FURNISHED AND INSTALLED EQUIPMENT

GFE/CI: GOVERNMENT FURNISHED EQUIPMENT, CONTRACTOR INSTALLED

CP/CI: CONTRACTOR PROVIDED, CONTRACTOR INSTALLAED

SUPPLIER/INSTALLER LEGEND

EQUIPMENT SCHEDULE

T a g

Description S u p p lie r

In s ta lle r

W id th

D e p th

H e ig h t

M o u n ti n g L o c a ti o n

OT Overbed Table GFE

PM Physiological Monitor GFE/CI

PR Printer - Desktop GFE 18" 18" 9"

PT Paper Towel Dispenser GFE/CI 42" A.F.F. TO BOTTOM

RF Refrigerator GFE

RR Rapid Response Cart GFE 18" 18" 36"

SB Sharps Box GFE/CI 19" 7" 15" 60" A.F.F. TO TOP

SD Soap Dispenser GFE/CI 42" A.F.F. TO BOTTOM

SE ScrubEx GFE 52" 16 1/2" 78"

SR Shredder Box GFE 22" 15" 35"

SW Open Shelf - Warmer GFE 28" 15" 36"

TM Telemetry Monitor GFE/CI 21" 3" 15"

TR1 Trash Can - Lidded GFE 18" 18" 30"

TR2 Trash Can - Small GFE 18" 18" 18"

TS Tray Storage Cart GFE 42" 72" 36"

UR Undercounter Refrigerator GFE 36" 24" 34"

WC Wall Clock GFE/CI

EQUIPMENT SCHEDULE

T a g

Description S u p p lie r

In s ta lle r

W id th

D e p th

H e ig h t

M o u n ti n g L o c a ti o n

HS Hand Sanitizer GFE/CI 5" 3" 8" 50" A.F.F. TO TOP

IM Ice Machine GFE/CI

IV IV Pole GFE 18" 19" 54"

LB Patient Lift - Bariatric CP/CI 60" 2" 12"

LC Linen Cart GFE 24" 20" 35 3/4"

LP Patient Lift - Typical GFE 60" 2" 12"

LS Linen Storage GFE 60" 28" 36"

MB Marker Board, 15x24 CP/CI

MD Medicine Destruction Box GFE/CI 18" 10" 14"

ME Monitor - eICU GFE/CI

MT Monitor - TV GFE/CI VARIES - SEE ELEVATION

MV Microwave GFE

NC Nurse Charting Terminal GFE/CI

OC1 OmniCell GFE 86" 24 1/2" 77 5/8"

OC2 OmniCell GFE 76 1/4" 24 1/2" 77 5/8"

OC3 OmniCell GFE 51 1/2" 24 1/2" 77 5/8"

OS Open Shelf GFE 36" 18" 36"

EQUIPMENT SCHEDULE

T a g

Description S u p p lie r

In s ta lle r

W id th

D e p th

H e ig h t

M o u n ti n g L o c a ti o n

GFE

Mobile Pedestal GFE 15" 18" 25 3/8"

AL Alex Automated Linen GFE 72" 30" 84"

BB Patient Bed - Bariatric GFE

BC Bed Camera Monitor GFE/CI 21" 3" 15"

BP Patient Bed - Typical GFE

BT Blue Tarp Storage Cart GFE 60" 26" 36"

BW Blanket Warmer GFE 22" 30" 36"

CB Cabinet - Staff CP/CI 24" 18" 36"

CC Crash Cart GFE 40" 24" 36"

CM Coffee Maker GFE

CP Copy/Print/Fax GFE 30" 38" 36"

CU Cabinet - Patient CP/CI 24" 12" 30"

FE Fire Extinguisher CP/CI

GB Glove Box GFE/CI 11 1/2" 4 1/4" 22 1/2" 80" A.F.F. TO TOP

HB Headwall - Bariatric CP/CI 136" 4" 96"

