Revised SOW.pdf
PDF 366 KB Posted
- Attached to
- Z1DA--Project: 619-23-101 - Replace Roof Systems for Main Hospital, Building 1 Federal contract opportunity
- Solicitation number
- 36C24725R0030
About this file
This Statement of Work outlines requirements for replacing roof systems on Building #1 at the Central Alabama Veterans Health Care System in Montgomery, AL. The project (619-23-101) involves replacing slate and TPO roof systems that are beyond their useful life and have caused water intrusion issues affecting patient and staff health.
The scope includes replacing roof systems, fall protection, lightning protection, dormers, antenna systems, and drainage systems. The contractor must repair/replace damaged drain covers, vent covers, and interior walls affected by water damage. Several rooftop HVAC units require removal and replacement, with commissioning needed for the new HVAC system. The work must be completed within 365 days of contract award while maintaining continuous building occupancy without service interruptions. The contractor is responsible for providing all management, engineering, supervision, labor, equipment and supplies needed. The Veterans Affairs staff will not exercise supervision over contractor employees, who remain accountable solely to their employer.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Title of Project: 619-23-101 - REPLACE ROOF ON BUILDING #1
Objective. This project will replace the roof systems of Building #1. The roof system for the building is beyond its' useful life. Over the years, water intrusion has caused health issues with patients and staff. Water intrusion has caused damage to the interior and exterior walls. The project will replace slate and thermoplastic polyolefin (TPO) roof systems, fall protection, lightning protection, dormers, antenna systems, and the drainage system.
General. The Veterans Affairs employee shall not exercise any supervision or control over the Contractor’s employees performing the tasks herein. Such contract employees shall be accountable solely to the Contractor who, in turn shall be responsible to the Veterans Affairs. This project will repair roof shingles, gutters, drains and apply asphalt mastic on wall flashing and cracks to stop and prevent water intrusion. Interior walls will need to be repaired if damages because of water intrusion during construction. The buildings are located at the 215 Perry Hill Road, Montgomery, AL 36109, Central Alabama Veterans Health Care System, West Campus.
Existing Conditions. The roof systems have multiple leaks that are causing secondary issues due to the water intrusion. If the repairs are not made there will be mold issues and further damages to existing structures.
Scope of Work. The Contractor shall furnish all management, engineering, supervision, labor, assemblies, transportation, equipment, and supplies needed to complete the following:
Building #1 - This project will replace the roof systems of Building #1. The roof system for the building is beyond its' useful life. Over the years, water intrusion has caused health issues with patients and staff. Water intrusion has caused damage to the interior and exterior walls. Interior walls will need to be repaired. The project will replace roof systems, fall protection, lightning protection, and the seal the drainage system. In addition, any damaged or missing drain covers, or vent covers shall be replaced. All dormers will be repaired, recovered, and painted. Several roof top HVAC equipment will need to be removed and replaced with new equipment.
Commissioning/Test and Balance. Commissioning for the HVAC system will be needed.
Phasing. The schedule work for this project will be planned to permit continual occupancy of the building without cancelling services. There is no required sequence for repairing the buildings.
Period of Performance. The required period of performance will be 365 days from the date of contract award or notice to proceed.
Location. Main Hospital Building #1 at Central Alabama Veterans Health Care System, 215 Perry Hill Road, Montgomery, AL, 36109.