This pre-solicitation notice announces a requirement by the Department of Veterans Affairs to renovate approximately 17,000 square feet of ICU/TCU space at the Dayton VA Medical Center. Key details include:

  • The project is set aside only for Service-Disabled Veteran-Owned Small Businesses and involves upgrading outdated IT systems associated with the renovation.

  • The solicitation and specifications will be posted on March 20, 2020 on FBO.gov with proposals due approximately 30 days later. Interested parties should register on FBO.gov to receive updates.

  • The project value is estimated between $5-10 million. The NAICS code is 236220 with a small business size standard of $39.5 million.

  • The SDVOSB prime or subcontractor must perform a minimum of 15% of construction work. Bid, payment and performance bonds will be required.

  • A one-time site visit will be scheduled. Amendments will be posted on FBO.gov and questions can be emailed to the point of contact by the deadline. The successful offeror must complete work within 365 calendar days of the notice to proceed.

36C25020B0028 S02. Attachment 3 - Project Drawings - Arch Structural (2 of 2).pdf

View the file

Other files

File Type Posted
36C25020B0028 0006.docx DOCX document
36C25020B0028 0005.docx DOCX document
Site Visit sign-in.pdf PDF
20200702 Addendum 1.pdf PDF
20200701 TCUICU 2nd Floor Room Names.pdf PDF
20200701 TCUICU 2nd Floor RCP.pdf PDF
PreBid RFIs Answers.pdf PDF
36C25020B0028 0004.docx DOCX document
Bid Opening Instructions.pdf PDF
36C25020B0028-0003000.docx DOCX document
36C25020B0028-0002000.docx DOCX document
36C25020B0028-0001000.docx DOCX document
36C25020B0028-0001001.pdf PDF
36C25020B0028-009.pdf PDF
36C25020B0028-007.pdf PDF
36C25020B0028-005.pdf PDF
36C25020B0028-008.pdf PDF
36C25020B0028-002.pdf PDF
36C25020B0028-006.pdf PDF
36C25020B0028-003.pdf PDF
36C25020B0028-001.docx DOCX document
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P-5

SS-1

RB-1

SS-1

RB-1

P-5

5' - 8 1/2" 5' - 0" 5' - 0" 5' - 8"

SR

PRBCBC

SS-1SS-1

P-2

RB-1

12.28

P-5

4' - 2 1/2"5' - 0"5' - 0"5' - 0"4' - 2"

RB-1

P-2

SS-1SS-1

P-5

12.28

SS-1

RB-1

P-5

9.27

SS-1

RB-1

P-5

9.27

TM

3' - 4 1/2" 5' - 0" 5' - 0" 5' - 0"

PR

P-5

SS-1SS-1

RB-1

P-2

12.28

CP

B1 B1 B1

3' - 0"3' - 6"3' - 0"

SS-1

PL-1

RB-1

P-1

BC BC

4' - 2" 5' - 0" 5' - 0" 4' - 2 1/2"

P-5

RB-1

P-2

SS-1SS-1

12.28

CP

3' - 0" 3' - 0" B1 B1

RB-1

PL-1

SS-1

A512

A512

A512

A512

A512

A512

19' - 6"

" 9"

2' - 9"

6' - 0"

2'

2"

12.32

TYP.

A512

A512

A512

A512

24' - 6"

9"

2' - 9"

9' - 6"

2'

2"

A512

A512

12.32

TYP.

EQUIPMENT TAG

WINDOW OPENING

DOOR OPENING

FINISH DESIGNATION

X

XX

SIGNAGE TAG

TOILET ACCESSORY TAGX

X

TAG LEGEND

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

ENLARGED PLANS & INTERIOR

ELEVATIONS - DEDUCT

ALTERNATE

A406

MWTH

17005.00

552-18-102

Dayton Ohio

Scale: 1/4" = 1'-0"6

C3-25 CONTROL CENTER

Scale: 1/4" = 1'-0"7

C3-25 CONTROL CENTER

Scale: 1/4" = 1'-0"8

C3-25 CONTROL CENTER

Scale: 1/4" = 1'-0"9

C3-25 CONTROL CENTER

Scale: 1/4" = 1'-0"1

C3-15 CONTROL CENTER

Scale: 1/4" = 1'-0"2

C3-15 CONTROL CENTER

Scale: 1/4" = 1'-0"3

C3-15 CONTROL CENTER

Scale: 1/4" = 1'-0"10

C3-25 CONTROL CENTER

Scale: 1/4" = 1'-0"4

C3-15 CONTROL CENTER

Scale: 1/4" = 1'-0"5

C3-15 CONTROL CENTER

Scale: 1/4" = 1'-0"A

C3-15 CONTROL CENTER - DEDUCT ALT #1, 2

Scale: 1/4" = 1'-0"B

C3-25 CONTROL CENTER - DEDUCT ALT #1, 2

GENERAL INT. ELEVATION NOTES

A. See Sheet AF101-F for Floor Finish Plan.

B. See Sheet A511 for Casework Details.

C. See Sheet AF601 for Room Finish Schedule.

D. See Sheet AF601 for Finish Materials Legend.

E. Provide tile substrate as follows: All Restrooms, HAC will receive Water-resistant gyp. board. Kitchen will receive Gyp. board.

F. Coordinate with owner and verify owner-provided equipment.

G. See Sheet A501 for Drop Down Grab Bar Details.

H. See Sheet F902 for Equipment Schedule.

I. See Sheet AS101 for Signage Schedule.

PLAN NOTES

9.27 Gypsum board soffit.

12.28 In-wall recessed countertop support bracket, 18" x 20".

12.32 2" Wire management grommet. Coordinate exact location with COR.

Revision s

Date

7 100% For Bid 03.09.2020

1' - 6"

9.02 9.44 9.315.175.195.20 5.26

/2

/2

1 1/2" 4 1/2" 4 1/2" 1 1/2"

5.277.06 7.06

5.18

330-THIRD FLOOR

126' - 0"

5.20 9.31

9.02

5.31

/4

2' - 6 1/2"

M in

5"

7.06

7.06

5.30

S2.0

5.19

5.17

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

MISCELLANEOUS DETAILS

A501

DWTH

17005.00

552-18-102

Dayton Ohio

Scale: 1 1/2" = 1'-0"1

DROP DOWN GRAB BAR PLAN

Scale: 1 1/2" = 1'-0"2

DROP DOWN GRAB BAR SECTION

PLAN NOTES

5.17 TS 6" x 3" x 1/4" welded to bottom plate w/ 3/16" weld.

5.18 Drop down grab bar.

5.19 3/8" diameter expansion anchor with 2 3/4" embed.

5.20 3/8" steel base plate.

5.26 Metal sleeve.

5.27 Mounting bracket.

5.30 Welded metal spacer to follow swing up grab bar mounting bracket profile.

5.31 Fasterners as required by grab bar manufacturer.

7.06 Sealant.

9.02 3 5/8" non-structural metal framing @ 16" o.c.

9.31 Ceramic wall tile.

9.44 5/8" cement board.

TYPICAL AT EACH PATIENT TOILET

Revision s

9.60

12.31

12.22

12.30

12.20

Drawer

B1

9.60

12.31

12.30

12.20

Sink

12.21

Drawer

Drawer

B2B3B4

W1

9.60

12.29

12.30

12.19

12.21

1'-0"

12.30

12.31

12.22

12.21

12.12

W2

Drawer

Drawer

12.27

Sink

12.20 8"

2'-1"

1'-8"

1"

/2

/2

12.12

12.21

12.29

12.30

12.31

11.32

12.21

/2

1"

2'-1" 2'-1" 2'-1"

1"

/2

3"3"

/4

3"

/2

2' - 1"

/2

B6

12.20

12.19

12.19

12.20

12.19

W3

12.30

12.31

12.21

12.12

1' - 0" 1' - 0"

1' - 8"

12.29

12.29

12.28

3"

12.32

22.06

22.09

12.29 12.29

3"

3"

12.05

12.30

12.31

12.21

9.60

12.20

12.22

1'-6"

A511

1"

3"

12.32

12.14

/4

/4

/4

/4

/4

A511

B5

12.17

12.1712.17

12.21

11 1/8"

2' - 9 3/8"

3' - 5 1/2"

1 1/2" 2"

/4

12.21

12.05

12.30

12.31

12.07

12.0612.13

12.14

1" 2' - 9 1/2" 1"

3' - 5 1/2"

/4

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

CASEWORK SECTIONS &

DETAILS

A511

MWTH

17005.00

552-18-102

Dayton Ohio

Scale: 1" = 1'-0"1

CASEWORK SECTIONS

9.60 Resilient base. See Room Finish Schedule.

11.32 Owner provided and installed microwave. See

Electrical and Plumbing Drawings.

12.05 Recessed pull.

12.06 Fixed shelf. Plastic laminate over 3/4" particle

board.

12.07 3/4" solid wood edge.

12.12 Soffit panel. Plastic laminate over 3/4" plywood.

Match finish to cabinet body finish.

12.13 Cabinet base panel. Plastic laminate over 3/4"

particle board.

12.14 Cutout gap in base panel for ventilation, 1" D.

12.17 Side splash. See Elevations for locations.

12.19 Applied solid surface backsplash.

12.20 Solid surface material over 3/4" plywood, with

1/4" eased edge.

12.21 Plastic laminate over 3/4" particle board.

12.22 Adjustable shelf. Plastic laminate over 3/4"

particle board.

12.27 Removable panel with concealed fasteners:

Plastic laminate over 3/4" plywood.

12.28 In-wall recessed countertop support bracket, 18"

x 20".

12.29 4" wire pull.

12.30 Self-latching, key-operated lock.

12.31 Concealed hinge.

12.32 2" Wire management grommet. Coordinate exact location with COR.

22.06 Undermount solid surface sink bowl.

22.09 Drop-in stainless steel sink. See Plumbing

Drawings.

