Final CSD Questions 9.10.26 - Combined Rev 05.pdf
PDF 649 KB Posted
- Attached to
- Z2NZ-- 658-23-108 Correct Stormwater Drainage
- Solicitation number
- 36C24626B0031
About this file
This is a Technical Questions and Responses Tracking Sheet for federal contract solicitation #36C24626B0031 (Revision 05) for "Correct Storm Water Drainage – Salem VAMC," a Service-Disabled Veteran-Owned Small Business (SDVOSB) set-aside project. The document contains 182 contractor questions and corresponding VA responses addressing project scope, specifications, and contract requirements.
The project involves correcting stormwater drainage systems at the Salem Veterans Affairs Medical Center over a 450-calendar-day period. Key scope elements include removal of approximately 1,900 linear feet of asbestos cement pipe, replacement of deficient pipe sections identified through CCTV inspection, installation of new stormwater infrastructure including pipes and structures, removal of damaged catch basins and inlets, utility tie-ins and relocations, and site restoration. The project is structured in six concurrent phases with a 500-linear-foot open trench limit. Critical requirements include: three separate dedicated personnel (Superintendent, CQC System Manager, and SSHO); contractor-retained materials testing laboratory; commercial photography documentation; badging for all personnel; tuberculosis screening; traffic control per VDOT standards; and erosion control measures including filter socks on both sides of trenches. The contractor must perform geotechnical investigations, provide field verification of existing utilities and inverts, manage differing site conditions per FAR 52.236-2, and coordinate closely with the VA's Contracting Officer on schedule adjustments, phasing approvals, and utility conflicts. Asbestos removal is classified as Class II work with 30-day pre-abatement notice required; the VA provides third-party monitoring as deemed necessary. An Administrative Notice to Proceed (NTP) for preconstruction activities is anticipated, with cost extensions available for VA-caused delays including design clarifications and regulatory reviews.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TECHNICAL QUESTIONS AND SOLICITATION #: 36C24626B0031 Rev. 05
RESPONSES TRACKING SHEET PROJECT TITLE: Correct Storm Water Drainage– Salem VAMC
CONTRACTOR QUESTION VA RESPONSE
1. Confirm how the set aside works. Does the Prime Contractor have to be a SDVOSB or can a company that is not a SDVOSB bid on this project but then need to subcontract at least 25% of the work to a SDVOSB? If a contract is set aside for SDVOSB (Service‑Disabled Veteran‑Owned Small Business), then only a certified SDVOSB may act as the prime contractor.
Non‑SDVOSB firms are not eligible to bid as prime on a SDVOSB set‑aside. A certified SDVOSB prime must also comply with the
“limitations on subcontracting” clause (FAR 52.219‑14 and 13 CFR 125.6).
Please see amendment 4. Posted on 9.22.26.
2. Work involving asbestos cement and other hazardous materials shall include the guidance of a professional licensed by the department of professional and occupational regulation (DPOR). Asbestos demolition work plan and notification shall be submitted to and in accordance with the department of labor and industries requirements for review. Hazardous Material Waste disposal work shall be in accordance with the VDEQ and EPA regulations. What is the linear footage of asbestos pipe to be demolished? What is the asbestos pipe dame.
Approximately 1,900 LF of asbestos pipe. The locations of existing asbestos pipe can be seen under CD series sheets, any pipe section labeled “AC” means the pipe material is asbestos cement.
3. Please confirm this is not a sales tax-exempt project. If sales tax-exempt, will the government provide the prime contractor with a tax-exempt certificate for use by subcontractors and vendors?
No exemption based on Far 29.302.
4. Currently the bids are due Monday, September 28th. Will the VA please consider rescheduling to any other day during the week. A Monday bid due date means the bid must be finalized by end of day the Friday before, and many subcontractors don’t work on Fridays. The bid due date will be
Monday September 28th as stated on the solicitation.
The VA has updated the bid due date to October 20, 2026, as stated in the solicitation amendment 3.
5. In the event of contract modifications/change orders, should performance and payment bond premiums be applied to each individual change order proposal or wait until the end of the project where a final modification is issued for the overruns? We ask this because VA Acquisition Regulation (VAAR) clause 852.228-70, titled "Bond Premium Adjustment” states “in determining the basis for final settlement.”
VAAR 852.228 70 states that bond premium adjustments are made at final settlement, not with each individual change order.
Because of this, bond premium costs should not be added to every modification as it occurs. Instead, any premium adjustments are calculated once at the end of the project when the final modification is issued
6. If a Prime Contractor is awarded multiple projects at the same VA Medical Center location: Can the Superintendent be shared across multiple projects at the same site/location, or should they only be dedicated full-time to this project only?
No. Superintendent must be dedicated for each project.
7. Can one person serve as the Superintendent, Quality Control Manager, & the SSHO?
Contractor must provide three separate dedicated individuals for Superintendent, CQC System Manager and SSHO.
Reference spec section 01 35 26 1.9.C for SSHO requirements.
Revise spec section 01 45 00 3.4.B as follows:
CQC System Manager: Identify as CQC System Manager an individual within the onsite work organization that is responsible for overall management of CQC and has the authority to act in all CQC matters for the Contractor. The CQC system Manager is required to be a PM or SRE to determine qualifications based on project complexity at construction review 3 years in related work. This CQC System manager is on the site at all times during construction and is employed by the General Contractor. The CQC System Manger must be a separate qualified individual from the Prime Contractor’s Superintendent and/or SSHO with duties only as the CQC System Manager. The requirements for the alternate are the same as the CQC System Manager.
8. Can the QCM serve as the SSHO? If the Super or SSHO can’t be the QCM and the QCM is required to be onsite full-time, should they be assigned to this project only, or can they be assigned to another project as well on the same property?
See responses to questions 6 and 7.
