RFI 1 Exhibit A QA RFIs Response.xlsx
XLSX spreadsheet 31 KB Posted
- Solicitation number
- 36C24825R0118
About this file
This Request for Information (RFI) document contains a detailed comment matrix for a VA construction project to install fall protection in parking garages at the Malcolm Randall VA Medical Center in Gainesville, Florida. The project, valued between $1,000,000 and $5,000,000, requires installing ballistic quality screen mesh and physical barriers over open areas of three parking garages above the first level, with a 371-calendar day performance period. The solicitation is set-aside exclusively for SBA certified, Veteran Owned Small Businesses (VOSB), with critical dates including a site walk on 06/24/2025, RFIs due by 06/30/2025, and proposals due by 07/24/2025. Key points from the RFI responses include clarifications on project scope, such as removing the P2 parking garage from the bid documents, confirming no commissioning services are required, establishing a low-risk infection control assessment, and specifying work hour restrictions (after 4:30 PM on business days and weekends).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 323140_High Security Fences and Gates.pdf | ||
| DWGs_Final_2015-02-03.pdf | ||
| SAM DBA WD FL20250194 03_14_2025.pdf | ||
| AS-BUILT LSPLAN P1 FREEDOM.pdf | ||
| 36C24825R0118 0001.pdf | ||
| SIGN IN SHEET 573-16-603 INSTALL PARKING GARAGE FALL PROTECTION 24 JUN 25.pdf | ||
| Bid Summary - REV 1.docx | DOCX document | |
| DWG_AS-BUILT_2012-05-01.pdf | ||
| 2025-07-15 Addendum No. 1.pdf | ||
| 010000 - General Requirements.pdf | ||
| Exhibit E Performance Relevancy Survey v2.docx | DOCX document | |
| AS-BUILT LSPLAN P3 LIBERTY.pdf | ||
| Exhibit C EMR.docx | DOCX document | |
| Exhibit A QA RFIs.xlsx | XLSX spreadsheet | |
| Exhibit F Past and Present Performance Questionnaire.docx | DOCX document | |
| SAM DBA 05_02_25.pdf | ||
| Exhibit B LOS Certification Solicitation Version.doc | DOC document | |
| Exhibit D Contract Progress Schedule.pdf | ||
| Exhibit I Price Matrix.xlsx | XLSX spreadsheet | |
| 36C24825R0118_1 Solicitation.pdf | ||
| 7A Bid Doc Combined Specifications.pdf | ||
| 7B 573-16-603 COMBINED DRAWINGS Install Parking Garage Fall Prote.pdf |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIRECTIONS
TAILORED COMMENT MATRIX
THIS DOCUMENT MUST BE RETURNED IN A MICROSOFT EXCEL FILE FORMAT. DO NOT RETURN YOUR RESPONSES IN ANY DIFFERENT FILE FORMAT.
| Directions & Explanation of TAILORED COMMENT MATRIX |
| This Tailored Comment Matrix is provided in order for potential offerors to provide feedback, comments, and ask questions with regard to the released RFP. |
The sheet labeled "DIRECTIONS" explains this document, and provides directions for its use.
The sheet labeled "MATRIX" contains a table with all labeled and numbered elements from the RFP. This table is where potential offerors may respond to the Government with feedback, comments, or ask questions.
| Directions and explanation of sheet labeled "MATRIX" |
| The MATRIX sheet can be reached by clicking the "MATRIX" Tab at the bottom of this spreadsheet. Add rows as necessary under the applicable item. |
| MATRIX COLUMN DESCRIPTIONS: | |
| Column A: | Contains the Item reference number for this item. This number is used for organizational purposes, when referring to this document only. |
Column B: Contains the section number that each element is labeled, within their respective documents. The section number relates directly to the item's location in the RFP.
Column C: Contains the written title for the corresponding item/section number.
| Column D: | Contains a drop down box for selecting the type of comment. Available options are "Critical" "Substantive" or "Administrative". |
| Critical: Violations of law -or- Unnecessary risks to safety, life & limb, or VA Material; waste or abuse of VHA appropriations; unreasonable burden on resources. | |
| Substantive: Appears or is potentially unnecessary, incorrect, misleading, confusing, or inconsistent with other sections; disagree with proposed responsibilities, requirements, and/or procedures. | |
| Administrative: Address typographical, grammatical, and formatting errors (grammar, punctuation, style, etc.) |
Column E: Contains recieved date of offerors' comments/questions/responses.
Column F: Contains space for potential offerors' comments/questions/responses.
Column G: Contains space for VHA comments/questions/responses.
Column H: Contains response date for VHA comments/questions/responses.
Column I: Contains VHA Section/ POC shop comments/questions/response
Column J: Contains Contractor Name requesting /questions/responses.
THIS DOCUMENT MUST BE RETURNED IN A MICROSOFT EXCEL FILE FORMAT. DO NOT RETURN YOUR RESPONSES IN ANY DIFFERENT FILE FORMAT.