DETAIL NOTES

GENERAL CASEWORK NOTES

A. See Interior Elevations on sheet A401-A406 for further information.

B. Lift hangers and bracing to be attatched to structural steel only. No attatchment to deck permitted.

Scale: 1" = 1'-0"2

B5 NURSE STATION

Scale: 1" = 1'-0"3

B5 NURSE STATION

Revision s

/2

/2 " 9"

2' - 9"

3"4 3/4"

12.20

12.2012.20

9.609.60

12.28

9.219.21

1 1/2"

12.32

2' - 6"

2' - 1 1/4"

12.20

2' - 9"

3"4 3/4"

12.20

12.28

9.609.60

9.219.21

12.20

1 1/2"

12.32

/2

12.2012.20

/2

2' - 1"

12.20

12.19

12.28

4 3/4" 3"

/4

/4

/4

12.2012.20

9.219.21

12.21

10.05

26.01

10.07

3" 9" 3"

/4

/4

/2

/2

1' - 3"

A512

GLOVES

THERMOMETERS

STETHOSCOPES

GOWNS

MASKS

1' - 3"

12.22

10.06

4"

8"

26.01

12.22

12.21

10.05

10.07

9.219.21

10.06

10.06

CONTROL

CENTER

C3-15

4' - 11 1/2" 4' - 0 1/2"2' - 6"

/2

2' - 0"

12.32

TYP.

CONTROL

CENTER

C3-25

1' - 10 5/8" 4' - 3 3/8" 2' - 4"

/8

2' - 0"

12.32

TYP.

3' - 10" 5' - 0 1/8" 4' - 7 1/4" 1' - 11 1/2"

12.32

TYP.

/4

3' - 3 1/2" 5' - 2" 5' - 0" 5' - 0"

12.32

TYP.

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

CASEWORK SECTIONS &

DETAILS

A512

MWTH

17005.00

552-18-102

Dayton Ohio

Scale: 1" = 1'-0"1

CONTROL CENTER SECTION

Scale: 1" = 1'-0"2

CONTROL CENTER SECTION

Scale: 1" = 1'-0"3

CONTROL CENTER SECTION

Scale: 1" = 1'-0"4

CONTROL CENTER DETAIL

Scale: 1" = 1'-0"5

PPS STORAGE CABINET

Scale: 1" = 1'-0"6

PPS STORAGE CABINET

9.21 5/8" Type X gypsum board. Provide cement backer board where tile is indicated on the finish plans.

9.60 Resilient base. See Room Finish Schedule.

10.05 Sign Type A. Mount directly to acrylic panel.

10.06 Aluminum signage standoff post, 1" diameter

and 2 1/2" long.

10.07 AR-1, Acrylic resin panel.

12.19 Applied solid surface backsplash.

12.20 Solid surface material over 3/4" plywood, with

1/4" eased edge.

12.21 Plastic laminate over 3/4" particle board.

12.22 Adjustable shelf. Plastic laminate over 3/4"

particle board.

12.28 In-wall recessed countertop support bracket, 18"

x 20".

12.32 2" Wire management grommet. Coordinate exact location with COR.

26.01 Light fixture. See Electrical Drawings.

DETAIL NOTES

GENERAL CASEWORK NOTES

A. See Interior Elevations on sheet A401-A406 for further information.

B. Lift hangers and bracing to be attatched to structural steel only. No attatchment to deck permitted.

Scale: 1/4" = 1'-0"7

C3-15 CONTROL CENTER GROMMETS

Scale: 1/4" = 1'-0"8

C3-25 CONTROL CENTER GROMMETS

Scale: 1/4" = 1'-0"9

C3-15 CONTROL CENTER GROMMETS - DEDUCT ALT

Scale: 1/4" = 1'-0"10

C3-25 CONTROL CENTER GROMMETS - DEDUCT ALT

Revision s

REGULAR POWER

EMERGENCY POWER

DATA

OXYGEN

AIR

CODE BLUE

NURSE CALL

HEADWALL LEGEND

eICU

OVER BED LIGHT SWITCH

VACUUM WITH TRACKS

32 PIN CONNECTION

12.09

PL-1

SS-3

PL-1

P-8

RB-1

2' - 0" 2' - 0" 2' - 8" 2' - 8" 2' - 0"

P-8

SB

22.08

11.0611.06

3"

4 1/2" 4 1/2"

4 1/2"

7 1/2"7 1/2"

4 1/2" 4 1/2"

4 1/2"

3" 3"

4 1/2" 4 1/2"

1' - 8"

A513

Sim

A513

Sim

C O

R R

ID

O

R S

ID

E

W

IN

D O

W S

ID

E

4" 4" 8" 4" 4" 4" 4" 8" 4" 4"

PM

11.0711.07

9.41

RB-1

P-8 P-8

12.09

PL-1

PL-1

SS-3

9.46

2' - 0" 4' - 0" 2' - 0" 2' - 0"

SB

A513

A513

11.06

3"

4 1/2" 4 1/2"

4 1/2"

7 1/2" 3"

4 1/2" 4 1/2"

4 1/2"

7 1/2"1' - 8"

4 1/2" 4 1/2"

1' - 7"

22.08

W

IN

D O

W S

ID

E

C O

R R

ID

O

R S

ID

E

4"4"8"4"4" 4" 4" 8" 4" 4"

PM

9.41

11.0711.07

11.05

11.18

11.18

5.32

2.28

11.10

11.01

2.28

2.27

11.1911.19

11.20

5.33

11.21

11.22

12.20

11.38

4.2

S1.1

9.60

9.41

11.06

11.07

1' - 10 3/4" 2' - 6 1/4"

5.01

5.325.32

11.20

11.21

2.27

2.282.28

11.1811.18

11.19

4"

S1.1

9.60

9.41

12.23

11.07

11.0711.07

12.21

12.22

12.31

12.29

12.30

12.21

12.29

12.30

12.20

1' - 6"

1"

1' - 0"

/2

EQUIPMENT TAG

WINDOW OPENING

DOOR OPENING

FINISH DESIGNATION

X

XX

SIGNAGE TAG

TOILET ACCESSORY TAGX

X

TAG LEGEND

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

HEADWALL DETAILS

A513

MWTH

17005.00

552-18-102

Dayton Ohio

Scale: 3/4" = 1'-0"4

TYP. BARIATRIC HEADWALL @ 3B110, 3B135, & 3B138

Scale: 3/4" = 1'-0"1

TYP. PATIENT HEADWALL

2.27 Existing roof deck. See structural.

2.28 Existing roof framing. See structural

5.01 Structural steel frame. See Structural Drawings.

5.32 New modular channel units by lift manufacturer.

See structural drawings. Coordinate final location of modular channel units supports and hangers with lift manufacturer and all PMEFPT trades.

5.33 Patch spray-on fire proofing on existing steel

structure as required.

9.41 Suspended acoustic ceiling tile/grid. See Room

Finish Schedule.

9.46 Align ceiling grid with edge of headwall. See

Reflected Ceiling Plan for details.

9.60 Resilient base. See Room Finish Schedule.

11.01 Patient lifts and structural supports provided by

lift manufacturer.

11.05 Standard patient lift.

11.06 Headwall acrylic accent panel.

11.07 Headwall laminate panel.

11.10 Patient lift structure provided by lift manfuacturer.

See structural dwgs.

11.18 New/existing mechanical ductwork. see

Mechanical drawings for approximate locations.

Verify locations of existing ductwork to remain and adjust supports as necessary. Lift manufacturer to participate in preparation of PME coordination drawings by providing/coordinating lift support requirements.

11.19 Unistrut or other lift support by lift manufacturuer.

11.20 New recessed fixed lift rail with hangers, lateral

bracing, trapeze and supplemental structure as required. Coordinate location of lift supports with mechanical contractor and other trades.

11.21 Traveling rail.

11.22 Base cabinet by headwall manfuacturer.

11.38 Wall cabinet by headwall manufacturer.

12.09 Vacuum equipment track.

12.20 Solid surface material over 3/4" plywood, with

1/4" eased edge.

12.21 Plastic laminate over 3/4" particle board.

12.22 Adjustable shelf. Plastic laminate over 3/4"

particle board.

12.23 Sloped top. Plastic laminate over 3/4" particle

board

12.29 4" wire pull.

12.30 Self-latching, key-operated lock.

12.31 Concealed hinge.

22.08 Dialysis box. See Plumbing Drawings.

23.01 Mechanical Equipment. See Mechanical

Drawings.

DETAIL NOTES

GENERAL CASEWORK NOTES

A. See Interior Elevations on sheet A401-A406 for further information.

B. Lift hangers and bracing to be attatched to structural steel only. No attatchment to deck permitted.

Scale: 3/4" = 1'-0"2

HEADWALL SECTION

Scale: 3/4" = 1'-0"3

HEADWALL SECTION

Revision s

SEE SCHED.