9. If the Super or SSHO can’t be the QCM, can a subcontractor (e.g., Terracon or a similar testing firm) fulfill the QCM role?
See response to question 7.
10. Can the Superintendent fulfill the Site Safety & Health Officer (SSHO) role? Specification 01 35 26, 1.9 D in its reference to FAR 52.236-6, can be interpreted to mean that the SSHO can also be the Superintendent.
Please confirm that the Superintendent can fulfill the Site Safety & Health Officer (SSHO) role.
Reference specification section 01 35 26 paragraph 1.9.C.
11. If the Super or QCM can’t be the SSHO, the average ADDITIONAL cost for a dedicated SSHO is approximately $36,000 per month (salary, labor burden, per diem, housing, company vehicle, monthly return trips home, company phone, etc). We expect this project to be 12 months long, and the bid is expected to increase by $432,000 Please confirm a dedicated SSHO is still required.
See response to question 10.
12. If the Super can’t be the SSHO, is the SSHO required to be on-site full-time, or can they visit the site daily for safety inspections?
Reference specification section 01 35 26 1.9.A.
13. If the Super can’t be the SSHO, is the SSHO required to be on-site full-time, or can they be a home office employee (e.g., Safety Director) on the prime contractor's staff?
See response to question 12.
14. If the Super can’t be the SSHO and the SSHO is required to be onsite full-time, should they be assigned to this project only, or can they be assigned to another project as well on the same property?
Reference specification section 01 35 26 1.9.A.
15. If the Super can’t be the SSHO, can a subcontractor fulfill the SSHO role or does the SSHO need to be directly employed by the General Contractor?
Reference specification section 01 35 26 1.9.A.
16. Is badging required for the project? If required, which scope of work and workers will it be required for? If required, how long is the turnaround time for background check results?
Yes, badging is required for all contractors on this project.
Contractor to coordinate with COR to obtain badges. Time frame for background check results can vary based on the individual. VA will provide temporary badges to be worn by contractor personal until permanent badges are issued.
17. Will background checks and fingerprinting be required for any scope of work related to this project?
If required, which scope of work and workers will it be required for?
If required, how long is the turnaround time for background check results?
See response to question 16.
18. The period of performance (POP) for this project is stated as 450 days.
We estimate that preconstruction activities (submittals, procurement, mobilization, etc.) will require a minimum of 120 days prior to the start of construction. If the VA plans to issue NTP before preconstruction begins, we request that the POP be extended by 90 days to account for these preconstruction activities.
VA anticipates issuing Administrative NTP for preconstruction activities.
19. Once awarded, will the VA provide an Administrative NTP to allow time for subcontracts to be executed, GC & Subs to work together to develop a project schedule, provide SF1413s, and prepare other Division 1 submittals?
VA anticipates issuing Administrative NTP for preconstruction activities.
20. Once awarded, if the VA will not provide an Administrative NTP, will the VA allow up to 90 days between the kickoff meeting and the NTP?
VA anticipates issuing Administrative NTP for preconstruction activities.
21. Is any scope of work for this project required to be performed outside of regular work hours?
If so, what trades or scopes will be required to be performed outside of regular work hours?
If so, what will the work hours and days be for scopes required to be performed outside of regular work hours?
Ref. 01 00 00 Paragraph 1.6 Section G. states, “The Medical Center must maintain its operation 24 hours a day 7 days a week.” As well as it is the contractor’s responsibility to develop a work plan and schedule to minimize impact on the normal operation of the facility.
If it becomes apparent project is falling behind schedule and phasing or contract completion dates will not be met, then it is the contractor’s responsibility to increase manpower or increase working hours per shift, shifts per working day, working days per week…etc. Ref. 01 32 16.5 Paragraph 1.10
22. Are water connections available near the construction area? Reference specification section 01 00 00 paragraph 1.18.
23. Will the VA allow contractors to use water from VA sources? Reference specification section 01 00 00 paragraph 1.18.
24. Are contractors required to set a temporary pole and meter electric usage?
Reference specification section 01 00 00 paragraph 1.18.
25. Where is the location of the temporary pole and meter? Reference Figure 1 at end of document.
26. Where is the electrical connection for power to the temporary pole and meter?
Reference Figure 1 at end of document.
27. What is the distance between the electrical connection and the temporary pole and meter?
Reference Figure 1 at end of document.
28. Is a 208V, 125A breaker available for connection to the temporary pole and meter?
Reference Figure 2 at end of document.
29. If a breaker isn't available, is a spare available? Reference specification section 01 00 00 paragraph 1.18.
30. Would contractors be expected to supply the needed breaker? Reference specification section 01 00 00 paragraph 1.18.
31. Will the feeder between the electrical point of connection and the pole and meter need to be underground?
Yes.
32. Will this feeder need to run across any asphalt or concrete roads or parking lots?
Contractor is responsible for determining routing of temp utilities.
33. Are contractors required to set a temporary pole and meter electric usage?
Reference specification section 01 00 00 paragraph 1.18.
34. Where can the mobile office be located? Mobile offices must be located in the contractor laydown area located behind parking lot T.
35. Is space available for a 8’ x 40’ temporary ground-level office? Yes.
36. Are contractors required to set a pole and meter for electric usage in the mobile office?
Reference specification section 01 00 00 paragraph 1.18.
37. Where is the electrical connection for power to the mobile office? Reference Figure 1 at end of document.
38. What is the distance between the electrical connection and the proposed location of the mobile office?
Reference Figure 1 at end of document.
39. Will the VA provide space for the Prime Contractor’s Superintendent to set up, or should we add costs to our bid for a mobile office?
VA will not provide space for superintendent, contractor is responsible for providing field office as needed.
