090516 Subsurface Preparation for Floor Finishes.pdf
PDF 142 KB Posted
- Solicitation number
- 36C24226B0036
About this file
This is a technical specification for subsurface preparation for floor finishes as part of the VA New York Harbor Health Care System's Repair Tunnel Utilities project (Project No. 630-26-800). The specification (Section 09 05 16) establishes requirements for preparing concrete substrates to receive applied and resinous flooring installations, including removal of existing floor coverings (sheet goods and vinyl tiles), moisture and pH testing, remedial floor coating application, floor leveling, and repair to achieve a Concrete Surface Profile (CSP) of 3-4. The maximum moisture vapor transmission limit is 75% relative humidity per ASTM F1869 and ASTM F-2170 standards.
The specification requires three primary product systems: (1) a high-solids epoxy moisture remediation coating with minimum 10 mils thickness and permeance rating of less than 0.1 perm (ASTM E96/E96M), designed to suppress excess moisture prior to overlay; (2) cementitious self-leveling underlayment that is calcium aluminate cement-based with minimum 4,100 psi compressive strength and 1,000 psi flexural strength at 28 days, applicable for substrate repair and leveling in thicknesses from feathered edge to 1 inch; and (3) cementitious trowel-applied underlayment (not suitable for resinous finishes) with minimum 4,000 psi compressive strength. Execution requirements include maintaining ambient temperatures at 60-85°F, conducting moisture testing via ASTM F1869 and F2170, concrete surface preparation per ASTM D4259 using mechanical abrasive methods, pH measurement per ASTM F710, and flatness/levelness tolerances not exceeding 1/4 inch deviation in 10 feet. Field quality control sampling must be conducted by qualified independent testing facilities.
View the file
Other files
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
VA NEW YORK HARBOR HEALTH CARE SYSTEM
MARGARET COCHRAN CAMPUS
VA Project Title: REPAIR TUNNEL UTILITIES
VA Project No. 630-26-800
09 05 16 - 1
SECTION 09 05 16
SUBSURFACE PREPARATION FOR FLOOR FINISHES
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies subsurface preparation requirements for areas to receive the installation of applied and resinous flooring. This section includes removal of existing floor coverings as sheet goods and vinyl tiles, concrete for moisture and pH, remedial floor coating for concrete floor slabs having unsatisfactory moisture or pH condition.
Limits for moisture vapor transmission 75% relative Humidity ASTM F-
1869 and ASTM F-2170. Floor leveling and repair as required to meet CSP of 3-4.
1.2 RELATED WORK
A. Section 07 92 00, JOINT SEALANTS.
B. Section 09 67 23.20, RESINOUS EPOXY BASE WITH VINYL CHIP BROADCAST
(RES-2)
1.3 SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA and TEST DATA.
B. Written approval confirming product compatibility with subfloor material manufacturer and the flooring manufacturer
C. Product Data:
1. Moisture remediation system
2. Underlayment Primer
3. Cementitious Self-Leveling Underlayment
4. Cementitious Trowel-Applied Underlayment (Not suitable for resinous floor finishes)
D. Test Data:
1. Moisture test and pH results performed by a qualified independent testing agency or warranty holding manufacturer’s technical representative.
1.4 DELIVERY AND STORAGE
A. Deliver materials in containers with labels legible and intact and grade-seals unbroken.
B. Store material to prevent damage or contamination.
09 05 16 - 2
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced in text by basic designation only.
B. ASTM International(ASTM):
D638-14(2014)...........Standard Test Method for Tensile Properties of
Plastics
D4259-18(2019)..........Standard Practice for Preparation of Concrete by Abrasion Prior to Coating Application.
C109/C109M-20b(2020)....Standard Test Method for Compressive Strength of Hydraulic Cement Mortars (Using 2-in. or
[50-mm] Cube Specimens
7234-19(2020)...........Standard Test Method for Pull-Off Adhesion
Strength of Coatings on Concrete Using Portable
Pull-Off Adhesion Testers
E96/E96M-16(2016).......Standard Test Methods for Water Vapor
Transmission of Materials
F710-1e1(2020)..........Standard Practice for Preparing Concrete Floors to Receive Resilient Flooring