S E

E S

C H

E D

U L E

FJ

2"

SEE

SCHED. 2"

S E

E S

C H

E D

U L E

3 1/4" SEE SCHEDULE 3 1/4"

/4

S E

E S

C H

E D

U L E

2"

SEE

SCHED. 2"

P A

T

IE

N T

L

IF

T M

A N

U F

A C

T U

R E

R

(C O

O R

D

IN

A T

E W

IT

H

SEE PLAN

1/2" 1/2"

H1J1

8.02

9.21

9.80

8.02

9.09

9.21

9.80

8.04

S1

9.08

7.82

7.82 1/2" 1/2"

J2 H2 S e e P la n

1 3/4"

ROUGH OPENING

PACKAGE WIDTH

See Plan

9.17

9.19 7

O P

E N

IN

G

/8

C L E

A R

P

A C

K A

G E

H E

IG

H

T

R O

U G

H O

P E

N

IN

G

9.20

SEE PLAN

S2

9.02

9.80

6.01

5.10

7.83

9.39

8.09

8.09

7.83

9.39

5.10

6.01 9.21

5.09

9.02

9.80

H4

J4

9.02

9.80

9.21 7.83

8.09

6.036.03

9.13

9.169.14

SEE PLAN

1/2" 1/2"

H6J5

9.21

9.80

9.09

9.21

9.80

9.08

7.82

7.82 1/2" 1/2"

SEE PLAN

8.02

8.03Applicable to all HM Frames

7.83

7.83

7.83

6.01

9.21

5.09

9.02 9.80

9.57

3/4"3/4"

9.66

S2.0

9.21

9.02

7.82

7.82

4 1/4"

9.80

S1.0-F

4 7/8"

9.219.21

9.02

9.80

7.82

7.82

S1.0

4 7/8"

9.219.21

9.02

9.80

7.82

7.82

FLOOR SLAB

FIN. CEILING

STRUCTURE ABOVE

T1.0

4 7/8"

1-HR RATED

FIRE BARRIER

U.L. #U465

S1.0-N

4 7/8"

9.219.21

9.02

9.80

7.82

7.82

NON-RATED

SMOKE PARTITION

S1.1

7 1/4"

9.03

9.80

9.219.21

9.819.81

9.819.81

9.219.21

9.02

9.80

7.82

7.82

1-HR RATED

FIRE BARRIER

U.L. #U465

E1.0

1' - 0"

9.03

9.21

7.82

7.82

9.21

7.14

7.14

4.01

4.23

7.18

4.16

7.18

6.19

A

1' - 4"

S4

A601

H5

A601

8.20

S

IL

L H

E

IG

H T

B

J4

A601

S2

A601

H4

A601

7.83

S

IL

L H

E

IG

H T

2' - 6 7/8" 2' - 6 7/8" 2' - 6 7/8" 2' - 6 7/8"

10' - 3 1/4"

8.16

C

6' - 9 1/2"

2' - 2 7/8" 2' - 2 5/8" 2' - 3 7/8"

J4

A601

S2

A601

H4

A601

7.83

S

IL

L H

E

IG

H T

8.16

D

4' - 7 5/8"

2' - 3 7/8" 2' - 3 7/8"

J4

A601

S2

A601

H4

A601

7.83

S

IL

L H

E

IG

H T

8.16

E

5' - 8 1/4"

2' - 10 1/8" 2' - 10 1/8"

J4

A601

S2

A601

H4

A601

7.83

S

IL

L H

E

IG

H T

8.16

F

J4

A601

S2

A601

H4

A601

7.83

S

IL

L H

E

IG

H T

2' - 4" 2' - 3 3/4" 2' - 4"

6' - 11 3/4"

8.16 7

8' - 0"

DOOR OPENING

4' - 5 3/4" CLEAR

8.25

G

(M

A T

C H

E X

IS

T

3' - 6"

S3

A601

H3

A601

S

IL

L H

E

IG

H T

(M A

T C

H E

X

IS

T

8.25

G-1

J3

A601

8.41

6.19

9.21

7.14

4.16

H3

6.05

7.18

8.19

7.65

S3

7.14

9.21

4.01

4.23

4.26

8.19

J3

3/4" 7.35

/2

7.65

10.25

8.24

6.01 9.21

5.09

9.02

9.80

H5

7.06

9.02

9.80

6.01

S4

8.24

7.83

3/4" 3/4"

9.66

9.21

7.14

6.05

8.19

7.18

6.19

4.16

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

WALL TYPES, DOOR SCHEDULE &

DETAILS

A601

DWTH

17005.00

552-18-102

Dayton Ohio

DOOR SCHEDULE - BASE BID

DOOR

BETWEEN DOOR DESCRIPTION FRAME DESCRIPTION

FIRE

RATING

HDWE

SET REMARKSRM RM TYPE MAT'L

SIZE

TYPE

MAT'L HEAD JAMB# W H T

100 C3-12 3B100 F WD 1 3' - 6" 7' - 0" 1 3/4" EXIST - - - 10 New WD door and HDWE, existing frame.

101 C3-12 3B101 F WD 1 3' - 0" 7' - 0" 1 3/4" EXIST - - - 15 New WD door and HDWE, existing frame.

102 C3-12 3B102 F HM 1 3' - 8" 7' - 0" 1 3/4" EXIST - - - 09 New WD door and HDWE, existing frame.

103 C3-12 3B103 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 07

104 C3-26 3B104 F WD 1 3' - 0" 7' - 0" 1 3/4" EXIST - - - 25A New WD door and HDWE, existing frame.

105 3B105 C3-14 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

105a 3B105 3B105a F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

106 C3-26 3B106 F HM 1 3' - 8" 7' - 0" 1 3/4" EXIST - - - 20 MIN. 18 New WD door and HDWE, existing frame.

106a C3-14 3B106a F WD 1 3' - 8" 7' - 0" 1 3/4" 1 HM H1 J1 20 MIN. 22

107 C3-14 3B107 F WD 1 3' - 8" 7' - 0" 1 3/4" 1 HM H1 J1 20 MIN. 31

108 3B108 C3-14 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

108a 3B108 3B108a F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

109 C3-14 3B109 F WD 1 3' - 8" 7' - 0" 1 3/4" 1 HM H1 J1 20 MIN. 30

110 C3-14 3B110 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

110a 3B110a 3B110 F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

111 3B111 C3-14 F WD 2 2' - 6" 7' - 0" 1 3/4" 1 HM H1 J1 34

112 C3-14 3B112 F WD 1 4' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 20

114 C3-17 3B114 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 12

116 C3-14 3B116 F WD 1 4' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 25

117 C3-17 3B117 F WD 1 3' - 0" 7' - 0" 1 3/4" EXIST - - - 07 New WD door and HDWE, existing frame.

119 C3-17 3B119 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 27

120 C3-18 3B120 F HM 1 3' - 8" 7' - 0" 1 3/4" EXIST - - - 08 New WD door and HDWE, existing frame.

121 3B121 C3-18 J AL/GL 1 8' - 0" 8' - 0" 1 3/4" 3 HM H2 J2 38

121a 3B121a 3B121 F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

122 3B122 C3-19 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

122a 3B122 3B122a F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

123 3B123 C3-19 J AL/GL 1 8' - 0" 7' - 6" 1 3/4"

Alum H2 J2 38 Provide smoke gasketing for Isolation (Infection Control) Room

123a 3B123a 3B123 F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

123b C3-19 3B123b F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 03

123c 3B123 3B123b F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 04

124 3B124 C3-19 J AL/GL 1 8' - 0" 7' - 6" 1 3/4"

Alum H2 J2 38 Provide smoke gasketing for Isolation (Infection Control) Room

124a 3B124 3B124a F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

124b 3B124b C3-19 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 03

124c 3B124b 3B124 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 04

125 3B125 C3-20 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

125a 3B125a 3B125 F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

126 3B126 C3-19 F HM 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 06

128 3B128 C3-19 F HM 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 06

130 C3-22 3B130 F HM 1 3' - 8" 7' - 0" 1 3/4" EXIST - - - 20 MIN. 33 New WD door and HDWE, existing frame.

130a C3-20 3B130 F HM 1 3' - 8" 7' - 0" 1 3/4" EXIST - - - 20 MIN. 28 New WD door and HDWE, existing frame.

135 3B135 C3-20 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

135a 3B135 3B135a F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

137 3B137 C3-20 J AL/GL 1 8' - 0" 7' - 6" 1 3/4"

Alum H2 J2 38 Provide smoke gasketing for Isolation (Infection Control) Room

137a 3B137a 3B137 F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

137b 3B137 3B137b F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 04

137c 3B137b C3-20 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 03

138 3B138 C3-20 J AL/GL 1 8' - 0" 7' - 6" 1 3/4"

Alum H2 J2 38 Provide smoke gasketing for Isolation (Infection Control) Room

138a 3B138 3B138a F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

138b 3B138b 3B138 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 04

138c C3-20 3B138b F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 03

139 3B139 C3-20 F WD 1 4' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 25

140 3B140 C3-20 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

140a 3B140a 3B140 F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

142 3B142 C3-20 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

142a 3B142 3B142a F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

144 3B144 C3-22 F WD 1 3' - 0" 7' - 0" 1 3/4" EXIST - - - 29 New WD door and HDWE, existing frame.

145 C3-20 3B145 F WD 1 3' - 6" 7' - 0" 1 3/4" 1 HM H1 J1 45 MIN. 17

146 C3-23 3B146 F WD 1 3' - 0" 7' - 0" 1 3/4" EXIST - - - 20 MIN. 01 New WD door and HDWE, existing frame.

146a C3-22 3B146 F WD 1 3' - 0" 7' - 0" 1 3/4" EXIST - - - 20 MIN. 02 New WD door and HDWE, existing frame.

147 C3-23 3B147 F WD 1 3' - 0" 7' - 0" 1 3/4" EXIST - - - 20 MIN. 11 New WD door and HDWE, existing frame.

148 3B148 C3-23 G WD 1 3' - 0" 7' - 0" 1 3/4" EXIST - - - 19 New WD door and HDWE, existing frame.

149 C3-23 3B149 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 24

150 C3-23 3B150 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 07

151 C3-27 3B151 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 13

152 C3-20 3B152 F WD 1 3' - 8" 7' - 0" 1 3/4" 1 HM H1 J1 45 MIN. 31

154 C3-27 3B154 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 27

155 C3-26 3B155 F HM 1 3' - 8" 7' - 0" 1 3/4" EXIST - - - 20 MIN. 23 New WD door and HDWE, existing frame.

158 3B158 C3-26 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

158a 3B158 3B158a F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

159 C3-26 3B159 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

159a 3B159a 3B159 F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

160 3B160 C3-26 J AL/GL 1 8' - 0" 7' - 6" 1 3/4" 3 Alum H2 J2 38

160a 3B160a 3B160 F WD 1 3' - 6" 7' - 0" 2" 2 HM H6 J5 05

164 3B164 C3-20 F HM 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 45 MIN. 30

165 3B165 C3-18 F WD 2 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 21

168 3B168 C3-23 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 14

171 C3-26 3B171 F WD 2 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 21

314 C3-26 C3-14 F WD 2 3' - 3" 7' - 0" 1 3/4" 3 HM H1 J1 20 MIN. 35

317 C3-22 C3-17 F HM 1 3' - 8" 7' - 0" 1 3/4" EXIST - - - 20 MIN. 32 New WD door and HDWE, existing frame.

319 C3-19 C3-20 F WD 2 3' - 6" 7' - 0" 1 3/4" 3 HM H1 J1 20 MIN. 35

326 C3-26 C3-12 F WD 2 3' - 6" 7' - 0" 1 3/4" 1 HM H1 J1 36

327 C3-23 C3-27 F WD 1 3' - 0" 7' - 0" 1 3/4" 1 HM H1 J1 26

Scale: 1/4" = 1'-0"

DOOR TYPES

Scale: 1/4" = 1'-0"

FRAME TYPES

DETAIL NOTES

N.T.S.Scale:

FRAME DETAILS

4.01 Brick veneer.

4.16 Limestone panel.

4.23 Masonry veneer anchor.

4.26 Thru wall flashing.

5.09 Cold formed framing box header.

5.10 Fastener

6.01 2" x 4" wood blocking.