Revision s

Date

8 Addendum #1 06.02.2020

9.60

12.31

12.22

12.30

12.20

Drawer

B1

9.60

12.31

12.30

12.20

Sink

12.21

Drawer

Drawer

B2B3B4

W1

9.60

12.29

12.30

12.19

12.21

1'-0"

12.30

12.31

12.22

12.21

12.12

W2

Drawer

Drawer

12.27

Sink

12.20 8"

2'-1"

1'-8"

1"

/2

/2

12.12

12.21

12.29

12.30

12.31

11.32

12.21

/2

1"

2'-1" 2'-1" 2'-1"

1"

/2

3"3"

/4

3"

/2

2' - 1"

/2

B6

12.20

12.19

12.19

12.20

12.19

W3

12.30

12.31

12.21

12.12

1' - 0" 1' - 0"

1' - 8"

12.29

12.29

12.28

3"

12.32

22.06

22.09

12.29 12.29

3"

3"

" 12.05

12.31

12.21

9.60

12.20

12.22

1'-6"

A511

1"

3"

12.32

12.14

/4

/4

/4

/4

/4

A511

B5

12.17

12.1712.17

12.21

11 1/8"

12.41

6.09

2' - 9 3/8"

3' - 5 1/2"

1 1/2" 2"

/4

12.21

12.05

12.30

12.31

12.07

12.0612.13

12.14

1" 2' - 9 1/2" 1"

3' - 5 1/2"

/4

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

CASEWORK SECTIONS &

DETAILS

A511

MWTH

17005.00

552-18-102

Dayton Ohio

Scale: 1" = 1'-0"1

CASEWORK SECTIONS

6.09 Stile Plate.

9.60 Resilient base. See Room Finish Schedule.

11.32 Owner provided and installed microwave. See

Electrical and Plumbing Drawings.

12.05 Recessed pull.

12.06 Fixed shelf. Plastic laminate over 3/4" plywood.

12.07 3/4" solid wood edge.

12.12 Soffit panel. Plastic laminate over 3/4" plywood.

Match finish to cabinet body finish.

12.13 Cabinet base panel. Plastic laminate over 3/4"

plywood.

12.14 Cutout gap in base panel for ventilation, 1" D.

12.17 Side splash. See Elevations for locations.

12.19 Applied solid surface backsplash.

12.20 Solid surface material over 3/4" plywood, with

1/4" eased edge.

12.21 Plastic laminate over 3/4" plywood.

12.22 Adjustable shelf. Plastic laminate over 3/4"

plywood.

12.27 Removable panel with concealed fasteners:

Plastic laminate over 3/4" plywood.

12.28 In-wall recessed countertop support bracket, 18"

x 20".

12.29 4" wire pull.

12.30 Self-latching, key-operated lock.

12.31 Concealed hinge.

12.32 2" Wire management grommet. Coordinate exact location with COR.

12.41 Battery powered electronic keypad cabinet lock, vertical throw.

22.06 Undermount solid surface sink bowl.

22.09 Drop-in stainless steel sink. See Plumbing

Drawings.

DETAIL NOTES

GENERAL CASEWORK NOTES

A. See Interior Elevations on sheet A401-A406 for further information.

B. Lift hangers and bracing to be attatched to structural steel only. No attatchment to deck permitted.

Scale: 1" = 1'-0"2

B5 NURSE STATION

Scale: 1" = 1'-0"3

B5 NURSE STATION

Revision s

Date

/2

/2 " 9"

2' - 9"

3"4 3/4"

12.20

12.2012.20

9.609.60

12.28

9.219.21

1 1/2"

12.32

2' - 6"

2' - 1 1/4"

12.20

2' - 9"

3"4 3/4"

12.20

12.28

9.609.60

9.219.21

12.20

1 1/2"

12.32

/2

12.2012.20

/2

2' - 1"

12.20

12.19

12.28

4 3/4" 3"

/4

/4

/4

12.2012.20

9.219.21

12.21

12.21

26.03

12.39

4 1/2" 9" 4 1/2"

