Amend 0002 RFI questions and sign in sheet 05222026.pdf

PDF 1 MB Posted

Attached to
Z1NB--Boiler replacement
Solicitation number
36C24626B0020_1
Issued by

About this file

This is an Amendment to Solicitation/Modification of Contract for a Department of Veterans Affairs boiler replacement project at the Durham VA Medical Center. The amendment provides responses to bidder questions submitted during the pre-solicitation phase and includes site visit sign-in sheets from May 11, 2026. The solicitation number is 36C24626B0020, with a project number of 558-22-152, issued by the VA Network Contracting Office 6 in Hampton, Virginia on May 22, 2026.

The amendment addresses over 100 bidder inquiries regarding project execution, staffing requirements, equipment specifications, and facility operations. Key clarifications include: the Superintendent and CQC System Manager may be the same individual, but the Safety and Health Officer (SSHO) must be a distinct, full-time role with no other duties; no deductive alternates are included despite language appearing in specifications; the VA will provide fuel and operators only for temporary boilers, with the contractor responsible for all other temporary boiler services including startup, permitting, and maintenance; the Commissioning Agent will be supplied by the VA via the design contract, with the contractor providing a Commissioning Manager and representatives; TB screening must be completed within 90 days of work start (tests read 48-72 hours post-injection); NTP may be issued as soon as 15 days after award; and the construction area does not require Infection Control Risk Assessment (ICRA) protections as it is not located near patient care areas. The amendment also specifies that utility work in parking lots shall occur during second shift (3pm-11:30pm) unless approved otherwise by the COR, and that existing underground storage tanks contain approximately 20,000 gallons of fuel that contractors should expect to be at near-capacity. The document confirms no preferred vendors are maintained and that coordination drawings, if needed, will be produced by the design contractor and distributed by the VA.

View the file

Other files

Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODECODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 20

0002 05-22-2026 558-22-152

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667

To all Offerors/Bidders

36C24626B0020

X

X X

The purpose of this amendment is to provide responses to bidder questions.

Not all questions have been answered. Another posting will be made when responses are available.

The amendment includes the two (2) pages of sign in sheets from the May 11, 2026 site visit.

ID Request for Information Request for Information Response

21 Can you please provide the job walk sign-in sheet?

Provided with the RFI responses

23 Is this project tax-exempt, and will the CO/COR provide the necessary tax-exempt certificates?

See the solicitation for information regarding taxes

24 Because of COVID-19 throughout the U.S. and the resulting Federal, State and local governments’ responses/requirements, are there any new work requirements or mandates that will be required by the VA on this project?

The solicitation is complete as to the current requirements and mandates

25 Many VA campuses are beginning to address tuberculosis protocols on VA campus projects, including the 90-day screening before assignment to the worksite. This requirement will limit the amount of personnel who can immediately perform work right after the award.

Will this project be required to follow 01 35 26

1.13 for TB-required protocols and a requirement to follow the 90-day screening before beginning work on the project?

Yes. Screening period is not 90 days. TB skin tests are read between 48-72 hours after injection. Test must be completed within 90 days of beginning work.

26 What is the approximate duration between issuing the award and issuing the NTP?

The VA may issue NTP as soon as 15 days after award.

27 For planning the preliminary project schedule, please provide an anticipated award date.

The award is anticipated to be during the current fiscal year

28 How many calendar days should be included in the critical-path method schedule for the owner and A/E to review and respond to RFIs?

Not less than 20 workdays, per Spec 01 32 16.15 - 1.7.A.3

29 How many calendar days should be included in the critical-path method schedule for owner and A/E submittal review?

Not less than 20 workdays, per Spec 01 32 16.15 - 1.7.A.3

31 Will this project allow for dual or triple hatting for the Superintendent, SSHO, and/or CQC Manager?

Superintendent and CQC System Manager can be 1 person, per Spec 01 45 00 - 3.4.B. SSHO is a distinct role and can have no other duties.