6.03 2x wood blocking.

6.05 2" x 6" presure treated wood blocking.

6.19 5/8" exterior glass matt gypsum board sheathing. Seal all joints.

7.06 Sealant.

7.14 Batt thermal wall insulation. R-19 min.

7.18 Air and moisture barrier.

7.35 Sill Flashing.

7.65 Cont. sealant.

7.82 Continuous acoustic sealant @ non-rated walls / fire-rated sealant @ rated walls each side.

7.83 Cont. sealant each side.

8.02 Hollow metal frame.

8.03 Hollow metal window frame.

8.04 Hospital stops @ all interior hollow metal frames.

8.09 1/2" monolithic glass

8.16 All glass window system.

8.19 Window type G.

8.20 Switchable privacy glass.

8.24 Window type A.

8.25 Integral blinds.

8.41 Aluminum window.

9.02 3 5/8" non-structural metal framing @ 16" o.c.

9.03 6" non-structural metal framing @ 16" o.c.

9.08 Metal framing box header.

9.09 Double metal framing at jambs, typ.

9.13 Floor mounted pivot

9.14 Header above

9.16 Recessed slide pulls

9.17 1/4" shim space

9.19 Access cover

9.20 Finished floor

9.21 5/8" Type X gypsum board. Provide cement backer board where tile is indicated on the finish plans.

9.39 U-channel

9.57 5/8" Type X gypsum board.

9.66 3/4" solid surface sill.

9.80 Acoustic insulation

9.81 Acoustic sealant / fire-rated sealant each side

10.25 Solid surface window sill.

N.T.S.Scale:

WALL TYPES

N.T.S.Scale:

WINDOW ELEVATIONS

DOOR SCHEDULE - DEDUCT ALTERNATE #1, #2

DOOR

BETWEEN DOOR DESCRIPTION FRAME DESCRIPTION

FIRE

RATING

HDWE

SET REMARKSRM RM TYPE MAT'L

SIZE

TYPE

MAT'L HEAD JAMB# W H T

106 3B106 C3-14 F WD 1 3' - 8" 7' - 0" 1 3/4" 1 HM H1 J1 45 MIN. 31

107 C3-14 3B107 F WD 1 3' - 8" 7' - 0" 1 3/4" 1 HM H1 J1 45 MIN. 17

109 C3-14 3B109 F WD 1 3' - 8" 7' - 0" 1 3/4" 1 HM H1 J1 45 MIN. 30

111 3B111 C3-14 F WD 2 2' - 6" 7' - 0" 1 3/4" 1 HM H1 J1 34

Revision s

CORRIDOR

C3-29

CONFERENCE

ROOM

3B100

WAITING

ROOM

3B101

CONSULTATION

ROOM

3B102

OFFICE

3B103

LOCKER

ROOM

3B104A

TOILET,

MALE

3B104B

TOILET,

FEMALE

3B104C

LOCKER

ROOM

3B104D

OFFICE

3B120

BEDROOM -

RESIDENT

ON-CALL

3B161

OFFICE,

PHYSICIAN

3B162

BEDROOM -

RESIDENT

ON-CALL

3B163BATH/SHOWER

ROOM

3B161A

CORRIDOR

C3-12

CORRIDOR

C3-14

CORRIDOR

C3-18

CORRIDOR

C3-19

CORRIDOR

C3-20

LOBBY

C3-30

CORRIDOR

C3-11

CORRIDOR

C3-28

STAIR

S-2-3

CORRIDOR

3C-27

CORRIDOR

3C-9

BED ROOM

3B121

RESTROOM

3B121a

RESTROOM

3B122a

BED ROOM

3B122

BED ROOM,

INFECTION

CONTROL

3B123

RESTROOM

3B123a

RESTROOM

3B124a

BED ROOM

3B125

RESTROOM

3B125a

BED ROOM

3B142

RESTROOM

3B142a

RESTROOM

3B140a

BED ROOM

3B140

BARIATRIC,

INFECTION

CONTROL

3B138

RESTROOM

3B138a

RESTROOM

3B137a

BED ROOM,

INFECTION

CONTROL

3B137

BED ROOM,

BARIATRIC

3B135

RESTROOM

3B160a

BED ROOM

3B160

BED ROOM

3B158

BED ROOM,

BARIATRIC

3B110

BED ROOM

3B105

RESTROOM

3B105a

RESTROOM

3B110a

NOURISHMENT

3B115

STORAGE

3B145

RESTROOM

3B158a

RESTROOM

3B135a

ANTE

ROOM

3B137b

ANTE

ROOM

3B138b

VESTIBULE

3B104

BED ROOM

3B108

RESTROOM

3B108a

ALCOVE,

WHEELCHAIR

3B165

ALCOVE

CRASH

CART

3B166

ANTE

ROOM

3B123b

ALCOVE

TRAY

STORAGE

3B141a

ALCOVE

WHEELCHAIR

3B112

CORRIDOR

C3-50

LVT-2

WSF-1

WSF-1

PT-1PT-1PT-1

WSF-1

WSF-1

CPT-1

WSF-1

PT-1

PT-1

PT-1

PT-1

PT-1

PT-1

WSF-1

WSF-1

WSF-1 WSF-1

WSF-1

PT-1PT-1

WSF-1 WSF-1

PT-1PT-1

WSF-1

WSF-1

LVT-2

LVT-2

WSF-1

CPT-1

CPT-1

LVT-3

PT-1

WSF-1

PT-1

LVT-2

WSF-1

CPT-1

LVT-2

SC-1

LVT-2

LVT-2

LVT-3

CPT-1

CPT-1

WSF-1

LVT-3

LVT-2

LVT-2

WSF-1

LVT-2

LVT-2

LVT-2

PT-1

WSF-1

LVT-2

PT-1

PT-1

LVT-2

LVT-2

CORRIDOR

C3-26

BED ROOM

3B159

RESTROOM

3B159a

PT-1

STORAGE

3B106

UTILITY

ROOM,

CLEAN

3B109

NURSE

WORKROOM

3B114

OFFICE

3B117

TOILET,

FEMALE

3B126

TOILET,

MALE

3B128

STORAGE

3B148

SOILED

UTILITY

3B152

MED ROOM

3B154

CONTROL

CENTER

C3-15

CORRIDOR

C3-22

CONTROL

CENTER

C3-25

NOURISHMENT

3B153

CORRIDOR

C3-27

BREAK

ROOM

3B146

STORAGE

3B168

HAC

3B155

CORRIDOR

C3-23

STORAGE

3B149

NURSE

WORKROOM

3B151

OFFICE

3B150

CLEAN

LINEN

3B139

CLEAN

LINEN

3B116

COMM

CLOSET

3B111

SOILED

UTILITY

3B107

UTILITY

ROOM,

CLEAN

3B130

ELECTRICAL

CLOSET

3B144MED ROOM

3B119

STORAGE

3B164

CORRIDOR

C3-17

OFFICE

3B147

CPT-1

ANTE

ROOM

3B124b

BED ROOM,

INFECTION

CONTROL

3B124

ALCOVE,

WHEELCHAIR

3B171

WSF-1

WSF-1

WSF-1

WSF-1

LVT-2

WSF-1

WSF-1

3' - 0"

ALCOVE

CRASH

CART

3B141

3' - 0"

CPT-1

SCRUBS

3B106a

WSF-1

WSF-1

LVT-2

LVT-2

PLAN AREA

CORRIDOR

C3-14

CORRIDOR

C3-19

CORRIDOR

C3-20

CORRIDOR

C3-26

UTILITY

ROOM,

SOILED

3B106

UTILITY

ROOM,

CLEAN

3B109

OFFICE

3B174

MED PREP

3B176

OFFICE,

PHYSICIAN

3B117

TOILET,

FEMALE

3B126

TOILET,

MALE

3B128

STORAGE

3B129A

TOILET

3B139

STORAGE,

GENERAL

3B147

HAC

3B148

OFFICE

3B149

NOURISHMENT

3B151

MED PREP

3B154

CONTROL

CENTER

C3-15

CORRIDOR

C3-17

CORRIDOR

C3-23

STORAGE,

STRETCHER/

WHEELCHAIR

3B107

COMM

CLOSET

3B111

OFFICE

3B174

NOURISHMENT

3B175

OFFICE,

PHYSICIAN

3B117

OFFICE

3B177

UTILITY

ROOM,

SOILED

3B178

UTILITY

ROOM,

CLEAN

3B130

ELECTRICAL

CLOSET

3B144

BREAK

ROOM

3B179

KITCHEN,

MISC

3B180

OFFICE

3B150

LINEN

ROOM,

SOILED

3B152

TOILET

3B181

UTILITY

ROOM,

CLEAN

3B155

UTILITY

ROOM,

SOILED

3B182

CORRIDOR

C3-22

LVT-3

CPT-1

SC-1

WSF-1

LVT-2

WSF-1

LVT-3

LVT-2

LVT-2

LVT-2

LVT-2

LVT-2

LVT-3

LVT-2

WSF-1

WSF-1

PT-1

LVT-2

PT-1

LVT-2

CPT-1

CPT-1

WSF-1 LVT-3

WSF-1

PT-1

LVT-2

CPT-1

PT-1

PT-1

WSF-1

CPT-1

CONTROL

CENTER

C3-25

CORRIDOR

C3-14

CORRIDOR

C3-19

CORRIDOR

C3-20

NOURISHMENT

3B115

CORRIDOR

C3-26

UTILITY

ROOM,

SOILED

3B106

STORAGE,

STRETCHER/

WHEELCHAIR

3B107

UTILITY

ROOM,

CLEAN

3B109COMM

CLOSET

3B111

OFFICE

3B174

KITCHEN,

NOURISHMENT

3B175

MEDICATION

PREP.