40. Will the VA provide space for a 30-yard dumpster? Dumpsters must be in contractor laydown area.
41. Where shall contractor dumpsters be located? Dumpsters must be in contractor laydown area.
42. Can the VA accommodate dumpsters near the job site? Dumpsters must be in contractor laydown area.
43. Can Porta Johns be placed within a 100’ radius of the job site / work area? Reference specification section 01 00 00 1.17.
44. Is temporary construction fencing required anywhere on the project or at the laydown area?
Reference specification section 01 00 00 1.6.H
45. If required, please confirm that 6’ tall temporary construction fencing is acceptable. We ask this because the standard VA specification is a minimum of 2.1m (seven feet) tall, which is not an industry standard height and would require a custom fence to be made at that height. Alternatively, an 8’ high fence generally tends to blow over even with sandbags on the bases when the fabric is required to be fastened to the fence, since 8’ tall panels with fabric have to potential to cause damage to property and injury to personal, we strongly recommend using 6’ tall temporary construction fencing.
Six foot tall temporary construction fencing is acceptable.
46. Can utility tie-ins be performed during regular hours? 01 00 00 Paragraph 1.6 Section G states, “The Medical Center must maintain its operation 24 hours a day 7 days a week.” As well as it is the contractor’s responsibility to develop a work plan and schedule to minimize impact on the normal operation of the facility.
47. Will the VA allow for stored material so that we can procure and lay down long lead items and/or critical path material/equipment?
Ref. 01 00 00 1.6
48. Will the VA fully pay for this material/equipment if stored onsite? No.
49. Please confirm that the current design documents meet current VA TIL guidelines.
Confirmed.
50. Must project phases be completed consecutively (one phase fully complete before the next begins), or will the VA allow multiple phases to proceed concurrently?
It is the contractor’s responsibility to develop a work plan and schedule to minimize impact to the normal operation of the facility. Ref. 01 00 00 Paragraph 1.6 Section G.
51. Who is responsible for hiring and paying for the materials testing laboratory—the VA or the Contractor?
Contractor.
52. CU101-CU109, General Note 9: Please provide available information identifying the type, size, material, elevation, and anticipated limits of relocation for utilities that conflict with the proposed stormwater work.
Please confirm that utility conflicts which cannot be identified or quantified during bidding based on the presently available information will be treated as additional work and are not required to be included in the Base Bid.
Any keynotes proposing the installation of other utilities that are not stormwater such as water, electrical, sewer show the anticipated location of where these non-stormwater utilities will need to be relocated to not conflict with the stormwater work.
For pricing, it is our suggestion to assume any water stubs directly connected to hydrants to be a 6” size, for any mains along roadways that are not building laterals or hydrant stubs, assume an 8” size for water pipes. However, it is the Contractor’s responsibility to perform field investigations to confirm these sizes at the beginning of the project by either suggested means of test pits within grass areas or by counting the number or turns connected water valves take to close and determine the approximate size of the existing pipe section.
Test pits in grass areas can be performed for electrical utilities.
Pipe sizes are already known for sewer.
Cost for unknown unforeseen activities shall be handled under FAR Part 52.236-2 "Differing Site Conditions Clause"
53. Please provide the anticipated quantities and limits of asbestos-cement piping requiring removal, disturbance, or abatement under this contract, and confirm the basis bidders should use for pricing asbestos quantities.
The work anticipates the removal of approximately 1,900 LF of asbestos pipe. The locations of existing asbestos pipe can be seen under CD series sheets, any pipe section labeled “AC” means the pipe material is asbestos cement.
54. We missed the site visit on 3rd September; we are interested in bidding the job. Please let us know was it mandatory site visit?
Site visit was not mandatory.
55. We need a soil boring report to find out the existing water table, some of the MH to be replaced are deeper than 10 ft.
The contractor is to perform their own geotechnical report/investigation and provide buoyancy calculations for stormwater structures. As part of geotechnical report, add boring exploration at the locations shown in the Attached PDF, Item 55 - Suggested Soil Boring Location to Bidders
56. Is there a contaminated soil disposal included in the SOW. Please share a report if it is available.
Directions for disposal of contaminated soils are described under Specification 31 20 11, Section 3.6.C.
57. Sec 02 82 13.31 -1.2 -Variance in quantities-Contractor shall provide unit price for newly discovered ACM- we did not find any quantities listed in the specifications under extent of work and a place for unit price in the RFP.
02 82 13.31 1.1 B. 2. states to refer to project drawings for approximate quantities of ACM.
58. Sec 31 20 11-1.5 -The unit of measurement for excavation and borrow will be in cubic yard, allowance will be made on the same basis for selected backfill. We did not find anywhere in the RFP asking for a unit price for excavation and selected backfill.
Please reference the updated specification in Addendum A.
59. Rock excavation will be paid under an allowance. Without the soil investigation report, it is not possible to estimate the rock excavation.
No rock excavation is anticipated. Any rock excavation will be handled under FAR 52.236-2 Differing Site Conditions.
60. CU -109 - Note #9 - If the existing utility does conflict with the new proposed storm system, The contractor shall replace section of the interfering utility. This should be included under the allowance since the actual cost will be based on the site conditions during execution.
Per Survey and Utility Notes under C-001, the existing utility information is based on the survey performed in 2022 and given to us. Where information is missing, engineering assumptions were made based on available information. Cost for unknown/unforeseen activities shall be handled under FAR Part 52.236-2 "Differing Site Conditions Clause"
61. CU 106- Keynote # 24 & 25- F&I new electrical service and match in kind.
We did not find any details in the plans and specifications for electrical work.
Refer to Survey and Utility Notes on sheet C-001. Existing utility information is limited; therefore, we cannot provide specifications and details for unknown items. The Contractor should perform field investigations to confirm and match in kind.