MATRIX
| ITEM # | SECTION or ATTACHMENT # | DOCUMENT NAME | COMMENT TYPE | |
| (Select from drop down) | Received Date | QUESTIONS / COMMENTS | ||
| (With justification of why considered source selection sensitive if applicable) | VA Response | Response Date | VA |
Response
| From | Company Name | |||||||||
| 1 | 1 | SOW | Administrative | 7/27/21 | Example | Example Response | 8/15/21 | Safety | TBD Contracting | |
| 2 | 1 | SPEC | Substantive | 06/30/25 | Specification 01 00 00 – 1, Item 1.3a provides requirements for offerors to submit pricing for three (3) deductive bid alternates; however, the RFP Price Schedule, RFP Page 6, does not list or make any reference to any bid alternates. Please clarify requirements of the Price Schedule with regards to any requirements for offerors to furnish pricing for any Bid Alternates. | It's our understanding all associated work for P2 parking garage (Independence) is to be removed from the scope of this contract as it is part of another veritical expansion project. VA direction required. VA RESPONSE: P2 will be removed from the bid documents. The AE will update the bid summary in the specifications and drawings. Please refer to the AE Addendum Letter. | 7/10/25 | AE | CPS, Inc. | |
| 3 | 2 | RFP | Administrative | 07/01/25 | RFP Page 8, Item 3, states magnitude of project is “Between $5,000,000 and $10,000,000”, however, the RFPSF 1442 Section 10 states that the magnitude is “$1,000,000 and $5,000,000”. Please clarify the magnitude of this project. | Error in statement RFPSF 1442 Section 10 the magnitude is “$1,000,000 and $5,000,000” See updated General proposal sheet. |
UPDATED: I. GENERAL PROPOSAL INFORMATION
| 3. | MAGNITUDE OF THIS PROJECT: Between $1,000,000 and $5,000,000 in accordance with (IAW) VAAR 836.204(f)(2). | |||||||||
| 7/10/25 | CO | CPS, Inc. | ||||||||
| 4 | 3 | RFP | Substantive | 07/02/25 | RFP Page 16, Item 3.5 requires offeror to “Describe the commissioning process –“. The scope of work does appear to include work elements that would normally be subjected to commissioning” . Please clarify whether commissioning is required or not. If required, please clarify the elements of work subject to commissioning. | VA RESPONSE: The project does not require comissioning services. | 7/10/25 | COR | CPS, Inc. | |
| 5 | 4 | RFP | Substantive | 07/03/25 | RFP Page 16, Item 3.2, requires offeror to describe infection control procedures to be implemented by offeror. If required, Please clarify the PICRA Risk Level for this project if infection control procedures are required and please clarify the elements of work subject to the implementation of infection control procedures. | VA PICRA risk level assessment worksheet to be provided by the VA to determine class of protection required for this project. Refer to specification section 01 35 26, Safety Requirement, for additional information. VA RESPONSE: IT WILL BE A LOW RISK, ICRA IS NOT REQUIRED. | 7/10/25 | AE/COR | CPS, Inc. | |
| 6 | 5 | RFP | Administrative | 07/04/25 | RFP Page 18, Items 5.9.3 and 5.9.4 require one project over $10M and 3 over $7M; however, the SF 1442 Section 10 that the magnitude is “$1,000,000 and $5,000,000”. The magnitude of the required relevant projects exceeds the project range stipulated on the RFP SF 1442. Please clarify requirements. | |||||
| - If the range is correct at $1M to #5M, please consider having one project exceed $4M and 3 projects above $1M. | Error in statement Contractor is required to provide one project over $4M and 3 over $2M; the SF 1442 Section 10 that the magnitude is “$1,000,000 and $5,000,000”. | |||||||||
| UPDATED: III. EVALUATION FACTORS FOR AWARD AND PRICE EVALUATION 5. | RELEVANT PAST PERFORMANCE/ EXPERIENCE | |||||||||
| 5.9.3. | At least one (1) of the projects submitted must be valued at greater than $4M and performed within the last 5 years. |
| 5.9.4. | Total Project Value and duration (at least 3 shall be greater than $2M). | 7/10/25 | CO | CPS, Inc. | ||||||
| 7 | 6 | RFP | Substantive | 07/05/25 | RFP Page 21, Item IIA, line 2 requires offeror to install “ballistic quality screen mesh”. Please provide the ballistic resistance standard and performance specifications. | The screen mesh system performance provided in the contract documents calls for impact resistance. Refer to specificaton section 32 31 40, paragraph 1.1 and 2.1 for additional information. VA respsone required if performance requirements are to be increased to ballistic resistance. VA RESPONSE: The screen mesh does not need to meet any ballistic resistance standards. | 7/10/25 | AE | CPS, Inc. | |
| 8 | 7 | RFP | Substantive | 07/06/25 | Page 21, Item II C 2, line 1 states screen must be “similar” to design used on bed tower 5th floor. The term “similar” could be interpreted in many ways. If the Government has an “equal” product or fabrication method please provide specific requirements to the maximum extent practical in order to reduce ambiguity and risk in the proposal pricing process. | VA to provide basis of design or "equal" for the product or fabrication provided in on bed tower 5th floor. VA RESPONSE: The Contractor must provide the screen mesh per the construction specifications 32 31 40. The reference for the bed tower on the 5th floor will be omitted. Specification 3203100 Revised and included in Addendum. For the installation, the contractor must be responsible for temporarily relocating any signage affixed to the walls or interfering with the opening to be infilled. | 7/10/25 | AE | CPS, Inc. | |