3B176

OFFICE,

PHYSICIAN

3B117

OFFICE

3B177

UTILITY

ROOM,

SOILED

3B178

TOILET,

FEMALE

3B126

TOILET,

MALE

3B128

STORAGE

3B129A

TOILET,

CONGREGATE

3B139

UTILITY

ROOM,

CLEAN

3B130

ELECTRICAL

CLOSET

3B144

BREAK

ROOM

3B179

KITCHEN,

MISC

3B180

STORAGE,

GENERAL

3B147

HOUSEKEEPING

AID CLOSET

3B148

OFFICE

3B149

OFFICE

3B150

NOURISHMENT

3B151

LINEN

ROOM,

SOILED

3B152

TOILET

3B181

MEDICATION

PREP.

3B154

UTILITY

ROOM,

CLEAN

3B155

UTILITY

ROOM,

SOILED

3B182

CONTROL

CENTER

C3-15

CORRIDOR

C3-17

CORRIDOR

C3-22

CORRIDOR

C3-23

CONTROL

CENTER

C3-25

LVT-3

LVT-3

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

FLOOR FINISH PLAN

AF101-F

MWTH

17005.00

552-18-102

Dayton Ohio

N Scale: 1/8" = 1'-0"1

FLOOR FINISH PLAN - BASE BID

N N.T.S.Scale:

KEY PLAN

GENERAL FINISH PLAN NOTES

A. See Sheet AF601-602 for Finish Materials Legend.

B. See Sheet AF601-602 for Room Finish Schedule.

C. See Interior Elevations on Sheet A401-A406 for further information.

D. All walls to be painted P-1, unless otherwise noted. See Finish Legend and Finish Schedule.

E. All metal door frames to be painted to match adjacent wall color, in Gloss Level 5, unless otherwise noted. See Finish Legend.

F. Provide appropriate flooring transition pieces at all unlike flooring material intersections. Color for all transition accessories to match

RB-1.

N Scale: 1/8" = 1'-0"2

FLOOR FINISH PLAN - DEDUCT ALTERNATE #1

N Scale: 1/8" = 1'-0"3

FLOOR FINISH PLAN - DEDUCT ALTERNATE #2

Revision s

CONFERENCE

ROOM

3B100

WAITING

ROOM

3B101

CONSULTATION

ROOM

3B102

OFFICE

3B103

LOCKER

ROOM

3B104A

TOILET,

MALE

3B104B

TOILET,

FEMALE

3B104C

LOCKER

ROOM

3B104D

OFFICE

3B120

BEDROOM -

RESIDENT

ON-CALL

3B161

OFFICE,

PHYSICIAN

3B162

BEDROOM -

RESIDENT

ON-CALL

3B163

BATH/SHOWER

ROOM

3B161A

CORRIDOR

C3-12

CORRIDOR

C3-14

CORRIDOR

C3-18

CORRIDOR

C3-19

CORRIDOR

C3-20

LOBBY

C3-30

CORRIDOR

C3-11

CORRIDOR

C3-28

STAIR

S-2-3

CORRIDOR

3C-27

CORRIDOR

3C-9

BED ROOM

3B121

RESTROOM

3B121a

RESTROOM

3B122a

BED ROOM

3B122

BED ROOM,

INFECTION

CONTROL

3B123

RESTROOM

3B123a

RESTROOM

3B124a

BED ROOM

3B125

RESTROOM

3B125a

BED ROOM

3B142

RESTROOM

3B142a

RESTROOM

3B140a

BED ROOM

3B140

BARIATRIC,

INFECTION

CONTROL

3B138

RESTROOM

3B138a

RESTROOM

3B137aBED ROOM, INFECTION

CONTROL

3B137

BED ROOM,

BARIATRIC

3B135

RESTROOM

3B160a

BED ROOM

3B160

BED ROOM

3B158

BED ROOM,

BARIATRIC

3B110

BED ROOM

3B105

RESTROOM

3B105a

RESTROOM

3B110a

NOURISHMENT

3B115

STORAGE

3B145

RESTROOM

3B158a

RESTROOM

3B135a

ANTE

ROOM

3B137b

ANTE

ROOM

3B138b

VESTIBULE

3B104

BED ROOM

3B108

RESTROOM

3B108a

ALCOVE,

WHEELCHAIR

3B165

ALCOVE

CRASH

CART

3B166

ANTE

ROOM

3B123b

ALCOVE

TRAY

STORAGE

3B141a

ALCOVE

WHEELCHAIR

3B112

CORRIDOR

C3-50

CG-1

CG-1

CG-2

CG-2

CG-2

CG-2

CG-2

CG-2 CG-2

CG-1

CG-1

CG-1

CG-2

CG-2

CG-2

CG-2

CG-2

CG-2CG-2

CG-2CG-2CG-2

CG-1

CG-1

CG-1

CG-2CG-2

CG-2

CG-2

CG-2

CG-2

CG-2

CG-1

CG-1

HR-2

HR-2

HR-2

HR-2

STORAGE

3B106

STORAGE

3B168

SOILED

UTILITY

3B107

UTILITY

ROOM,

CLEAN

3B109

COMM

CLOSET

3B111

NURSE

WORKROOM

3B114

BREAK

ROOM

3B146

CORRIDOR

C3-23

CORRIDOR

C3-27

CONTROL

CENTER

C3-15

CONTROL

CENTER

C3-25

SOILED

UTILITY

3B152

OFFICE

3B150

STORAGE

3B149

MED ROOM

3B119

TOILET,

MALE

3B128

NOURISHMENT

3B153

BED ROOM

3B159

RESTROOM

3B159a

CG-1

CG-1

EG-1

CG-1CG-1

ELECTRICAL

CLOSET

3B144

CORRIDOR

C3-26

CLEAN

LINEN

3B116

OFFICE

3B117

TOILET,

FEMALE

3B126

CLEAN

LINEN

3B139

UTILITY

ROOM,

CLEAN

3B130

OFFICE

3B147

STORAGE

3B148

NURSE

WORKROOM

3B151

MED ROOM

3B154

HAC

3B155

CORRIDOR

C3-17

CORRIDOR

C3-22

STORAGE

3B164

CG-1

CG-1

CG-3

CG-1

CG-1

CG-1

CG-3

HR-1

HR-1

HR-1HR-1HR-1HR-1

HR-1

HR-1

HR-1 HR-1 HR-1 HR-1

CG-1

CG-1

EG-1

CR-1

CR-1

EG-1

CR-1

CR-1CR-1CR-1CR-1

CR-1

CR-1

CR-1 CR-1 CR-1CR-1

CR-2

HR-2

CG-1

CR-2

CG-1

CR-2

CR-2

CR-2

CG-1

CG-1

CG-1

CG-1

CG-1

CG-1 CG-1 CG-1

CG-1

CG-1

CG-1

CG-1

CG-1

CG-1

CG-1

CG-1 CG-1

CG-1

CG-1

CG-1

CG-1

CG-1

CG-1CG-1

RWC-2

RWC-2

RWC-2

RWC-2

RWC-2

CG-2

RWC-2

RWC-1

RWC-1

RWC-1

RWC-2

RWC-1

RWC-2

ANTE

ROOM

3B124b

BED ROOM,

INFECTION

CONTROL

3B124

ALCOVE,

WHEELCHAIR

3B171

CG-1

EG-1EG-1

EG-1

EG-1

RWC-2

CG-1

CG-1

CG-3

ALCOVE

CRASH

CART

3B141

RWC-2

CR-2

HR-2

CG-3

SCRUBS

3B106a

RWC-2

RWC-2

RWC-2

RWC-2

RWC-2

RWC-2

CG-1 CG-1

CG-1

CG-1

CG-1

CG-1

CR-2

RWC-2

CG-1 HR-2

PLAN AREA

CORRIDOR

C3-14

CORRIDOR

C3-19

CORRIDOR

C3-20

CORRIDOR

C3-26

UTILITY

ROOM,

SOILED

3B106

STORAGE,

STRETCHER/

WHEELCHAIR

3B107

UTILITY

ROOM,

CLEAN

3B109COMM

CLOSET

3B111

OFFICE

3B174

KITCHEN,

NOURISHMENT

3B175

MEDICATION

PREP.

3B176

OFFICE,

PHYSICIAN

3B117

OFFICE

3B177

UTILITY

ROOM,

SOILED

3B178

TOILET,

FEMALE

3B126

TOILET,

MALE

3B128

STORAGE

3B129A

TOILET,

CONGREGATE

3B139

UTILITY

ROOM,

CLEAN

3B130

ELECTRICAL

CLOSET

3B144

BREAK

ROOM

3B179

KITCHEN,

MISC

3B180

STORAGE,

GENERAL

3B147

HOUSEKEEPING

AID CLOSET

3B148

OFFICE

3B149

OFFICE

3B150

NOURISHMENT

3B151

LINEN

ROOM,

SOILED

3B152

TOILET

3B181

MEDICATION

PREP.