62. CU106- Keynote #26 - F&I new DI water service- we need the size of the existing water main to replace in kind.
The existing conditions survey and record drawings provided do not identify the size of the existing water services to be replaced. For pricing, it is our suggestion to assume any water stubs directly connected to hydrants to be a 6” size, for any mains along roadways that are not building laterals or hydrant stubs, assume an 8” size. However, it is the Contractor’s responsibility to perform field investigations to confirm these sizes at the beginning of the project by either suggested means of test pits within grass areas or by counting the number or turns connected water valves take to close and determine the approximate size of the existing pipe section.
63. Note # 10- SOW is not clear on the plans, the extent of pipe replacement is not marked, whereas #11 is clearly marked in dark lines wherever it is to be replaced.
Assuming this is referring to keynote 10 in the CU series sheets. The note is used throughout the design to replace deficient pipe sections that were identified during a CCTV inspection. The Contractor can assume 1 stick/section nominal PVC (SDR 26 or 35, depending on the depth) pipe length will be replaced.
64. CU -106- Keynote #1 & #10 - are we replace coupling and PVC piping under existing building #14?
A hole was found in the pipe section at this location based on CCTV results. Yes, this section of pipe shall be replaced and coupled per the drawing plans.
65. CD 101-Keynote #1 -Rem & dispose selective damaged pipe section between DMH -15 and outfall 1A/1B -please confirm the pipe length to be rem and replaced.
For sections involving keynote 1 from DMH-15 to outfall 1A/1B, the Contractor can assume 6 sections of 32” RCP nominal size (assumed to be 8 ft long each) to be removed and replaced with new PVC pipe (SDR 26). Refer to Specification 33 40 00, Section 2.2.E for information on when to use SDR 26 VS SDR 35 for similar scenarios.
66. CU-101 - Keynote #1 & 10 sow not clear between DMH -17 & outfall 1A/1B - are we replacing the existing 32" RCP with new PVC as per keynote #10?
Yes, see response above for item 65. This includes coupling per detail F5 on sheet CK501.
67. CU -102 -Keynote #1&10 parking lot C -sow work is not marked. Please confirm the length and size of the PVC pipe to be replaced.
Based on the existing conditions survey, the existing pipe size is 15 inch, therefore it would be replaced with 15” PVC. The Contractor can assume 1 stick of 15” pipe of nominal length (20ft) to be replaced.
68. Please confirm whether all the pipe to be replaced are shown in dark shade in the drainage plans .( CU -101 to Cu-109).
No, dark shade pipes and locations where keynotes are present represent any proposed work.
69. Keynote # 15 - Jet out and vacuum debris to replace blockage as shown on CU drawings -please confirm the pipe lengths included in the sow. Is it only between the drainage structures within the arrow.
Yes, only pipe section between upstream and downstream structures
70. Drainage plans (CU 101 to CU 108) Keynote #1-F&I coupling of joint connection . See note 2 . See sheet CK501, det F5- This detail is for new and old pipe joint connection , whereas the note #1 as shown on CU plans do not show any pipe replacement at these locations? ( CU 107 -at bldg 10).
At locations as such where new pipe replacement and joints are called out, it is done to repair pipe deficiencies such as cracks and holes identified during CCTV inspection. The Contractor can assume 1 stick of nominal PVC pipe length to be replaced with associated coupling of joint.
71. CU-107 at Bldg #4- The keynote #1, 10 & 15, we are supposed to install new PVC piping under #10 whereas #15 calls for jet out and vacuum debris to remove blockage? Please confirm the sow.
See response to item 70 above.
72. CD -101- note #2- other than asbestos cement pipe removal and disposal , are we responsible for any hazardous material disposal? Please share the quantity and sow .
Hazardous material disposal for this project only anticipates removal of asbestos cement pipe which is approximately 1,900 LF. However, the Contractor is responsible for the removal of any hazardous material encountered that is incidental to the limit of work and dispose of the materials in accordance with local, municipal and federal laws.
73. Can we backfill with the excavated material for pipe replacement? Refer to detail E6 on sheet CK 502 for drain pipe trench detail.
For final backfill, the contractor may use excavated material as long as is complies with the requirements under Specification 31 20 11, do not use unsuitable materials as defined in Specification 31 20 11.
74. Stormwater profiles are not provided for several pipe runs. Can profiles please be provided for all pipe runs to be installed? A list of profiles not provided is included below for reference.
a. FES-8 to CB-13 to CB-14
b. CB-7 (Tee) to DMH-B1
c. DMH-132 to CB-115
d. CB-116 to DMH-58
e. CB-117 to DMH-137
f. DMH-E to DMH-49 to DMH-46
g. TD-1A to CB-109
h. Exist to DMH-163 to DMH-47A
i. DMH-57 to DMH-56 to DMH-54 to CB-12
j. CI-3 to CI-2
k. CB-119 to DMH-133 to DMH-104 to DMH-103
l. DMH-134 to CB-123 to CB-124 to CB-125
m. FES-3 to CB-129
n. CB-128 to CB-132 to CB-133
o. CB-130 to CB-131
p. CB-135 to CB-136
q. CB-134 to CB-137
r. FES-6 to CB-138 to CB-139 to CB-140 to CB-141
s. CB-17 to DMH-142
t. CB-159 to DMH-28
u. CB-156 to CB-155 to DMH-158
v. CB-154 to CB-41
Profiles are provided for stormwater main runs and not for minor runs or stubs of the system. Profiles were provided at main stormwater sections that are part of the hydraulic critical path modeling, utility conflict management, and project cost efficiency.
w. CB-40 to DMH-31
x. EX to DMH-125 to CB-150 to CI-19
y. CB-149 to CI-18
z. CI-17 to CI-16 to DMH-109
aa. DMH-169 to CI-11 TO DMH-171
bb. CB-86 to DMH-145
cc. CB-143 to DMH-133
dd. CB-144 to DMH-140
ee. CB-36 to CB-35 to DMH-141
ff. DMH-100E to CB-94
gg. CB-161 to CB-160
hh. CB-SF1 to CB-168
75. Throughout the plans, sections of existing pipes are called out to be replaced with PVC pipe (10). Can you please confirm the length, diameter, and material of the sections to be replaced? The pipe runs in question are listed below for easy reference.