| 9 | 8 | RFP | Administrative | 07/07/25 | RFP Page 21, Item IV II C 4 appears to stipulate that the project must have 3 individual persons filling 3 separate positions on a full time basis. Please clarify or confirm the requirements with regards whether in fact the Government requires 3 full time individuals filling 3 positions with no overlapping of duties or job/sharing, i.e. no triple hatting or double hatting allowed | VA RESPONSE: Due to level coordination for Gainesville VAMC projects this project WILL require at least a dedicated QC/Project manager, jobsite superintendent and safety officer who are not the same individual. | 7/10/25 | COR | CPS, Inc. | |
| 10 | 9 | RFP | Substantive | 07/08/25 | RFP Page 21, Item IV II C 5 stipulates work hours as “normal work hours”. Given the traffic and parking demands that exist in the 3 parking garages during normal work hours, please confirm that it is the Government’s intent to have all work performed during normal work hours. |
- If normal work hours are to be used, please clarify:
- Who is responsible for traffic control inside the garages each day?
- Will entire garage floors, one or more floor, be closed for the contractor to perform work each day? If so, how many floors and for how long can floors be closed.
- Will contractor be allowed to move materials into and out of the garage during normal work hours?
- Will contractor be allowed to store materials inside the garage on closed floors, i.e current and next work day materials stored to maintain production The installation will take place after normal working hours, specifically after 4:30 PM on business days and throughout the weekends. Work at the stairwells is permitted during regular working hours. The contractor is responsible for providing appropriate signage and traffic control. The garage will remain open during this period. The general contractor will be responsible for traffic control during construction. Alls work must be in strick coordination with the VA COR.
The contractor must develop a phasing plan to install the sections on each floor and sides, in coordination with the COR. Additionally, the contractor must provide a 6-foot temporary construction barrier fence to block off the section being worked on at any given time. The phasing plan must be in accordance to the scheule requiremns per spec 01 32 16.15 Project Schedules.
| The contractor is permitted to store materials on the garage floor they are currently working on, but only one floor at a time. They may use any available corner that does not interfere with traffic flow and does not occupy more than three parking stalls. The storage area must be fenced and secured at all times. All storage areas must be approved by the COR. | 7/10/25 | COR | CPS, Inc. | |||||||
| 11 | 10 | RFP | Substantive | 07/09/25 | RFP Page 23, Item N, does the Government have a preferred phasing sequence for the work, i.e. is work limited to one garage at a time, can multiple floors be under construction simultaneously, how many days can each floor be impacted by construction, what is the sequence of garages to be under construction? | Refer to General Project Note "H" located on drawings G002. VA response required to allow multiple floors at one time. VA RESPONSE: Refer to Item No. 10. | 7/10/25 | AE/COR | CPS, Inc. | |
| 12 | 11 | RFP | Substantive | 07/10/25 | RFP, Page 23 and 24, Item P, is every individual who performs work on site for this project be required to obtain a VA issue PIV? If so, has the VA discontinued issuing the PIV ! badges and now require full background investigations for every PIV issued? | |||||
| - If required, what is the VA PIV processing time from application submission to issuance of the PIV by the VA | PIV is not required for everyone. (ADD SPECIFIC CONTRACTORS AND SUBS MUST BE EASYLY IDENTIFIABLE WITH COMPANY LOGO ETC…) | 7/10/25 | CO/COR | CPS, Inc. | ||||||
| 13 | 12 | RFP | Substantive | 07/11/25 | RFP, Specification 01 00 00 -6, Please provide a copy of the current life safety plan for each garage. | Attached | 7/10/25 | COR | CPS, Inc. | |
| 14 | 13 | Drawings | Substantive | 07/12/25 | Please provide digital copies of as-built documents for each garage, in particular showing structural rebar that may impacted during contractor’s installation of required fabricated metal components. | VA Response: Life safety drawings for P1 and P3 are attached for reference. The contractor is responsible for updating any changes to the life safety drawings based on the construction phasing plan developed by the contractor. | 7/10/25 | COR | CPS, Inc. | |
| 15 | 14 | SOW | Substantive | 07/13/25 | During the Site Visit it was stated that a contract has been awarded for the addition of 2 new parking levels at the Independence Garage. Please provide the performance period for the construction of the 2 floors at Independence. | |||||
| - Also, please clarify phasing of work under this RFP in consideration of the work by other contractors at Independence. | VA Response: Refer to Item No. 2 above | 7/10/25 | COR | CPS, Inc. |
| 1 |
| 2 |