3B154

UTILITY

ROOM,

CLEAN

3B155

UTILITY

ROOM,

SOILED

3B182

CONTROL

CENTER

C3-15

CORRIDOR

C3-17

CORRIDOR

C3-22

CORRIDOR

C3-23

CONTROL

CENTER

C3-25

CR-1

CR-1

CR-1 CR-1CR-1

RWC-1

RWC-1

RWC-1

HR-1

HR-1

HR-1HR-1HR-1

CR-1

HR-1

CR-1CR-1CR-1

CR-1

CR-1

HR-1HR-1 HR-1

CR-1

HR-1

CR-1

HR-1

HR-1

HR-1

RWC-1

RWC-1

CG-3

CG-1

CG-1

CG-1

CG-1

CG-1

CG-1

CG-3

CG-4

CG-2

CG-2

CG-2

CG-1

CG-1

CG-2

CG-3

CG-2 CG-2CG-2

CG-1

CG-1

CG-1

CG-1CG-1

EG-1CG-1

CORRIDOR

C3-14

CORRIDOR

C3-19

CORRIDOR

C3-20

CORRIDOR

C3-26

UTILITY

ROOM,

SOILED

3B106

STORAGE,

STRETCHER/

WHEELCHAIR

3B107

UTILITY

ROOM,

CLEAN

3B109

COMM

CLOSET

3B111

OFFICE

3B174

NOURISHMENT

3B175

MED PREP

3B176

OFFICE,

PHYSICIAN

3B117

OFFICE

3B177

UTILITY

ROOM,

SOILED

3B178

TOILET,

FEMALE

3B126

TOILET,

MALE

3B128

STORAGE

3B129A

TOILET

3B139

UTILITY

ROOM,

CLEAN

3B130

ELECTRICAL

CLOSET

3B144

BREAK

ROOM

3B179

KITCHEN,

MISC

3B180

STORAGE,

GENERAL

3B147

HAC

3B148

OFFICE

3B149

OFFICE

3B150

NOURISHMENT

3B151

LINEN

ROOM,

SOILED

3B152

TOILET

3B181

MED PREP

3B154

UTILITY

ROOM,

CLEAN

3B155

UTILITY

ROOM,

SOILED

3B182

CONTROL

CENTER

C3-15

CORRIDOR

C3-17

CORRIDOR

C3-22

CORRIDOR

C3-23

CONTROL

CENTER

C3-25

CR-1

CR-1

CR-1 CR-1CR-1

RWC-1

RWC-1

RWC-1

HR-1

HR-1

HR-1HR-1HR-1

CR-1

HR-1

CR-1CR-1CR-1

CR-1

CR-1

HR-1HR-1 HR-1

CR-1

HR-1

CR-1

HR-1

HR-1

HR-1

RWC-1

RWC-1

CG-1

CG-1

CG-1CG-1

CG-1

CG-1

CG-1

CG-1

CG-1

CG-1

CG-1

CG-2

CG-2

CG-2

CG-1

CG-1

CG-2

CG-1

CG-1

CG-1

CG-2

CG-1

CG-2

CG-2

EG-1

CG-2

CG-2

CG-2

CG-2

CG-1

CG-2

CG-2 CG-2CG-2

CG-1

CG-1

CG-1

CG-1CG-1

EG-1CG-1

RWC-2

RWC-2

RWC-2

RWC-2

RWC-2

RWC-2

RWC-2

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

WALL PROTECTION PLAN

AF101-P

MWTH

17005.00

552-18-102

Dayton Ohio

N Scale: 1/8" = 1'-0"1

WALL PROTECTION PLAN - BASE BID

N.T.S.Scale:

KEY PLAN

GENERAL FINISH PLAN NOTES

A. See Sheet AF601-602 for Finish Materials Legend.

B. See Sheet AF601-602 for Room Finish Schedule.

C. See Interior Elevations on Sheet A401-A406 for further information.

D. All walls to be painted P-1, unless otherwise noted. See Finish Legend and Finish Schedule.

E. All metal door frames to be painted to match adjacent wall color, in Gloss Level 5, unless otherwise noted. See Finish Legend.

F. Provide appropriate flooring transition pieces at all unlike flooring material intersections. Color for all transition accessories to match

RB-1.

N Scale: 1/8" = 1'-0"3

WALL PROTECTION PLAN - DEDUCT ALTERNATE #2

N Scale: 1/8" = 1'-0"2

WALL PROTECTION PLAN - DEDUCT ALTERNATE #1

Revision s

CONFERENCE

ROOM

3B100

WAITING

ROOM

3B101

CONSULTATION

ROOM

3B102

OFFICE

3B103

LOCKER

ROOM

3B104A

TOILET,

MALE

3B104B

TOILET,

FEMALE

3B104C

LOCKER

ROOM

3B104D

OFFICE

3B120

BEDROOM -

RESIDENT

ON-CALL

3B161

OFFICE,

PHYSICIAN

3B162

BEDROOM -

RESIDENT

ON-CALL

3B163

BATH/SHOWER

ROOM

3B161A

CORRIDOR

C3-12

CORRIDOR

C3-14

CORRIDOR

C3-18

CORRIDOR

C3-19

CORRIDOR

C3-20

LOBBY

C3-30

CORRIDOR

C3-11

CORRIDOR

C3-28

STAIR

S-2-3

CORRIDOR

3C-27

CORRIDOR

3C-9

BED ROOM

3B121

RESTROOM

3B121a

RESTROOM

3B122a

BED ROOM

3B122

BED ROOM,

INFECTION

CONTROL

3B123

RESTROOM

3B123a

RESTROOM

3B124a

BED ROOM

3B125

RESTROOM

3B125a

BED ROOM

3B142

RESTROOM

3B142a

RESTROOM

3B140aBED ROOM

3B140

BARIATRIC,

INFECTION

CONTROL

3B138

RESTROOM

3B138a

RESTROOM

3B137a

BED ROOM,

INFECTION

CONTROL

3B137

BED ROOM,

BARIATRIC

3B135

RESTROOM

3B160a

BED ROOM

3B160

BED ROOM

3B158

BED ROOM,

BARIATRIC

3B110

BED ROOM

3B105

RESTROOM

3B105a

RESTROOM

3B110a

NOURISHMENT

3B115

STORAGE

3B145

RESTROOM

3B158a

RESTROOM

3B135a

ANTE

ROOM

3B137b

ANTE

ROOM

3B138b

VESTIBULE

3B104

BED ROOM

3B108

RESTROOM

3B108a

ALCOVE,

WHEELCHAIR

3B165

ALCOVE

CRASH

CART

3B166

ANTE

ROOM

3B123b

ALCOVE

TRAY

STORAGE

3B141a

ALCOVE

WHEELCHAIR

3B112

CORRIDOR

C3-50

STORAGE

3B106

HAC

3B155

SOILED

UTILITY

3B107

UTILITY

ROOM,

CLEAN

3B109

OFFICE

3B147

COMM

CLOSET

3B111

CLEAN

LINEN

3B116

BREAK

ROOM

3B146

OFFICE

3B117

NURSE

WORKROOM

3B114

CORRIDOR

C3-23

STORAGE

3B148

MED ROOM

3B154

CONTROL

CENTER

C3-25

NURSE

WORKROOM

3B151

SOILED

UTILITY

3B152

CLEAN

LINEN

3B139

UTILITY

ROOM,

CLEAN

3B130

STORAGE

3B164

TOILET,

MALE

3B128

TOILET,

FEMALE

3B126

MED ROOM

3B119

ELECTRICAL

CLOSET

3B144

CORRIDOR

C3-17

STORAGE

3B149

CONTROL

CENTER

C3-15

BED ROOM

3B159

RESTROOM

3B159a

CORRIDOR

C3-26

NOURISHMENT

3B153

OFFICE

3B150CORRIDOR

C3-22

CORRIDOR

C3-27

STORAGE

3B168

FWP-1

FWP-1

FWP-1

FWP-1

FWP-1

FWP-1

FWP-1 FWP-1 FWP-1 FWP-1 FWP-1

FWP-1

FWP-1

FWP-1

FWP-1

FWP-1

P-5

P-5

P-5

P-5

P-2

P-2

P-2

P-2

P-2

P-2

P-2

P-3

P-2

P-2

P-2

P-3

P-3

P-3

P-2

ANTE

ROOM

3B124b

BED ROOM,

INFECTION

CONTROL

3B124

ALCOVE,

WHEELCHAIR

3B171

P-2

P-2

ALCOVE

CRASH

CART

3B141

P-2

SCRUBS

3B106a

P-2

P-2

PLAN AREA

CORRIDOR

C3-14

CORRIDOR

C3-19

CORRIDOR

C3-20

CORRIDOR

C3-26

UTILITY

ROOM,

SOILED

3B106

STORAGE,

STRETCHER/

WHEELCHAIR

3B107

UTILITY

ROOM,

CLEAN

3B109

COMM

CLOSET

3B111

OFFICE

3B174

KITCHEN,

NOURISHMENT

3B175

MEDICATION

PREP.

3B176

OFFICE,

PHYSICIAN

3B117

OFFICE

3B177

UTILITY

ROOM,

SOILED

3B178

TOILET,

FEMALE

3B126

TOILET,

MALE

3B128

STORAGE

3B129A

TOILET,

CONGREGATE

3B139

UTILITY

ROOM,

CLEAN

3B130

ELECTRICAL

CLOSET

3B144

BREAK

ROOM

3B179

KITCHEN,

MISC

3B180

STORAGE,

GENERAL

3B147

HOUSEKEEPING

AID CLOSET

3B148

OFFICE

3B149

OFFICE

3B150

NOURISHMENT

3B151

LINEN

ROOM,

SOILED

3B152

TOILET

3B181

MEDICATION

PREP.