F1869-16a...............Standard Test Method for Measuring Moisture
Vapor Emission Rate of Concrete Subfloor Using
Anhydrous Calcium Chloride
F2170-19a(2020).........Standard Test Method for Determining Relative
Humidity in Concrete Floor Slabs Using in situ
Probes
C348-20(2020)...........Standard Test Method for Flexural Strength of
Hydraulic-Cement Mortars
C191-19(2020)...........Standard Test Method for Time of Setting of
Hydraulic Cement by Vicat Needle
PART 2 - PRODUCTS
2.1 PREPARED SUBSTRATE
A. Concrete Surface Profile.
2.2 MOISTURE REMEDIATION COATING
A. System Descriptions:
09 05 16 - 3
1. High-solids, epoxy system designed to suppress excess moisture in concrete prior to an overlayment. For use under resinous products, VCT, tile and carpet where issues caused by moisture vapor are a concern.
B. Products: Subject to compliance with applicable fire, health, environmental, and safety requirements for storage, handling, installation, and clean up.
C. System Components: Verify specific requirements as systems vary by manufacturer. Verify build up layers and installation method. Verify compatibility with substrate. Use manufacturer’s standard components, compatible with each other and as follows:
1. Liquid applied coating:
a. Resin: epoxy.
b. Formulation Description: Multiple component high solids.
c. Application: Per manufacturer’s written installation requirements.
d. Thickness: minimum 10 mils
D. Material Vapor Permeance: Application shall achieve a permeance rating of less than 0.1 perm in accordance with ASTM E96/E96M.
E. Maximum RH requirement: 100% testing in accordance with ASTM F2170.
Property Test Value
Tensile Strength
ASTM D638 4,400 psi
Volatile Organic Compound
Limits (V.O.C.)
SCAMD Rule 1113
(Ammended
02/05/2016)
25 grams per liter
Permeance ASTM E96 0.1 perms
Tensile Modulus ASTM D638 1.9X105 psi
Percent Elongation ASTM D638 12%
Cure Rate Per manufacture’s
Data
4 hours Tack free with 24hr recoat window
Bond Strength ASTM D7234 100% bond to concrete failure
09 05 16 - 4
2.3 CEMENTITIOUS SELF-LEVELING UNDERLAYMENT
A. System Descriptions:
1. High performance self-leveling underlayment resurfacer. Single component, self-leveling, cementitious material designed for easy application as an underlayment for all types of flooring materials.
It is used for substrate repair and leveling.
B. Products: Subject to compliance with applicable fire, health, environmental, and safety requirements for storage, handling, installation, and clean up. Gypsum-based products are unacceptable.
C. System Characteristics:
1. Wearing Surface: smooth
2. Thickness: Per architectural drawings, ranging from feathered edge to 1”, per application. Applications greater than 1” require additional 3/8” aggregate to mix or as recommended by manufacturer.
D. Underlayment shall be calcium aluminate cement-based, containing
Portland cement. Gypsum-based products are unacceptable.
E. Compressive Strength: Minimum 4100 psi in 28 days in accordance with
ASTM C109/C109M.
F. Flexural Strength: Minimum 1000 psi in 28 days in accordance with ASTM
C348
G. Dry Time: Underlayment shall receive the application of moisture insensitive tile in 6 hours, floor coverings in 16 hours, and resinous flooring in 3 days.
H. Primer: compatible and as recommended by manufacturer for use over intended substrate
I. System Components: Manufacturer's standard components that are compatible with each other and as follows:
1. Primer:
a. Resin: copolymer
b. Formulation Description: single component ready to use.
c. Application Method: Squeegee and medium nap roller.
d. All puddles shall be removed, and material shall be allowed to dry, 1-2 hours at 70F/21C.
e. Number of Coats: (1) one.
2. Grout Resurfacing Base:
09 05 16 - 5
a. Formulation Description: Single component, cementitious self-leveling high-early and high-ultimate strength grout.
b. Application Method: colloidal mix pump, cam rake, spike roll.
1) Thickness of Coats: Per architectural scope, 1” lifts.
2) Number of Coats: More than one if needed.
c. Aggregates: for applications greater than 1inch, require additional 3/8” aggregate to mix.
J.
2.4 CEMENTITIOUS TROWEL-APPLIED UNDERLAYMENT(NOT SUITABLE FOR RESINOUS FLOOR
FINISHES)
A. Underlayment shall be calcium aluminate cement-based, containing
Portland cement. Gypsum-based products are unacceptable.