32 Please confirm that the project scope will be completed during normal working hours, not nights and weekends.

Per SOW, Utility work in the East or West Parking Lots shall be performed during VA working 2nd Shift, 3pm-11:30pm. Where Utility work in these areas does not interfere with regular traffic flow or Facility operations, it may be permitted during 1st Shift, subject to review and approval of the COR. Per Spec 23 52 39 - G.6.e, if variable hosptial loads interfere with testing, then testing shall be conducted on nights or weekends when loads are more stable. The COR, at their discretion, may require 2nd or weekend shift work if shutdowns, or other scheduled work activities, significantly impact Patient Care or standard Facility Operations. All other work to be conducted during VA working 1st shift, 7am - 3:30pm, 7:30am-4pm, or 8am-4:30pm.

34 Can you confirm that the owner will be contracting directly with a third-party commissioning agent for commissioning the project and that the Contractor is only to include participation/coordination with the Commissioning Agent?

The Commissioning Agent will be supplied by the VA via the Design Contract. The Contractor will have duties and responsibilities per Spec 01 91 00 - 1.8.B and per Spec 01 91 00 - 1.11.

35 Knowing that the campus is limited on space and parking, it is critical that the contactor project superintendent have freedom of access and close proximity to the work. Can the VA/Owner provide a designated parking spot for the contractor project superintendent?

The VA does not guarantee parking outside of the Contractor's designated construction area.

37 Can the contractor use an existing office inside the building for a temporary construction office during construction instead of setting up a temporary trailer?

Areas in Building 7 (Boiler Plant) within the Contractor's Scope of Work are available for Contractor use, provided that use does not impede construction activities. The use of the 1st Floor Kitchen/Break Room or 2nd Floor Office may be allowed, provided the COR reviews and approves the Contractor's proposed plan for use. If use is approved by the COR, the Contractor will be responsible for maintaining the condition of and repairing any and all damage caused by Contractor use of ancillary spaces.

38 Can the contractor use the existing restroom facilities in the work area or adjacent ones nearby?

The Contractor may use the existing restroom in Building 7. The Contractor will be responsible for maintaining the condition of and repairing any and all damage caused by Contractor use of the restroom.

Should the restroom in Building 7 be inoperable, the Contractor may use public restrooms located within the main Building, approximately 100 yards from the construction site.

39 Can the contractor use the existing on-site utilities for temporary electrical and water free of charge?

Existing on-site 120V electrical and water utilities located within the designated construction area are available for reasonable and moderate use, subject to review and approval by the COR. The Contractor may propose the installation of temporary electrical connections to the Facility grid to the COR for review and approval. Construction activities requiring significant electrical or water supply, e.g. welding and power washing, shall be supported by Contractor resources, e.g. generators and portable water tanks.

40 Will the owner provide the fire watch during the period that the fire suppression and/or fire alarm system is not in service?

No. Contractor is responsible for supplying any fire watches required due to Contractor/Construction activity.

41 Please provide detailed guidance for noise and vibration operations, including acceptable levels/duration, hours of operations for acceptable levels, and acceptable noise levels after hours.

The Construction Area is not located near patient care or patient-resident areas, and the VA does not anticipate any operational hour or noise/vibration restrictions based upon the scope of work. However, if contractor activity generates noise levels above 85 decibels, measured at the construction area perimeter, the Contractor must take measures to ensure the safety of potential passersby. Activities generating significant vibration must be coordinated with the COR and all possible measures taken to protect the integrity of Facility structures. The Construction Area is located adjacent to an animal research facility. The VA is not aware of any operational hour restrictions associated with animal research. However, if noise and/or vibration is interfering with the operation of the animal research facility, the Contractor will work with the COR and the Facility to minimize that interference. Any work anticipated to cause significant and sudden noise and/or vibration, e.g.

blasting, must be coordinated with and approved by the COR. After hours noise and vibration that interferes with patient restfulness will be eliminated or minimized to the greatest possible degree.

42 Please provide a bid form and a clear alternate schedule confirming how each deductive alternate is to be priced.

See the SF 1442 included with the solicitation. No deductive alternates are included.