V a ri e s

/4

/8

B a s e

1' - 6"

A512

GLOVES

GOWNS

BOOTIES

BOUFFANTS

1' - 6"

12.36

12.36

/4

/2

/2

/2

/2

/2

/4

GLOVES GLOVES

MASKS

MISCELLANEOUS

12.36

12.37

12.37

12.21

12.3812.38

CEILING PLANE

PR-1

PL-3

PL-3

PL-3

PL-3

PL-3

PL-3

PL-3

PL-3

12.39

PR-1

R u b b e r

B a s e

U p t o C e ili n g P la n e

26.03

12.36

12.37

9.21

6"

5/8"

3/8"

5 3/8"

5/8"

3/8"

/4

" 1

/2

/2

/2

/2

/2

/4

9.21

9.60

12.36

12.37

12.36

12.40

10.05

12.39

CEILING PLANE

PR-1

PR-1

CONTROL

CENTER

C3-15

4' - 11 1/2" 4' - 0 1/2"2' - 6"

/2

2' - 0"

12.32

TYP.

CONTROL

CENTER

C3-25

1' - 10 5/8" 4' - 3 3/8" 2' - 4"

/8

2' - 0"

12.32

TYP.

3' - 10" 5' - 0 1/8" 4' - 7 1/4" 1' - 11 1/2"

12.32

TYP.

/4

3' - 3 1/2" 5' - 2" 5' - 0" 5' - 0"

12.32

TYP.

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

CASEWORK SECTIONS &

DETAILS

A512

MWTH

17005.00

552-18-102

Dayton Ohio

Scale: 1" = 1'-0"1

CONTROL CENTER SECTION

Scale: 1" = 1'-0"2

CONTROL CENTER SECTION

Scale: 1" = 1'-0"3

CONTROL CENTER SECTION

Scale: 1" = 1'-0"4

CONTROL CENTER DETAIL

Scale: 1" = 1'-0"5

PPE STORAGE CABINET

Scale: 1" = 1'-0"6

PPE STORAGE CABINET

9.21 5/8" Type X gypsum board. Provide cement backer board where tile is indicated on the finish plans.

9.60 Resilient base. See Room Finish Schedule.

10.05 Sign Type A. Mount directly to high pressure

laminate phenolic door.

12.19 Applied solid surface backsplash.

12.20 Solid surface material over 3/4" plywood, with

1/4" eased edge.

12.21 Plastic laminate over 3/4" plywood.

12.28 In-wall recessed countertop support bracket, 18"

x 20".

12.32 2" Wire management grommet. Coordinate exact location with COR.

12.36 Adjustable shelf. Plastic laminate over 1/2"

plywood.

12.37 Fixed shelf. Plastic laminate over 1/2" plywood.

12.38 Plastic laminate over 1/2" plywood.

12.39 3/8" High pressure laminate phenolic panel.

12.40 3/8" High pressure laminate phenolic door with continuous hinge.

26.03 Sconce light. Mount to HPL phenolic panel.

DETAIL NOTES

GENERAL CASEWORK NOTES

A. See Interior Elevations on sheet A401-A406 for further information.

B. Lift hangers and bracing to be attatched to structural steel only. No attatchment to deck permitted.

Scale: 1/4" = 1'-0"7

C3-15 CONTROL CENTER GROMMETS

Scale: 1/4" = 1'-0"8

C3-25 CONTROL CENTER GROMMETS

Scale: 1/4" = 1'-0"9

C3-15 CONTROL CENTER GROMMETS - DEDUCT ALT

Scale: 1/4" = 1'-0"10

C3-25 CONTROL CENTER GROMMETS - DEDUCT ALT

Revision s

Date

REGULAR POWER

EMERGENCY POWER

DATA

OXYGEN

AIR

CODE BLUE

NURSE CALL

HEADWALL LEGEND

eICU

OVER BED LIGHT SWITCH

VACUUM WITH TRACKS

32 PIN CONNECTION

12.09

PL-1

SS-3

PL-1

P-8

RB-1

2' - 0" 2' - 0" 2' - 8" 2' - 8" 2' - 0"