a. Sheet CU101 – Outfall 1A/1B to DMH-17. Existing labeled 32” RCP.
b. Sheet CU102 – CB-50C to DMH-85. Existing labeled as
15” AC.
c. Sheet CU106 – Adjacent to BLDG. 143. Existing line is not pictured.
d. Sheet CU106 – DMH-29 to Ex. Structure. Existing labeled as 10” VCP.
e. Sheet CU107 – DMH-94 to Ex. Structure. Existing labeled at 18” CI.
f. Sheet CU107 – DMH-95B to SIS-2B. Existing labeled as
12” Conc.
g. Sheet CU108 – DMH-33 to DMH-33A. Existing labeled as 20” RCP
a. For this section, the Contractor can assume 4 sections of 32” RCP nominal length (assumed to be 8 ft long each) to be removed and replaced with new PVC pipe (SDR 26) from DMH-17 to outfall 1A/1B. The existing conditions survey says the pipe size is 32”, however this is not a nominal inner diameter size; therefore, the Contractor should confirm existing pipe size and replace it with new PVC pipe of the same size.
b. 1 stick section of nominal length 15”AC pipe (assumed to be 10 ft long) should be replaced with 15” SDR 35 PVC pipe.
c. The section from DMH-11 to DMH-10 will be replaced with new 15” HDPE dual wall corrugated pipe for a length of 131 LF.
An addendum showing this information will be provided.
d. Once section of nominal length of the existing 10” VCP would be replaced with 10” SDR 35 PVC
e. For section between DMH-94 to DMH-95, two nominal length sections of the existing 18” CI pipe would be replaced with 18” SDR 26 PVC pipe.
f. 1 nominal pipe length section of 12” SDR 26 PVC pipe
g. Replace existing section of 20” RCP nominal length (assumed to be 8 ft) with new 21” SDR 26 PVC
76. On Sheet CU102 Call Out 14 specifies, “Remove intruding root in pipe.” Can you please provide guidance the desired repairs to the existing 12” VCP beyond root removal?
Yes, the Contractor shall remove tree root and existing damaged pipe section and replace the damaged section with PVC pipe of the same size. We will provide an addendum to provide additional detail in the drawing.
77. The Curb Inlet Detail E3 on Sheet CK503 references the VDOT DI-2 Standard. This Standard varies in both length and drop location by structure. Inlet lengths are not listed on the Structure Schedules. Can the inlet length and type of each Curb Inlet please be provided?
The Contractor should install DI-2B with 4-foot L value for the curb inlets. We will issue an addendum to reflect direction in the detail.
78. Some Roof Drains are shown as being connected to the storm sewer systems mid pipe-run. Can a detail of this connection please be provided?
These connections are made with tees, elbows, wyes and branch connections unless a cleanout is shown in the drawing as C/O.
79. Some Storm Sewer pipes are shown as being connected mid-run. Several of these are listed below, can a detail for these connections please be provided?
ii. CB-154 to CB-41 connects to DMH-156 to DMH-157
jj. CB-5 connects to EX. DMH-64 to EX. DMH-63
kk. CB-60 connects to SIS-2B TO DMH-95
ll. CB-19 connects to DMH-142 to CB-103W
These are tee connections with gaskets for HDPE pipes (12x24x24; 12x12x12; 12x18x18; 12x30x30)
See link for a product example of dual wall tee fittings:
https://www.adspipe.com/pipe/fittings/dual-wall/tees
80. Structures shown in gray on the Stormwater Profiles appear to be existing. However, only some of these are labeled “EX.” Can you please confirm all structures shown in gray are existing?
All structures in gray are existing
81. The following pipe runs have a “tee” noted on the Stormwater Profiles, causing the pipe runs to deflect either horizontally or vertically between structures. Can you please provide a detail for the “tee” and allowable deflection limits?
a. DMH-64 to DMH-63
b. DMH-157 to DMH-158
c. DMH-142 to CB-103W
d. DMH-145 to DMH-146
Confirming tee callouts. Allowable deflections are per manufacturer’s specifications for the selected tee with gaskets.
82. Section 01 33 23, 1.12 part D - Can Procore submittal software be used in lieu of Submittal Exchange?
No.
https://www.adspipe.com/pipe/fittings/dual-wall/tees
83. Do we need to provide VDOT standard traffic control and ROW closures or can this all be coordinated privately with VAMC police?
Methods for traffic control should be in accordance with VDOT standards. The contractor shall present the finalized traffic plan to the VA for their acceptance. The campus presents its own unique logistics which may require coordination with VAMC police. The Contractor may provide suggestions to be implemented into the traffic plan as long as the VA accepts these.
84. Section 01 00 00 General Requirements 1.2.D states that the Department of Veterans Affairs will retain the services of a testing laboratory. Confirm that the awarded contractor is to NOT include costs for 3rd party geotechnical engineer for materials testing in accordance with 01 45 29.
Testing laboratory shall be retained by the contractor in accordance with specification section 01 45 29.
85. Please confirm that photo documentation per spec section 01 00 00
1.21.B will be required for this project?
Confirmed.
86. Considering this is an all outdoors project, will tuberculosis screening be required per 01 35 26 1.16.A? Can screening be limited to only workers required to be inside the facility?
Tuberculosis screening is required for all contractors in accordance with specification section 01 35 26 1.16.
87. Spec section 01 45 00 3.4.B states that the CQC Systems Manager is required to be a PM or SRE. These acronyms are not defined elsewhere and are not typical CQC acronyms, please clarify those requirements.