43 Can you please confirm that we are to include the alternates mentioned on 01 00 00 - 2 section 1.4?

See the SF 1442 included with the solicitation. No deductive alternates are included.

44 Can you please provide the Commissioning firm has been or will be contracted for this project by the VA?

The Commissioning Agent will be supplied by the VA via the Design Contract. The Contractor will have duties and responsibilities per Spec 01 91 00 - 1.8.B and per Spec 01 91 00 - 1.11.

45 Per CD101, it appears the GC is to remove the existing prefabricated metal carport and storage shed. Is this to be salvaged and turned over to the Owner or is this to be disposed of?

Coordinate with COR prior to demolition. The VA may choose to retain this structure.

47 Please confirm who provides fuel, maintenance, startup, permitting, and monitoring for the temporary boilers.

VA to provide fuel and operators. Contractor to provide all other temporary boiler services, including, but not limited to, startup, permitting, maintenance, status & performance monitoring, repair, and replacement.

52 Please confirm Buy American requirements for major equipment, including boilers, pumps, controls, fuel oil tanks, structural steel, electrical gear, and fire protection materials.

Reference the solicitation for information regarding Buy American and Trade Agreements

53 Please provide Infection Control Risk Assessment (ICRA) requirements, temporary barriers, negative air requirements, shutdown procedures, and contractor certification requirements, if applicable.

Per Spec 01 00 00 - 1.7.H.2, Contractor is to notify COR of a shutdown no less than 4-weeks in advance of the initial proposed date. Scope of Work does not include patient care areas, and no ICRA requirements are anticipated.

57 Please confirm the contractor is responsible for acquiring all required air-permitting for the temporary boilers and new boilers with support from the COR and local station as required

Confirmed. VA to supply fuel and operators, only. All other requirements for temporary boilers to be furnished by the Contractor.

58 Please confirm the Government will provide all consumables for the rental boilers to include chemicals, propane, and fuel oil.

VA to provide fuel (propane and fuel oil) and operators, only. Contractor responsible for all other temporary boiler services, including, but not limited to, maintenance (including the supply and application of chemical treatment), performance monitoring, repair, and replacement.

61 Will the Government consider candidates with extensive relevant experience and CQM-C certification as meeting the qualification requirements in lieu of a formal degree, consistent with FAR and VA guidelines that allow for equivalent experience for technical roles?

No. The VA believes that the Specification requirements are appropriate to the complexity of this Scope of Work and its potential to adversely impact the Facility and Patient Care.

62 Please clarify whether QC Manager candidates with directly relevant QC experience on comparable Federal construction projects may be considered acceptable if their formal education differs from the degree described in the solicitation/specification/01 45 00, provided their qualifications are documented in the proposal/QC Plan submittal.

No. The VA believes that the Specification requirements are appropriate to the complexity of this Scope of Work and its potential to adversely impact the Facility and Patient Care.

63 Please confirm if the Government will consider a QA/QC organization in which the named QC Manager provides overall program management and decision-making authority, while on-site inspections and documentation are carried out by project-dedicated QC personnel reporting to that individual.

No. Per Spec 01 45 00 - 3.4.B, the CQC System Manager is within the onsite work organization. The CQC SM, or approved alternate, must be onsite at all times during work activities.

64 May CQM discipline-specific staff (HVAC, plumbing, electrical, low voltage, civil, etc.) be provided by trade subcontractors performing the work, rather than directly by the CM, provided they meet the minimum experience requirements?

No. Per Spec 01 45 00 - 3.4.C, the CQC specialized personnel must be distinct from the CQC SM and may not be supplied via Trades subcontracted by the Contractor. The contractor may employ an individual or a specialized technical company to serve in these roles, but an individual or company may not both perform and provide quality control for the work.

65 Given the limited structural steel scope associated with this project, would the Government consider waiving the requirement for the steel fabricator and erector to maintain AISC certification?

No. The VA must ensure the quality of all work performed, regardless of the extent or complexity for specific scopes.

69 Are there preferred vendors at this campus? No. Durham VA Engineering does not maintain a list of preferred vendors.

70 Will the VA provide all required fuel for temporary and permanent tanks and boilers?

Yes. VA to provide fuel and operators, only, for temporary boilers. All other required services, including, but not limited to, performance monitoring, maintenance, supplies, repair, and replacement to be furnished by Contractor.

71 Please clarify if offerors are to include sales tax in their proposals.

See the solicitation for information regarding taxes

72 Please clarify that the roles of project superintendent, SSHO, & CQC System Manager shall be filled by three individual persons.

The CQC SM and Superintendent may be one individual. The SSHO is a distinct role and individual with no other duties.

73 Is there a designated area available for contractor trailers & storage?

The VA does not guarantee any space beyond the designated construction area. Additional space for a Container, e.g. a Conex, or laydown yard may be available, but is not guaranteed.

75 There is a statement of deductive alternates included in specification section 01 00 00- 1.4, but no separate CLINs or mention of alternates in the drawing set. Please clarify if there are deductive alternates applicable, and if so, provide CLIN sheet and indicate if they are successive or independent alternates.

See the SF 1442 included with the solicitation. No deductive alternates are included.

90 What is the current PACS manufacturer and vendor, as well as location of nearest PACS control panel for tie-in of new card reader?

Current PACS system is the “S2 NetBox Enterprise” and is made by the S2 security corporation. Nearest Panel is in Building 15, approximately 200ft from badge reader location.

91 Are the propane tanks shown on AE311 provided by the VA or GC? If GC provided, please indicate size/capacity.

These will be supplied by the VA. Contractor to indicate on schedule, or to COR, when these tanks will be needed for commissioning/testing/startup activities.

92 Please confirm that the VA will provide fuel for the underground storage tanks and temporary boiler use.

Confirmed. VA will supply fuel for the new underground storage tanks and for the temporary boilers

101 Will the sign-in sheet from site visit be available in addendum?

Provided with the RFI responses

102 Please clarify if a superintendent can be a dual hat to cover the requirements of SSHO?

No. The Superintendent may also serve as the CQC SM, but the SSHO is a distinct role and individual with no other duties.

103 If no to the question above, will the SSHO need to be full-time for this project?

Per Spec 01 35 26 - 1.7.D, the SSHO will maintain a presence on site during construction operations.

104 Please clarify if a superintendent can be a dual hat to cover the requirements of QA/QC?

Per Spec 01 45 00 3.4.B, the CQC SM may serve in dual role as the Superintendent.

105 If no to the question above, will the QA/QC need to be full time for this project?

Per Spec 01 45 00 - 3.4.B, the CQC System Manager is within the onsite work organization. The CQC SM, or approved alternate, must be onsite at all times during work activities.

106 Can a superintendent be a triple hat to cover the requirements of SSHO and QA/QC?

No. The Superintendent may also serve as the CQC SM, but the SSHO is a distinct role and individual with no other duties.

107 Please confirm if tax should be included in our proposal? Will an exempt certificate be provided?

See the solicitation for information regarding taxes

108 Please confirm if the current prevailing wages will be consistent for the life of the project with no escalation?

Refer to Davis Bacon Act and state prevailing wage laws

115 Please clarify: • Existing BAS manufacturer and platform,

• Whether controls integration is contractor furnished,

• Whether licensing/software costs are included,

• Whether owner controls vendor participation is required,

• Responsibility for point-to-point checkout and graphics integration.

DA and Condensate tanks controlled by Siemens Insight. Contractor responsible for installation and coordinating integration with Facility and Facility Controls vendor. Contractor responsibility for point-to-point checkout and graphics integration defined by specifications for commissioining and other relevent sections.

117 As work occurs within an occupied healthcare facility operating 24/7, please clarify: • Required Infection Control Risk Assessment (ICRA) procedures,

• Required containment measures,

• Negative air requirements,

• Interim Life Safety requirements,

• Whether Government-provided ICRA permits are required prior to work.

The Construction Area is not located near patient care areas or in the medical facility and no ICRA requirements are anticipated.

118 Please clarify: • Existing roof warranty status,

• Approved roofing manufacturers,

• Requirements for new penetrations and patching,

• Whether manufacturer-certified installers are required.

Status of roof warranty is most likely expired. Other requirements detailed in Specifications for Division 07

119 Who is responsible for contracting the commissioning agent?

The VA is providing the Commissioning Agent via the design contract

120 20) What are the ICRA/PCRA requirements for this project?

The Construction Area is not located near patient care areas or in the medical facility and no ICRA requirements are anticipated.

121 Is the use of temporary plastic wall panels (such as STARC panels) acceptable to meet ICRA requirements?

The Construction Area is not located near patient care areas or in the medical facility and no ICRA requirements are anticipated.

124 Will hydrostatic testing be sufficient on all pipe welds or will x-ray be required?

see Specification 01 45 29 - 3.14

125 If X-ray is required, what percentage of welds and who will be responsible for the cost of testing?

see Specification 01 45 29 - 3.14, Contractor responsible for cost of all testing as detailed in the specifications

126 Can discharge water from hydrostatic testing be allowed to go into sewer drains or will the contractor need to provide a frac tank?

Refer to requirements of the City of Durham Public Works Department Requirements

127 Please confirm if there is assumed asbestos on any piping that is to be removed whether underground or within manholes or buildings?

Provide report if available.

No asbestos is anticipated within Building 7 or Temporary Boiler Facility. Refer to City of Durham Public Works information for possibility of asbestos-containing cement pipe within City distribution systems.

128 Will boiler and chiller plant, mechanical rooms etc. be cleared of all stored items and debris prior to the contractor entering those areas?

The VA is responsible for clearing VA-stored items from areas within the Contractor's scope of work.

129 Who is responsible for all coordination drawings if required? Who will act as the “Gate Keeper”

Coordination drawings, if needed, will be produced by the Design Contractor and distributed to the Construction Contractor by the VA

130 Will it be the responsibility of the mechanical contractor to lead the coordination process?

Question unclear. Coordination leader dependent upon item/trade/task.

COR generally responsible for coordination or establishing coordination between Contract Parties. Refer to Specifications

133 Who is vendor or contractor currently servicing and maintaining the Building Automation System or Temperature Controls System?

Siemens provides software system and technical support

134 Who is the vendor or contractor currently servicing and maintaining the Telecommunications System?

The VA utilizes several Telecommunications vendors depending upon the application. Telecomm for the scope of this project includes a PACS badge reader. Current PACS system is the “S2 NetBox Enterprise” and is made by the S2 security corporation.

135 Who is the vendor or contractor currently servicing and maintaining the Fire Alarm System?

Johnson Controls

137 Please confirm if there is a separate staging area onsite for fill material to be stockpiled for re-use?

The VA does not guarantee any space beyond the designated construction area. Additional space for a staging may be available at the time of need, but is not guaranteed.

139 If the underground site package requires removal of contaminated soils. Will the site contractor be required to have operators trained and certified in all various levels of contamination handling?

Spec 02 65 00 - 1.7

141 Please confirm if we will be allowed to keep a locked storage container or conex box within the grounds.

The VA does not guarantee any space beyond the designated construction area. Additional space for a Container, e.g. a Conex, or laydown yard may be available, but is not guaranteed.

142 Will a guard / escort be required at all work areas including but not limited to buildings, outside areas?

No

143 Please advise volume of fuel that needs to be pumped out from fuel tanks that are called out to be removed. If unknown, could the VA provide an allowance.

Current tank capacity is 20,000 gallons. Contractor should expect tank to contain near-max capacity fuel level

144 Please clarify which portions of the project are considered critical path by the VA.

Contractor to determine/propose, VA to review and approve

145 Is temporary office trailer placement permitted on site? If yes, where?

The VA does not guarantee any space beyond the designated construction area. Additional space for an office trailer may be available, but is not guaranteed.

155 Underground fuel tank removal and replacement will require support of excavation.

Clarify if the VA’s design team will be providing details for this location.

VA Design Contractor to provide support via submittal, shop drawing, and RFI review.

156 Clarify how the VA will proceed with unforeseen conditions.

See the solicitation for information regarding differing site conditions

157 Will the VA, VA Safety team, or local fire department require maintenance access to rear of boiler plant?

Contractor to maintain VA access to construction are, excepting where localized and specific safety concerns are present

158 There is existing equipment and storage sheds in close proximity the excavation area. Please confirm access to these areas will be significantly impacted by the excavation and work areas needed to replace the underground tanks.

the VA is aware of the impact to the accessibility of storage areas located within the construction area.

160 1. As the SSHO is governed by the FAR clause 52.236-6: superintendence, is dual and triple hat supervision allowed (Super/QC/SSHO or Super, QC/SSHO) or are there supervision roles that do not allow for collateral duties other than a primary role?

The Superintendent may also serve as the CQC SM, but the SSHO is a distinct role and individual with no other duties.

161 2. Is a project consultant required to be a third party contracted position for the development and issue of schedules, or can the Prime’s staff accomplish this role (Super/ Project manager)?

The Scheduling Consultant must be distinct from the Superintendent, but may be self-supplied by the Prime

162 3. What ICRA level temporary barrier is required for demolition inside of the plant (VA Staff occupied area, existing operating equipment)?

The Construction area is not located within patient care areas, and ICRA protections do not apply. Contractor responsible for general containment of construction dust/debris and preventing impact to areas outside of the construction area.

164 5. Please verify the QC manager may also be the SIOR.

The Superintendent may also serve as the CQC SM, but the SSHO is a distinct role and individual with no other duties.

165 6. Please verify if the Prime is to provide the Commissioning Agent, Commissioning Manager, and designated sub-contractor commissioning representatives to comply with he commissioning specifications.

Commissioining Agent to be supplied by the VA via Design Contract, Contractor to supply Contractor's Commissioning Manager, Representatives, and Trade/Subcontractor Representatives. Per Spec 01 91 00

166 7. Is the Commissioning Agent retained by the Government or the Prime on behalf of the government?

Commissioining Agent to be retained by the VA via Design Contract

173 2. Will a letter from the burner manufacturer be required to comply with: #16 on 23.09.11-9, “Controllers shall be the current generation product that will be supported by the manufacturer, with parts and service, for a minimum of ten years from time of installation.”

yes.

187 10. Can the facility provide an estimation of the amount of fuel to be reclaimed?

Existing UST capacity is 20,000 gallons. Contractor should expect tank to be at or near capacity at time of reclamation/removal

194 1. Is the countertop in room 107 to be removed and reinstalled, or replaced?

replaced

196 1. Is the phasing plan a suggestion for basis of project bid or the minimally accepted phasing plan for project schedule build and acceptance to meet facility operation requirements?

Per Spec 01 00 00 - 1.7.H, a phasing plan Submittal and review is required. The assumed required phasing sequence includes establishing a fully operational temporary boiler facility before decommissioning any existing boiler. Construction activity will not be allowed within an operational Boiler Facility. Temporary Facility will provide total supply to the Facility.

199 2. What is the current BAS manufacture? Siemens Insight software and hardware

201 1. Will a Bid Price/Schedule with the deducts be provided?

There are no bid deducts in this project. Inclusion of deduct language in drawings and specifications to be disregarded.

208 1. The QC specs require “The CQC system Manager is required to be a graduate engineer, graduate architect, or a graduate of construction management, with a minimum of 3 years construction experience on construction similar to the scope of this Contract.” Please confirm if this degree is required or if this can be waived if experience requirements is met.

Degree is required. The VA believes that the Specification requirements are appropriate to the complexity of this Scope of Work and its potential to adversely impact the Facility and Patient Care.

209 2. Please confirm the minimum total number of GC site personnel that are required to fulfill the roles of Superintendent, SSHO and QC manager.

The Superintendent may also serve as the CQC SM, but the SSHO is a distinct role and individual with no other duties. Two individuals, minimum.