3B154

UTILITY

ROOM,

CLEAN

3B155

UTILITY

ROOM,

SOILED

3B182

CONTROL

CENTER

C3-15

CORRIDOR

C3-17

CORRIDOR

C3-22

CORRIDOR

C3-23

CONTROL

CENTER

C3-25

P-5

P-5

P-5

P-5

P-2

P-2

P-2

P-2

P-2

P-2

P-2

P-2

CORRIDOR

C3-14

CORRIDOR

C3-19

CORRIDOR

C3-20

CORRIDOR

C3-26

UTILITY

ROOM,

SOILED

3B106

STORAGE,

STRETCHER/

WHEELCHAIR

3B107

UTILITY

ROOM,

CLEAN

3B109

COMM

CLOSET

3B111

OFFICE

3B174

NOURISHMENT

3B175

MED PREP

3B176

OFFICE,

PHYSICIAN

3B117

OFFICE

3B177

UTILITY

ROOM,

SOILED

3B178

TOILET,

FEMALE

3B126

TOILET,

MALE

3B128

STORAGE

3B129A

TOILET

3B139

UTILITY

ROOM,

CLEAN

3B130

ELECTRICAL

CLOSET

3B144

BREAK

ROOM

3B179

KITCHEN,

MISC

3B180

STORAGE,

GENERAL

3B147

HAC

3B148

OFFICE

3B149

OFFICE

3B150

NOURISHMENT

3B151

LINEN

ROOM,

SOILED

3B152

TOILET

3B181

MED PREP

3B154

UTILITY

ROOM,

CLEAN

3B155

UTILITY

ROOM,

SOILED

3B182

CONTROL

CENTER

C3-15

CORRIDOR

C3-17

CORRIDOR

C3-22

CORRIDOR

C3-23

CONTROL

CENTER

C3-25

P-5

P-5

P-5

P-5

P-2

P-2

P-2

P-2

P-2

P-3

P-3

P-3

P-3

P-3

P-3

P-3

P-2

P-2

P-2 P-2

P-2

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

WALL FINISH PLAN

AF101-W

MWTH

17005.00

552-18-102

Dayton Ohio

N Scale: 1/8" = 1'-0"1

WALL FINISH PLAN - BASE BID

N.T.S.Scale:

KEY PLAN

GENERAL FINISH PLAN NOTES

A. See Sheet AF601-602 for Finish Materials Legend.

B. See Sheet AF601-602 for Room Finish Schedule.

C. See Interior Elevations on Sheet A401-A406 for further information.

D. All walls to be painted P-1, unless otherwise noted. See Finish Legend and Finish Schedule.

E. All metal door frames to be painted to match adjacent wall color, in Gloss Level 5, unless otherwise noted. See Finish Legend.

F. Provide appropriate flooring transition pieces at all unlike flooring material intersections. Color for all transition accessories to match

RB-1.

N Scale: 1/8" = 1'-0"3

WALL FINISH PLAN - DEDUCT ALTERNATE #2

N Scale: 1/8" = 1'-0"2

WALL FINISH PLAN - DEDUCT ALTERNATE #1

Revision s

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

FINISH SCHEDULE

AF601

MWTH

17005.00

552-18-102

Dayton Ohio

FINISH LEGEND

CODE FINISH TYPE MANUFACTURER PRODUCT / COLOR COMMENTS

CASEWORK FINISHES

PL-1 PLASTIC LAMINATE (TYPICAL CABINETRY) FORMICA 8826-58 NEUTRAL TWILL

PL-2 PLASTIC LAMINATE (TOILET ROOM) FORMICA 8826-58 NEUTRAL TWILL

SS-1 SOLID SURFACE (CONTROL STATION) DUPONT CORIAN DUNE PRIMA

SS-2 SOLID SURFACE (TYPICAL CABINETRY) DUPONT CORIAN HAZELNUT

SS-3 SOLID SURFACE (TOILET) FORMICA LUNA SAND, 757

CEILING FINISHES

ACT-1 ACOUSTIC CEILING TILE 2x2 (OFFICE, WORK) ARMSTRONG "OPTIMA HEALTH ZONE" 3114, 24x24 GRID: "PRELUDE XL" 15/16" EXPOSED TEE

ACT-2 ACOUSTIC CEILING TILE 4x4 (VECTOR EDGE) ARMSTRONG "OPTIMA VECTOR" 3909, 48x48 GRID: "PRELUDE" 15/16" CONCEALED

ACT-3 ACOUSTIC CEILING TILE 2X2 (CLEAN LAY IN) ARMSTRONG "CLEAN ROOM VL" 868, 24x24 GRID: "CLEAN ROOM" 15/16" CO-EXTRUDED

P-6 PAINT SHERWIN WILLIAMS SW 7004 SNOWBOUND GLOSS LEVEL 1

FLOOR FINISHES

CPT-1 CARPET TILE (OFFICE, CONSULT) MILLIKEN "WHALE SONG BELUGA" BEL 108-204 BRINY, 50CMx50CM

LVT-2 LUXURY VINYL TILE (CORRIDOR, UTILITY, STORAGE) MANNINGTON "CITY BLOCK" ANT200 CORE, 18x18

LVT-3 LUXURY VINYL TILE (CONTROL, BREAK, MED, KITCHEN) MANNINGTON "HERITAGE CHERRY" 12105 NATURAL, 3x36

PT-1 PORCELAIN TILE ATLAS CONCORDE "FRAY" SAND 30CMx60CM

SC-1 SEALED CONCRETE - -

WSF-1 WELDED SHEET FLOORING MANNINGTON "REALITIES II BOARDWALK" 5667R COCONUT

MISCELLANEOUS FINISHES

CG-1 CORNER GUARD CS ACROVYN #929 OYSTER GRAY TO CEILING

CG-2 CORNER GUARD, ANGLED CS ACROVYN #929 OYSTER GRAY TO CEILING

CG-3 CORNER GUARD CS ACROVYN #373 AMBER CHERRY TO 2'-9" A.F.F. UNLESS NOTED OTHERWISE

CR-1 CRASH RAIL CS ACROVYN #373 AMBER CHERRY

CR-2 CRASH RAIL CS ACROVYN #929 OYSTER GRAY

EG-1 END GUARD CS ACROVYN #929 OYSTER GRAY TO CEILING

GR-1 GROUT MAPEI 39 IVORY

HR-1 HAND RAIL CS ACROVYN #373 AMBER CHERRY

HR-2 HAND RAIL CS ACROVYN #929 OYSTER GRAY

WALL FINISHES

AR-1 ACRYLIC RESIN SHEET 3FORM VARIA ECORESIN, MIRAGE TWILIGHT STRAIGHT FRONT FINISH: SANDSTONE

FWP-1 FLEXIBLE WALL PROTECTION DL COUCH "P3TEC" UPLIFT, BONE WHITE P3T-60112

P-1 PAINT (FIELD) SHERWIN WILLIAMS SW 6098 PACER WHITE

P-2 PAINT (DARK NEUTRAL) SHERWIN WILLIAMS SW 7038 TONY TAUPE

P-3 PAINT (LIGHT ACCENT) SHERWIN WILLIAMS SW 7603 POOLHOUSE

P-5 PAINT (DARK ACCENT) SHERWIN WILLIAMS SW 7604 SMOKY BLUE

P-7 HIGH BUILD EPOXY (TOILET ROOM) SHERWIN WILLIAMS SW 6098 PACER WHITE

P-8 PAINT (PATIENT ROOM) SHERWIN WILLIAMS SW 6106 KILIM BEIGE

P-9 PAINT (MATCH EXISTING) SHERWIN WILLIAMS MATCH EXISTING

PT-2 PORCELAIN TILE ATLAS CONCORDE "FRAY" SAND, 30CMx60CM

PT-3 PORCELAIN TILE - ACCENT ATLAS CONCORDE "FRAY" TATAMI WARM, 1" x 6" SHEET MOUNTED MOSAIC

PT-4 PORCELAIN TILE - BULLNOSE ATLAS CONCORDE "FRAY" SAND, 7.2CMx60CM

RB-1 RUBBER BASE JOHNSONITE COVE BASE, 80 FAWN CB

RB-2 RUBBER BASE (WOOD PROFILE) JOHNSONITE MILLWORK REVEAL BASE, ACH AMBER CHERRY

RB-3 RUBBER BASE (MATCH EXISTING) JOHNSONITE MATCH EXISTING

RWC-1 RIGID WALL COVERING CS ACROVYN #373 AMBER CHERRY TO 2'-9" A.F.F. UNLESS NOTED OTHERWISE

RWC-2 RIGID WALL COVERING CS ACROVYN #929 OYSTER GRAY TO 4'-0" A.F.F. UNLESS NOTED OTHERWISE

GENERAL FINISH PLAN NOTES

A. See Sheet AF601-602 for Finish Materials Legend.

B. See Sheet AF601-602 for Room Finish Schedule.

C. See Interior Elevations on Sheet A401-A406 for further information.

D. All walls to be painted P-1, unless otherwise noted. See Finish Legend and Finish Schedule.

E. All metal door frames to be painted to match adjacent wall color, in Gloss Level 5, unless otherwise noted. See Finish Legend.

F. Provide appropriate flooring transition pieces at all unlike flooring material intersections. Color for all transition accessories to match

RB-1.