B. Compressive Strength: Minimum 4000 psi in 28 days
C. Trowel-applied underlayment shall not contain silica quartz (sand).
D. Dry Time: Underlayment shall receive the application of floor covering in 15-20 minutes.
PART 3 - EXECUTION
3.1 ENVIRONMENTAL REQUIREMENTS
A. Maintain ambient temperature of work areas at not less than 16 degree C
(60 degrees F), without interruption, for not less than 24 hours before testing and not less than three days after testing.
B. Maintain higher temperatures for a longer period of time where required by manufacturer's recommendation.
C. Do not install materials when the temperatures of the substrate or materials are not within 60-85 degrees F/ 16-30 degrees C.
3.2 SURFACE PREPARATION
A. Existing concrete slabs with existing floor coverings:
1. Conduct visual observation of existing floor covering for adhesion, water damage, alkaline deposits, and other defects.
Property Test Value
Compressive Strength
ASTM C109/C109M
2,200 psi @ 24 hrs
3,000 psi @ 7 days
Initial set time
Final Set time
ASTM C191
30-45 min.
1 to 1.5 hours
Bond Strength
ASTM D7234
100% bond to concrete failure
09 05 16 - 6
2. Remove existing floor covering and adhesives. Comply with local, state and federal regulations and the RFCI Recommended Work
Practices for Removal of Resilient Floor Coverings, as applicable to the floor covering being removed.
B. Concrete shall meet the requirements of ASTM F710 and be sound, solid, clean, and free of all oil, grease, dirt, curing compounds, and any substance that might act as a bond-breaker before application. As required prepare slab by mechanical methods. No chemicals or solvents shall be used.
C. General: Prepare and clean substrates according to flooring manufacturer's written instructions for substrate indicated.
D. Prepare concrete substrates per ASTM D4259 as follows:
1. Dry abrasive blasting.
2. Wet abrasive blasting.
3. Vacuum-assisted abrasive blasting.
4. Centrifugal-shot abrasive blasting.
5. Comply with manufacturer's written instructions.
E. Repair damaged and deteriorated concrete according to flooring manufacturer's written recommendations.
F. Verify that concrete substrates are dry.
G. Perform anhydrous calcium chloride test, ASTM F 1869. Proceed with application only after substrates have maximum moisture-vapor-emission rate of per flooring manufactures formal and project specific written recommendation.
H. Perform in situ probe test, ASTM F2170. Proceed with application only after substrates do not exceed a maximum potential equilibrium relative humidity per flooring manufacture’s formal and project specific written recommendation.
I. Provide a written report showing test placement and results.
J. Prepare joints in accordance with Section 07 92 00, JOINT SEALANTS and material manufacturer’s instructions.
K. Alkalinity: Measure surface pH in accordance with procedures provided in ASTM F710 or as outlined by qualified testing agency or flooring manufacturer’s technical representative.
L. Tolerances: Subsurface shall meet the flatness and levelness tolerance specified on drawings or recommended by the floor finish manufacturer.
09 05 16 - 7
Tolerance shall also not to exceed 1/4” deviation in 10’. As required, install underlayment to achieve required tolerance.
M. Other Subsurface: For all other subsurface conditions, such as wood or metal, contact the floor finish or underlayment manufacturer, as appropriate, for proper preparation practices.
3.3 MOISTURE REMEDIATION COATING
A. Where results of relative humidity testing (ASTM F2170) exceed the requirements of the specified flooring manufacturer, apply remedial coating as specified to correct excessive moisture condition.
B. Prior to remedial floor coating installation mechanically prepare the concrete surface to provide a concrete surface profile in accordance with ASTM D4259.
C. Mix and apply moisture remediation coating in accordance with manufacturer’s instructions.
3.4 CEMENTITOUS UNDERLAYMENT
A. Install cementitious self-leveling underlayment as required to // correct surface defects, // floor flatness or levelness corrections to meet the tolerance requirements as or detailed on drawings, // address non-moving cracks or joints, // provide a smooth surface for the installation of floor covering,// or meet elevation requirements detailed on drawings.
B. Mix and apply in accordance with manufacturer's instructions.
3.5 PROTECTION
A. Prior to the installation of the finish flooring, the surface of the underlayment should be protected from abuse by other trades by the use of plywood, tempered hardwood, or other suitable protection course
3.6 FIELD QUALITY CONTROL
A. Where specified, field sampling of products shall be conducted by a qualified, independent testing facility.
- - - E N D - - -