About this file

This is a Construction Documentation specification section (01 32 00) for the Margaret Cochran Campus Repair Tunnels Utilities project (Project #630-26-800) under VISN 2 VA facilities. The specification establishes mandatory requirements for construction contractors awarded this project to utilize the Autodesk Build Construction Cloud (ACC) platform for all project management, collaboration, and official correspondence. VISN 2 provides access to the ACC platform and ProductivityNOW eLearning training portal at no cost to the contractor for the duration of the project.

Contractors must submit a written access request to the project Contracting Officer Representative (COR) no later than 14 days after contract award, including a list of staff requiring platform access with full names, company names, email addresses, and roles/positions. Upon access approval, all designated staff must complete required ACC training through the ProductivityNOW platform within 12 calendar days, with certificates of completion submitted to the COR within 2 business days. The specification mandates that all contract submissions, official project correspondence, RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys must occur exclusively through the ACC platform. Contractors must inform the COR of any staff changes within 2 business days and may add additional staff and subcontractors at any time through request submission. Failure to utilize the ACC platform will not entitle the contractor to additional time or contract amount increases, and work cannot begin until all ACC platform requirements, including training completion, are satisfied.

View the file

Other files

File Type Posted
230711 HVAC and Boiler Plant Insulation.pdf PDF
033000 Cast In Place.pdf PDF
015719 Temporary Enviromental Control.pdf PDF
013526 Safety Requirement.pdf PDF
013323 Shop Drawing.pdf PDF
013216.01 CMP.pdf PDF
000115 List of Drawing Sheets.pdf PDF
Repair Tunnel Utilities_Contract Document_Drawing.pdf PDF
RFI Questions_Repair Tunnel and Crawler Spaces Utilities_VA responses.pdf PDF
233400 HVAC FAN.pdf PDF
092900 Gypsum.pdf PDF
090516 Subsurface Preparation for Floor Finishes.pdf PDF
040100 Maintenance Mansory.pdf PDF
010000 General Requirement.pdf PDF
36C24226B0036 0001.docx DOCX document
260511 Requirements for Electrical Installations.pdf PDF
220511 Common Work Plumbing.pdf PDF
024100 Existing Condition.pdf PDF
014500 Quality Control.pdf PDF
013216.15 Project Schedule.pdf PDF
260526 Grounding and Bounding.pdf PDF
260519 Low Voltage Electrical Power.pdf PDF
099100 Painting.pdf PDF
NY Tax Exempt Form.pdf PDF
Steam Piping Pennoni Drawing.pdf PDF
36C24226B0036_1.docx DOCX document
Wage Determination.pdf PDF
VA NOTICE OF LIMITATIONS ON SUBCONTRACTING CERTIFICATION.pdf PDF
52.225-2 Buy American Certificate.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Margaret Cochran Campus

Project: REPAIR TUNNELS UTILITIES

Project #: 630-26-800

01 32 00 - 1

SECTION 01 32 00

CONSTRUCTION DOCUMENTATION

PART 1- GENERAL

1.1 DESCRIPTION:

A. Construction contractors, selected by award to perform work at VISN 2

VA facilities, are required to utilize VISN 2 Autodesk Build

Construction management platform, also called Autodesk Construction

Cloud (ACC). Access to the platform and training portal will be provided by VISN 2 through project Contracting Officer Representative

(COR) at no cost for the duration of the project. Autodesk Build is the management and collaborative environment that VISN 2 uses for all its

Non-Recurring Maintenance (NRM), Minor Program projects, Feasibility

Studies, Commissioning and Retro-Commissioning contracts. There is no user, license, or subscription fee to the contractor for using this cloud-based platform.

1.2 REQUIREMENTS:

A. Contractor shall accomplish and complete the following tasks upon award of contract:

1. Request access to ACC platform and ProductivityNOW eLearning Site to project VA COR NLT 14 days from contract award.

2. Only staff that shall utilize the platform to be granted access.

Examples: Project manager, sub-contractors POC, Site manager, Safety officer, etc.

3. The access request shall be in writing and include a list of staff.

The list shall include the following information:

• Full Name

• Company Name

• Email Address

• Role/Position on the project (i.e., Project manager, site super)

4. Upon granting access, staff shall complete required ACC training through ProductivityNOW platform within 12 Calendar days.

5. Upon successful completion of training, contractor shall submit certificates of completion to COR NLT 2 Business days.

B. Access to ProductivityNOW eLearning will expire after 12 Calendar days after online access is granted. Contractor shall complete ACC training within that period.

Margaret Cochran Campus

Project: REPAIR TUNNELS UTILITIES

Project #: 630-26-800

01 32 00 - 2

C. Additional Staff and Subcontractors can be added at any time with a request submission to the project COR as described above.

D. The contractor shall only use the ACC platform for all contract required submissions, official project correspondence to be acknowledged, reviewed, and actioned by the responsible party. No additional time shall be added to the contract, nor an increase in contract amount be provided for the contractor’s failure to utilize the

ACC platform as the project’s official communication and collaboration system. Any correspondence out of platform shall not be the governing authority contradicting direction and will be at the contractor’s expense. Official project correspondence and collaboration includes but not limited to: RFIs, submittals, schedules, shutdown requests, actionable tasks, reports, testing, safety inspections, photos, and site surveys.

E. Contractor must inform the COR of any staff changes NLT 2 business days from the change. Staff changes pertains to staff who was granted access to the ACC platform. Contractor shall request termination of access, replacement of personnel and/or any other action that might impact the contractor ability to maintain required utilization of the platform.

F. Contractor submission requirements cannot be accepted for work to begin without meeting all ACC Platform requirements outlined herein, including completing required ACC platform training.

- - - E N D - - -