ROOM FINISH SCHEDULE

ROOM # ROOM NAME FLOOR BASE

WALLS CASEWORK

CEILINGNORTH SOUTH EAST WEST CABINET COUNTERTOP

3B102 CONSULTATION ROOM CPT-1 RB-1 P-1 P-1 P-1 P-3 - - ACT-1

3B103 OFFICE CPT-1 RB-1 P-1 P-1 P-1,2 P-1 - - ACT-1

3B104 VESTIBULE LVT-2 RB-1 P-1 P-1 P-1 P-1 - - ACT-1

3B105 BED ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B105a RESTROOM PT-1 - P-7/PT-2,3,4 P-7/PT-2,4 PT-3 P-7/PT-2,4 PL-2 SS-3 P-6

3B106 STORAGE LVT-2 RB-1 P-1 P-1 P-1 P-1 - - ACT-1

3B106a SCRUBS WSF-1 WSF-1 P-1 P-1 P-1 P-1 - - ACT-3

3B107 SOILED UTILITY WSF-1 WSF-1 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 - - ACT-3

3B108 BED ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B108a RESTROOM PT-1 - P-7/PT-2,3,4 P-7/PT-2,4 PT-3 P-7/PT-2,4 PL-2 SS-3 P-6

3B109 UTILITY ROOM, CLEAN WSF-1 WSF-1 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 - - ACT-3

3B110 BED ROOM, BARIATRIC WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B110a RESTROOM PT-1 - P-7/PT-2,3,4 P-7/PT-2,4 P-7/PT-2,4 PT-3 PL-2 SS-3 P-6

3B111 COMM CLOSET - - P-1 P-1 P-1 P-1 - - -

3B112 ALCOVE WHEELCHAIR LVT-2 RB-1 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 - - ACT-1

3B114 NURSE WORKROOM CPT-1 RB-1 P-1 P-1 P-1,3 P-1 - SS-3 ACT-1

3B115 NOURISHMENT LVT-2 RB-1 P-1 P-1 P-1 P-1 PL-1 SS-3 ACT-1

3B116 CLEAN LINEN WSF-1 WSF-1 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 - - ACT-3

3B117 OFFICE CPT-1 RB-1 P-1 P-1 P-2 P-1 - - ACT-1

3B119 MED ROOM LVT-2 RB-1 P-1 P-1 P-1 P-1 PL-1 SS-3 ACT-1

3B120 OFFICE CPT-1 RB-1 P-1 P-1 P-2 P-1 - - ACT-1

3B121 BED ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B121a RESTROOM PT-1 - PT-3 P-7/PT-2,4 P-7/PT-2,3,4 P-7/PT-2,4 PL-2 SS-3 P-6

3B122 BED ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B122a RESTROOM PT-1 - P-7/PT-2,4 PT-3 P-7/PT-2,3,4 P-7/PT-2,4 PL-2 SS-3 P-6

3B123 BED ROOM, INFECTION CONTROL WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-3

3B123a RESTROOM PT-1 - PT-3 P-7/PT-2,4 P-7/PT-2,3,4 P-7/PT-2,4 PL-2 SS-3 P-6

3B123b ANTE ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 - - ACT-1

3B124 BED ROOM, INFECTION CONTROL WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-3

3B124a RESTROOM PT-1 - P-7/PT-2,4 PT-3 P-7/PT-2,3,4 P-7/PT-2,4 PL-2 SS-3 P-6

3B124b ANTE ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 - - ACT-1

3B125 BED ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B125a RESTROOM PT-1 - PT-3 P-7/PT-2,4 P-7/PT-2,4 P-7/PT-2,4 PL-2 SS-3 P-6

3B126 TOILET, FEMALE PT-1 - PT-3 P-7/PT-2,4 P-7/PT-2,4 P-7/PT-2,4 PL-2 SS-3 ACT-1

3B128 TOILET, MALE PT-1 - P-7/PT-2,4 PT-3 P-7/PT-2,4 P-7/PT-2,4 - - ACT-1

3B130 UTILITY ROOM, CLEAN WSF-1 WSF-1 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 - - ACT-3

3B135 BED ROOM, BARIATRIC WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B135a RESTROOM PT-1 - P-7/PT-2,4 P-7/PT-2,3,4 P-7/PT-2,4 PT-3 PL-2 SS-3 P-6

3B137 BED ROOM, INFECTION CONTROL WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-3

3B137a RESTROOM PT-1 - P-7/PT-2,4 P-7/PT-2,3,4 PT-3 P-7/PT-2,4 PL-2 SS-3 P-6

3B137b ANTE ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 - - ACT-1

3B138 BARIATRIC, INFECTION CONTROL WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-3

3B138a RESTROOM PT-1 - P-7/PT-2,4 P-7/PT-2,3,4 P-7/PT-2,4 PT-3 PL-2 SS-3 P-6

3B138b ANTE ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 - - ACT-1

3B139 CLEAN LINEN WSF-1 WSF-1 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 - - ACT-3

3B140 BED ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B140a RESTROOM PT-1 - P-7/PT-2,4 P-7/PT-2,3,4 PT-3 P-7/PT-2,4 PL-2 SS-3 P-6

3B141 ALCOVE CRASH CART LVT-2 RB-1 P-1/RWC-2 - P-1/RWC-2 P-1/RWC-2 - - ACT-1

3B141a ALCOVE TRAY STORAGE LVT-2 RB-1 P-1/RWC-2 - P-1/RWC-2 P-1/RWC-2 - - ACT-1

3B142 BED ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B142a RESTROOM PT-1 - P-7/PT-2,4 P-7/PT-2,3,4 P-7/PT-2,4 PT-3 PL-2 SS-3 P-6

3B144 ELECTRICAL CLOSET - - P-1 P-1 P-1 P-1 - - -

3B145 STORAGE LVT-2 RB-1 P-1 P-1 P-1 P-1 - - ACT-1

3B146 BREAK ROOM LVT-3 RB-1 P-1 P-3 P-1,3 P-1,3 PL-1 SS-3 ACT-1

3B147 OFFICE CPT-1 RB-1 P-2 P-1 P-1 P-1 - - ACT-1

3B148 STORAGE LVT-2 RB-1 P-1 P-1 P-1 P-1 - - ACT-1

3B149 STORAGE LVT-2 RB-1 P-1 P-1 P-1 P-1 - - ACT-1

3B150 OFFICE CPT-1 RB-1 P-1 P-1 P-2 P-1 - - ACT-1

3B151 NURSE WORKROOM CPT-1 RB-1 P-1 P-1 P-1 P-3 - SS-3 ACT-1

3B152 SOILED UTILITY WSF-1 WSF-1 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 - - ACT-3

3B153 NOURISHMENT LVT-2 RB-1 P-1 P-1 P-1 P-1 PL-1 SS-3 ACT-1

3B154 MED ROOM LVT-2 RB-1 P-1 P-1 P-1 P-1 PL-1 SS-3 ACT-1

3B155 HAC PT-1 - PT-2 PT-2 PT-2 PT-2 - - ACT-3

3B158 BED ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B158a RESTROOM PT-1 - P-7/PT-2,4 PT-3 P-7/PT-2,4 P-7/PT-2,3,4 PL-2 SS-3 P-6

3B159 BED ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B159a RESTROOM PT-1 - PT-3 P-7/PT-2,4 P-7/PT-2,4 P-7/PT-2,3,4 PL-2 SS-3 P-6

3B160 BED ROOM WSF-1 WSF-1 P-8 P-8 P-8 P-8 PL-1 SS-3 ACT-1

3B160a RESTROOM PT-1 - P-7/PT-2,4 PT-3 P-7/PT-2,4 P-7/PT-2,3,4 PL-2 SS-3 P-6

3B161 BEDROOM - RESIDENT ON-CALL WSF-1 WSF-1 P-1 P-1 P-1 P-1 - - -

3B164 STORAGE LVT-2 RB-1 P-1 P-1 P-1 P-1 - - ACT-1

3B165 ALCOVE, WHEELCHAIR LVT-2 RB-1 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 - - ACT-1

3B166 ALCOVE CRASH CART LVT-2 RB-1 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 - - - ACT-1

3B168 STORAGE LVT-2 RB-1 P-1 P-1 P-1 P-1 - - ACT-1

3B171 ALCOVE, WHEELCHAIR LVT-2 RB-1 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 P-1/RWC-2 - - ACT-1

3C-27 CORRIDOR LVT-2 RB-1 P-1 P-2/RWC-2 P-1 P-1 - - ACT-1

C3-12 CORRIDOR LVT-2 RB-1 P-1 P-1 P-1 P-2/RWC-2 - - ACT-1

C3-14 CORRIDOR LVT-2,3 RB-1,2 P-2,5/RWC-1 P-1/FWP-1 P-1/FWP-1 P-1,5/FWP-1 PL-1 SS-1,2 ACT-1,2/P-1,5

C3-15 CONTROL CENTER LVT-3 RB-1 P-2,5 P-2,5 P-2,5 P-2,5 PL-1 SS-1 ACT-1/P-5,6

C3-17 CORRIDOR LVT-2,3 RB-1,2 P-2/RWC-1 P-2 P-2 P-2,5 - - ACT-1/P-5

C3-18 CORRIDOR LVT-2 RB-1 FWP-1 P-1/FWP-1 P-2/RWC-2 P-1/FWP-1 PL-1 SS-1,2 ACT-1/P-1

C3-19 CORRIDOR LVT-2,3 RB-1,2 P-1,5/FWP-1 P-5/FWP-1 P-2,5/RWC-1,2 P-1/FWP-1 PL-1 SS-1,2 ACT-1,2/P-1,5

C3-20 CORRIDOR LVT-2,3 RB-1,2 P-1/FWP-1 P-2,5/RWC-1,2 P-1,5/FWP-1/RWC-1 P-1/FWP-1 PL-1 SS-1,2 ACT-1,2/P-1,5

C3-22 CORRIDOR LVT-2 RB-1 P-1 P-1 P-1 P-1 - - ACT-1

C3-23 CORRIDOR LVT-2 RB-1 P-1 P-1 P-1 P-1 - - ACT-1

C3-25 CONTROL CENTER LVT-3 RB-1 P-2,5 P-2,5 P-2,5 P-2,5 PL-1 SS-1 ACT-1/P-5,6

C3-26 CORRIDOR LVT-2,3 RB-1,2 P-2,5/FWP-1 P-1/FWP-1 P-1/FWP-1 P-2,5/RWC-1,2 PL-1 SS-1,2 ACT-1,2/P-1,5

C3-27 CORRIDOR LVT-2,3 RB-1,2 P-2 P-2/RWC-1 P-2,5 P-2 - - ACT-1/P-5

Revision s

JOHN

A.

POE

IO

HO

FOET

A T

S

R E G

IS

E T

R

ED RA

C H

TI

E C T

Drawing Title

Location

Building Number

Project Title

Checked DrawnDate

Project No.

Drawing Number o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o t th re e in c h e s o n e fo o t

F E

D C

B A

1 2 3 4 5 6 7 8 9

1 2 3 4 5 6 7 8 9

F E

D C

B A

VA Project No.

FULLY SPRINKLERED

ARCHITECT/ENGINEERS:CONSULTANTS:

Office of Construction and Facilities Management

JPA Project No.

Dwg. of

Renovate TCU-ICU Space Bldg. 330

03/09/2020

FINISH SCHEDULE -…