Spec section 01 45 00 3.4 B updated in addendum to remove the PM and SRE acronyms.
88. The specs and drawings call out asbestos transite pipe for abatement.
Have the soils been tested for hazmat? If not, will contaminated soils found during construction be considered a changed condition and paid for via change order?
FAR Part 52.236-2 "Differing Site Conditions Clause".
89. Do the drawings indicate all underground utility conflicts? If unidentified underground utilities are found during construction that conflict with the pathways of new utilities, and result in rerouting or excavating deeper, will a change order to accommodate the costs be given to reroute around or under? The potential for conflicts at these historical VAMC hospitals is extremely high and extremely expensive. Should the bidding contractors carry an allowance or bid per the plans and expect change orders for differing underground conditions?
FAR Part 52.236-2 "Differing Site Conditions Clause".
90. Spec section 32 90 00 outlines requirements for soil amendments, plantings, fertilizers, trees, shrubs, etc. However, the drawings do not indicate any landscaping plans or plant schedules. Please confirm that 32 90 00 is intended only for seeding and stabilizing disturbed areas and there is no requirement for plantings or hydroseeding, only topsoil and seed to prevent soil runoff?
Yes, only restoration to lawn is applicable. Topsoil and seeding are anticipated but other methods such as hydroseeding are acceptable.
91. Solicitation Page 9 – Instructions, item 7 states to include FAR 52.219-28 Post Award small Business Program Representation, however, I do not see this FAR included with the solicitation documents. Please provide.
See amendment A0005.
92. Please confirm that the Representations and certifications included with the solicitation (pages 13 – 16) must be returned with the proposal
Please return VAAR 852.219-75 signed for acknowledgement.
93. Spec Section 01 45 00 – section 3.2 b.1 states the CQC plan must “include a CQC System Manager that reports to the project superintendent.” Section 3.4B states “The CQC System Manger is assigned as CQC System Manager but has duties as project superintendent in addition to quality control.” Please confirm that the CQC System Manager and Project Superintendent may be the same individual for this project?
See response to question 7.
94. RFI – Curb Inlet Configuration
References: CU110–CU112; CK503 Detail E3
Please provide/confirm the required curb inlet configuration and inlet/throat length for CI-1 through CI-19.
The Contractor should use DI-2B, 4 ft “L” value configuration for curb inlets
95. RFI – Permits and Regulatory Approvals
References: 01 00 00; 01 57 19; 31 23 19
Please provide a complete list of required permits and regulatory approvals and confirm which are the responsibility of the Department of Veterans Affairs versus the Contractor, including the National Pollutant Discharge Elimination System (NPDES), Virginia Department of Environmental Quality (VDEQ), dewatering, and local permits.
We have obtained an Erosion and Stormwater Management Plan De Minimis Approval for the project design from VDEQ.
The Contractor is responsible for permits related to construction which we anticipate to include a Construction General Permit (CGP), dewatering permit and any permit related to asbestos pipe material and contaminated soil removal. The Contractor is responsible for the cost of these permits.
96. RFI – Construction Testing Responsibility
References: 01 00 00; 01 45 29
Please clarify which required material testing and inspection services are to be furnished and paid for by the Department of Veterans Affairs versus the Contractor.
See response to question 84.
97. RFI – Existing Stormwater Infrastructure Cleaning
References: 01 00 00; 33 40 00
Please provide the limits, quantities, pipe sizes, lengths, structures, required cleaning standard, and inspection requirements for cleaning the existing stormwater infrastructure included in the base bid.
Cleaning of existing stormwater infrastructure refers to items/keynotes within the project drawings such as, but not limited to the following:
1. Keynote 5 in CD series sheets (limits at location identified in drawing/structure)
2. Keynote 12 in CG series sheets (limits at location identified in drawing/structure)
3. Keynote 15 in CU series sheets (from upstream to downstream structure)
98. RFI – Geotechnical and Subsurface Conditions
References: 01 00 00; 31 20 11; 31 23 19
Please provide all available geotechnical reports, boring logs, groundwater information, and bid basis quantities for rock excavation and unsuitable material removal and replacement.
A geotechnical exploration program was not completed to support this project. The Contractor shall perform a geotechnical report as part of this project. Refer to Specification 31 20 11 for payment of rock excavation and unsuitable material. Rock removal requires a report with proof and measured quantities for payment to be submitted to the Government.
99. RFI – Existing Underground Utilities
References: 01 00 00; 33 10 00; 33 40 00
Please provide all available utility surveys and record drawings and confirm whether exploratory test pits or vacuum excavation required to verify existing underground utility locations and elevations are included in the Contractor’s base bid
The information shown in the drawings are the limits of existing conditions known for this project. The Contractor shall perform verification of existing underground utility locations and elevations as part of Contractor’s base bid
100. RFI – Asbestos Transite Quantity
References: 02 82 13.31
Please provide the quantity, size, location, and limits of asbestos containing Transite material to be included in the base bid and confirm the pricing mechanism for quantities exceeding the indicated amount.
1,900 LF of asbestos pipe removal should be allocated to the base bid. Cost for unknown unforeseen activities shall be handled under FAR Part 52.236-2 "Differing Site Conditions Clause".
101. RFI – Dewatering Discharge Requirements
References: 31 23 19; 01 57 19
Please identify the approved dewatering discharge locations and confirm any required treatment, filtration, sampling, monitoring, discharge limitations, and associated permitting requirements.
The construction documents did not include a plan or permit for dewatering. Per Specification 31 23 19, Section 1.3.G, the contractor is responsible for obtaining associated permitting.
102. RFI – Temporary Stormwater Bypass Requirements
References: 01 00 00; 33 40 00
Please confirm whether temporary bypass pumping, piping, diversion, or other measures are required to maintain the existing stormwater system during construction and provide the required capacity or design criteria.
Yes, these are required during construction. Contractor should refer to the VDEQ Stormwater Management Handbook Chapter 7, Design Specifications for Construction BMPs and CGP guidelines for these activities.
103. RFI – Contractor Work Hours
References: 01 00 00; 01 35 26
Please provide the permitted normal work hours and identify any work anticipated to require nights, weekends, holidays, or other after hours operations.
Reference question 21.
104. RFI – Traffic Control and Construction Phasing
References: 01 00 00
Please confirm if there is any construction phasing and traffic control restrictions, including allowable road and parking closures, pedestrian access requirements, emergency vehicle access, and limits on simultaneous work areas.
Ref. 01 00 00 Paragraph 1.6 Section G.
105. CU 107 -Keynote # 9 - Pump out water from flooded CB inlet. Contractor to investigate inlet & outlet connections to determine flood issue within the structure. Is the contractor responsible only for investigating? Will fixing the flood issue be a change order?
The Contractor should pump out water within flooded CB and clean pipelines connected to the structure. The Contractor should perform a CCTV field investigation and provide findings to VA to determine action, if any.
106. CU-103-107- Keynote #22 is in grey color (means not used in this sheet) whereas it is shown in dark color at CB -160 & 163. Please confirm the SOW at CB -160 & 163.
This is a typo and keynote 22 is included in these sheets and should be dark/bold color, inclusive of CB 160-163. A catch basin hood should be included for all proposed new catch basins. We will provide revised drawings in an addendum
107. CU 107- Keynote #24 has two arrows pointing at light poles, whereas one electric pole is in dark color and other one is in grey color. Are we responsible to replace two poles or one electric pole?
Gray shows the location of the existing light pole and dark shows where that existing light pole is to be re-installed (one light pole to be relocated).
108. CU-101-Keynote is missing for the dark line starting from DMH -B1.
Please share the pipe size and SOW.
Keynote will be added. Refer to sheet CU112, Valley Bypass Stormwater Pipes table for details on pipe. It is a 12” HDPE pipe that is 134 ft long.
109. CU-101-Keynote is missing for the pipe between DMH -132 & CB -115.
Are we supposed to replace the pipe between the structures? Please share the SOW.
Keynote will be added. Refer to CU110-CU112, it is a 37’ long 12” HDPE pipe
110. CU-101-Keynote #11 is shown between structures in certain sections and it is missing between some ( DMH -59 -DMH 110W, DMH -136 to DMH - 59). Please confirm that all lines shown in dark color are to be replaced with HDPE piping.
Refer to CU110-CU112 for pipe information. Dark color are proposed pipes.
111. CU-102 - Keynote #14-Remove intruding root in pipe. Are we replacing a section of the pipe? Scope of work is not clear.
Yes, the Contractor shall remove tree root and existing damaged pipe section and replace the damaged section with PVC pipe of the same size. We will provide an addendum to provide additional detail in the drawing.
112. CU-102-pipe between CB-116 & DMH -58 is shown in dark color, keynote is missing? Are we replacing the pipe, if yes, please share the sow.
Refer to CU110 for pipe information. Keynote will be added.
113. CU -103- the pipe lengths to the right of IP -2 all are marked with keynote
#11, whereas pipe lengths shown in dark color to the left of IP-2 ( infiltration pond) are missing keynote #11,.
Refer to sheets CU110 to CU112
114. Need clarification regarding new HDPE pipe replacement that are missing keynote #11 on all the drainage plans.
Refer to sheets CU110 to CU112
115. Can the VA provide existing drawings showing the sizes of the waterlines? Refer to responses to items 52 and 62.
116. Can the VA provide existing drawings showing the conductor sizes? The Contractor will be responsible for field investigation to determine the existing information for electrical services/conductor sizes
117. Sheet CD101 shows the existing pipe on Patriot Blvd to be removed from under the Guard Shack area. Instead of removing this section of pipe, can it be plugged and filled with flowable fill?
Yes, storm pipe located within the curb line of the guard shack may be plugged and filled with flowable fill.
118. If flowable fill is approved, can other areas be allowed to have flowable fill instead of removal to prevent additional demolition and repairs?
No.
119. Spec section 01 00 00 Paragraph 1.5 B 3 states that no photography of the VA premises is allowed. Please confirm the contractor or others are to take any photos.
No personal photography allowed. Photography related to scope of work is allowed.
120. Spec Section 01 00 00 Paragraph 1.21 states the contractor is to provide a commercial photographer for this project. With this project being the entire campus and over a year long, the cost of a professional photographer will be a large amount. Will this be a requirement for this project?
Yes. Contractor shall provide photographic documentation in accordance with specification section 01 00 00 1.21
121. Instructions to Bidders indicates we must complete and sign VAAR Clause 852.219-75 with the note see pages 55 and 56, but the solicitation is only 50 pages long. Please provide the document or update the reference.
Please return VAAR 852.219-75. This has been provided as an attachment for signature.
122. Instructions to Bidders indicates a completed and signed FAR 52.219-28 - Post Award Business program representation may be submitted as an alternative to SAM registration- please provide the document or update the for our use.
This clause does not apply. The solicitation is a SDVOSB set a side.
123. Page numbering of the solicitation claims there are 51 pages, the document is actually 50 pages long. Page 7 is missing. Please provide.
Please see updated solicitation.
124. Please confirm which FAR 52.225-12 Buy American Requirement is applicable. May 2014 or November 2023? Please incorporate the clause in detail to the contract.
Solicitation has been updated to include 52.225-11. Please see attachment.
125. Please confirm a cost-loaded schedule is required and all activities must be 20 days or less.
Confirmed.
126. Please confirm one individual can perform the collateral duties of Superintendent, QCM and SSHO.
See response to question 7.
127. Please confirm and identify any asbestos pipes or items in the project area.
02 82 13.31 1.1 B. 2. states to refer to project drawings for approximate quantities of ACM.
128. Section 01 45 29 states the Contractor is to retain the Testing Laboratory.
Section 01 00 00 states the VA will retain the Testing Laboratory. Which is correct?
See response to question 84.
129. Will the contractor be required to provide mowing or maintenance of lawns during the contract period? This could be an extensive cost.
Contractor is responsible for lawn maintenance of their assigned laydown area (within 10ft around office trailers, dumpsters and storage containers.)
130. Will the Contractor be required to maintain or water disturbed and reseeded areas after work is completed? If so, to what extent and for what duration?
Reference Section 32 90 00.
131. Please confirm that the price is not to include any rock removal. See response to question 59.
132. 01 00 00 - 1.2.D
01 45 29 - 1.1
Specification Section 01 00 00 - 1.2.D states "Before placement and installation of work subject to tests by testing laboratory retained by
Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspections." Specification Section 01 45 29 - 1.1 includes the phrase
"...testing activities and inspection services required during project construction to be provided by a Testing Laboratory retained by the
Contractor". Please clarify which testing services will be provided by
Department of Veterans Affairs and which testing services must be provided by the Contractor using a third party firm.
See response to question 84.
133.
01 00 00 - 1.5.E.1
Please clarify whether an authorization request will be necessary for vehicles making deliveries to the project.
Contractor shall coordinate material deliveries with the COR.
134. 01 00 00 - 1.5.E.2
Please confirm that there will be onsite parking available for contractor, subcontractor and vendor parking along with their employees working on the project. If not, then please clarify how parking will be addressed for the project and who will be allowed to park onsite.
Contractor parking is available adjacent to the contractor laydown area. Reference Figure 1 at end of document.
135. 01 00 00 - 1.6.B
Will Contractor be provided space to set up an office and if so where is the location?
Reference Figure 1 at end of document.
136. 01 00 00 - 1.6.F.2
There will be a significant amount of materials required for the successful performance of this project. In light of the material volume and liner nature of the project will material storage onsite be limited to only two day?
VA will provide the contractor with a laydown area for materials onsite. Final location will be coordinated with the COR depending on the amount of material to be stored onsite.
Contractor is responsible for transporting materials as needed to actual location of the work.
137. 01 00 00 - 1.6.F.2
This Specification Section states "Provide unobstructed access to Medical Center areas required to remain in operation". This project includes work in the main parking lot for Building 143 as well as work within the perimeter roadway and specifically near Building 75 and Building 76. Are there any work restrictions associated with this project as none are listed other than the general statement as noted herein?
It is the Contractor’s responsibility to create work plan to minimize facility operations. Reference specification section 01 000 00 paragraph 1.6 G.
138. 01 00 00 - 1.6.G.3
Please clarify whether there is an expectation that access and egress routes are to be provided through active and/or uncompleted work areas.
If not, please clarify whether alternate routes are to be provided and the nature of these routes if they are required.
Ref. 01 00 00 1.6 L and 01 00 00 16.
139. 01 00 00 - 1.6.H
Specification Section 01 00 00 - 1.6.H states "Before construction operations begin, Contractor shall provide a chain link construction fence
… around the construction area indicated on the drawings." This project is linear in its nature. Will construction fence be required for all active and/or unfinished work areas? Please clarify this requirement.
Yes.
140. 01 00 00 - 1.6.L
Specification Section 01 00 00 - 1.6.L states "Wherever excavation for new utility lines cross existing roads, at least one lane must be open to traffic at all times with approval." Even with approval there are several locations where new storm sewer lines run parallel, or nearly so, with the roadway. The work in the vicinity of Building 75 and Building 76 is an example of this condition. In light of the work required at the specific location and the nature of this project as a whole will Department of Veterans
Affairs be willing to allow partial roadway closures where work is occurring?
Roadway closures are made on a case by case basis based on overall impact to operations and needs of the medical facility. It is the contractor’s responsibility to prepare a raw work plan and coordinate with the COR.
141. 01 00 00 - 1.12
01 00 00 - 1.13
These specification sections appear to be dated relative to construction survey and layout currently being utilized in the industry. The use of GPS machine controls and rovers is more prevalent while traditional stakes with layout data is less common. GPS models are generated from the electronic plan data, a network of control points installed to 'localize' the project and GPS machine controls in concert with rovers used to perform the physical installation. Will the use of GPS machine controls and rovers be permissible or will physical staking and layout be required?
Reference 01 00 00 1.12 and 01 00 00 1.13.
142. 01 00 00 - 1.12
Will Contractor be provided with the electronic files (in CAD, DWG or TIN format) as requested to facilitate generation of a GPS model for the project
Yes, these can be provided among request, however, in any discrepancy between drawings and provided electronic files, the stamped drawings overrule.
143.
01 00 00 - 1.13.E
Please clarify the requirement for as-built and/or red line drawings at project completion as well as changes from the contract drawings as they occur during construction.
Requirements are provided in 01 00 00 1.13 and 01 00 00 1.14.
144. 01 00 00 - 1.13.F
If stamped and sealed drawings are required per 01 00 00 - 1.13E and 01 00 00 - 13.F then keeping full size plan sets to red line along with providing a scanned PDF upon completion of each phase as well as upon project acceptance seems superfluous.
Contract requirements remain unchanged.
145.
01 00 00 - 1.14
Please clarify the interim red line manual tracking and final as-built requirements.
Reference 01 00 00 1.13 and 01 00 00 1.14.
146.
Please explain the process for and expectations of the 4 month and 9 month post construction warranty inspection.
Reference 01 00 00 1.15.
147.
01 00 00 - 1.15.A.5
01 00 00 - 1.15.C
This Specification Section includes…
This is the start of the file's text. The full file is on GovTribe.