P-8

SB

22.08

11.0611.06

3"

4 1/2" 4 1/2"

4 1/2"4 1/2" 4 1/2"

4 1/2"

3" 3"

4 1/2" 4 1/2"

1' - 8"

A513

Sim

A513

Sim

C O

R R

ID

O

R S

ID

E

W

IN

D O

W S

ID

E

4" 8" 4" 4" 4" 4" 8" 4"

PM

11.0711.07

9.41

RB-1

P-8 P-8

12.09

PL-1

PL-1

SS-3

9.46

2' - 0" 4' - 0" 2' - 0" 2' - 0"

SB

A513

A513

11.06

3"

4 1/2" 4 1/2"

4 1/2"

3"

4 1/2" 4 1/2"

4 1/2"

7 1/2"1' - 8"

4 1/2" 4 1/2"

1' - 7"

22.08

W

IN

D O

W S

ID

E

C O

R R

ID

O

R S

ID

E

4"4"8"4" 4" 4" 8" 4" 4"

PM

9.41

11.0711.07

11.05

11.18

5.32

2.282.28

2.27

11.1911.19

5.33

11.22

12.20

11.38

4.2

S1.1

9.60

9.41

11.06

11.07

1' - 10 3/4" 2' - 6 1/4"

5.32

2.27

S1.1

9.60

9.41

12.23

11.07

11.0711.07

12.21

12.22

12.31

12.29

12.30

12.21

12.29

12.30

12.20

1"

/2

EQUIPMENT TAG

WINDOW OPENING

DOOR OPENING

FINISH DESIGNATION

X

XX

SIGNAGE TAG

TOILET ACCESSORY TAGX

X

TAG LEGEND

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

HEADWALL DETAILS

A513

MWTH

17005.00

552-18-102

Dayton Ohio

Scale: 3/4" = 1'-0"4

TYP. BARIATRIC HEADWALL @ 3B110, 3B135, & 3B138

Scale: 3/4" = 1'-0"1

TYP. PATIENT HEADWALL

2.27 Existing roof deck. See structural.

2.28 Existing roof framing. See structural

5.01 Structural steel frame. See Structural Drawings.

5.32 New modular channel units or structural steel by

lift manufacturer. See structural drawings.

Coordinate final location of patient lift supports and hangers with lift manufacturer and all PMEFPT trades.

5.33 Patch spray-on fire proofing on existing steel

structure as required.

9.41 Suspended acoustic ceiling tile/grid. See Room

Finish Schedule.

9.46 Align ceiling grid with edge of headwall. See

Reflected Ceiling Plan for details.

9.60 Resilient base. See Room Finish Schedule.

11.01 Patient lifts and structural supports provided by

lift manufacturer.

11.05 Standard patient lift.

11.06 Headwall acrylic accent panel.

11.07 Headwall laminate panel.

11.10 Patient lift structure provided by lift manfuacturer.

See structural dwgs.

11.18 New/existing mechanical ductwork. see

Mechanical drawings for approximate locations.

Verify locations of existing ductwork to remain and adjust supports as necessary. Lift manufacturer to participate in preparation of PME coordination drawings by providing/coordinating lift support requirements.

11.19 Unistrut or other lift support by lift manufacturuer.

11.20 New recessed fixed lift rail with hangers, lateral

bracing, trapeze and supplemental structure as required. Coordinate location of lift supports with mechanical contractor and other trades.

11.21 Traveling rail.

11.22 Base cabinet by headwall manfuacturer.

11.38 Wall cabinet by headwall manufacturer.

12.09 Vacuum equipment track.

12.20 Solid surface material over 3/4" plywood, with

1/4" eased edge.

12.21 Plastic laminate over 3/4" plywood.

12.22 Adjustable shelf. Plastic laminate over 3/4"

plywood.

12.23 Sloped top.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .