This amendment report outlines revisions to bid documents for a project to renovate the spinal cord injury rehabilitation area in Building 7 at a VA medical center in Memphis, Tennessee. The revisions include changes to drawings, specifications, and the addition of new specifications. Drawings were revised to update asbestos notes, floor plans, keynotes, and finish schedules. Specifications were revised to incorporate abatement of asbestos-containing brown duct sealant, add specifications for resilient rubber sheet flooring, epoxy resinous flooring, signage, and metal storage shelving.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24920B0003 0007.docx | DOCX document | |
| 36C24920B0003 0006.docx | DOCX document | |
| 36C24920B0003 0005.docx | DOCX document | |
| 36C24920B0003 0004.docx | DOCX document | |
| Amendent_SPECS.pdf | ||
| Amendment_DRAWINGS.pdf | ||
| 36C24920B0003 0003.docx | DOCX document | |
| RFI Form - Renovate Bldg. 7 SCI Rehab Area.docx | DOCX document | |
| Contractor EMR Certification Form 2020.docx | DOCX document | |
| 36C24920B0003 0002.docx | DOCX document | |
| 36C24920B0003 0001.docx | DOCX document | |
| Drawings 614-19-102.pdf | ||
| Electric-Telecom Drawings.pdf | ||
| 36C24920B0003_1.docx | DOCX document | |
| Addendum G-101.pdf | ||
| Architectural Drawings 2.pdf | ||
| Wage Determination - Shelby County.pdf | ||
| Specifications.pdf | ||
| Architectural Drawings 1.pdf | ||
| Mechanical Drawings.pdf | ||
| Fire-Plumbing Drawings.pdf | ||
| General Drawings.pdf |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT REPORT
Amendment Number: 0001
Project Title: Renovate Bldg 7 Spinal Cord Rehab Area
Project Location: Memphis, TN
Date of Amendment: 5 February 2021
The reason for Amendment 0001 to the Renovate Bldg 7 Spinal Cord Rehab Area is to make revisions to the Bid Documents. The revisions regard various items and are outlined below.
A. Revisions to Drawings
1) A-001
a. Revised General Asbestos Containing Material Note #1 to include suspect
Brown Duct Joint Sealant.
2) A-101
a. Floor plan revised at space 2C110 Equip. Storage to indicate metal storage shelving layout and quantity of shelving units.
b. Keynote 11 revised.
3) A-171
a. Keynote 5 revised.
4) A-371
a. Note 25 deleted.
5) A-631
a. Finish Schedule revised to change VS-1 to RES-1 for spaces 2C110, 2C114A, 2C-119, and 2C121.
b. Finish Schedule revised to change the base from RB-1 to RES-1 for spaces 2C110, 2C114A, 2C-119, and 2C121.
c. Finish Legend revised to change RES-1 Epoxy Flooring Manufacturer name to Torginal.
d. Finish Floor Plan revised to change the floor finish at space 2C111A from VS-1 to RF-1.
6) MD101
a. Added general note #3 referring to Specification 02 82 13.19 for Asbestos
Abatement and brown duct joint sealant presence.
B. Revised Table of Contents
1) Added 01 33 23 attachment, Submittal Register.
2) Section 09 67 23.20 RESINOUS (EPOXY BASE) WITH VINYL CHIP BROADCAST
(RES-1) added for Resinous Flooring.
3) Section 10 11 23 TACKBOARDS deleted.
4) Section 10 14 00 SIGNAGE added for Signage.
5) Section 10 56 13 METAL STORAGE SHELVING added for Metal Shelving.
C. Revisions to Specifications
1) 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
a. 1.3.C, added “See Submittal Register attachment following this specification.”
2) 02 82 13.19 ASBESTOS FLOOR TILE AND MASTIC ABATEMENT
a. Edited paragraph 1.1.2 to add ACM brown duct sealant/mastic, quantity, and note.
b. Edited paragraph 3.2.9 Wall Barriers to instruct for areas with floor removal.
c. Added paragraph 3.2.10 Floor Barriers to instruct in case of no floor removal.
d. Edited paragraph 3.3.3 heading to say REMOVAL OF FLOORING MASTIC.
e. Added paragraph 3.3.4, “Removal of Duct Sealant/Mastic on Duct Joints.”
3) 09 65 16 RESILIENT SHEET FLOORING
a. Revised paragraph 1.1.A to include 2.Resilient recycled rubber sheet flooring.
b. Added paragraph 2.4 RECYCLED RUBBER SHEET FLOORING.
4) Added specification Section 09 67 23.20 RESINOUS (EPOXY BASE) WITH VINYL
CHIP BROADCAST (RES-1).
5) Added specification Section 10 14 00 SIGNAGE.
6) Added specification Section 10 56 13 METAL STORAGE SHELVING.
7) 23 05 11 COMMON WORK RESULTS FOR HVAC – Revised sections 1.2 and 3.6 to include reference to Specification 02 82 13.19 for Asbestos Abatement.