This is a specification section for painting work on the Margaret Cochran Campus Repair Tunnels Utilities project (Project #630-26-800). The specification outlines comprehensive requirements for all painting and finishing tasks, including prime coats, surface preparation, and finish applications across various substrates such as ferrous metals, galvanized metals, concrete block, gypsum drywall, and wood.

The contractor must use Benjamin Moore paints and comply with Master Painters Institute (MPI) product specifications, with all coats on a particular substrate sourced from a single manufacturer. Volatile Organic Compound (VOC) content limits are specified for different paint types: flat paints at 50 g/L, non-flat at 150 g/L, primers at 200 g/L, and anticorrosive paints at 250 g/L. Lead content must not exceed 0.06 percent by weight. Painters must be qualified journeymen with documented experience on at least three similar projects within three years. Paint applications require brush or roller methods, with spray application only upon written approval from the Contracting Officer Representative (COR). Surface preparation is mandatory, including cleaning, sanding, and moisture content verification (maximum 12-15 percent depending on substrate type). Applications typically require three coats: prime, body, and finish, with minimum 48-hour drying intervals. The specification includes detailed identity painting schedules for piping systems following ASME A13.1 standards, with specific color-coding for various pipe contents and pressure designations. Mock-up panels must be approved on-site before proceeding with full work, and all painting must comply with federal safety requirements, environmental regulations, and manufacturer specifications.

View the file

Other files

File Type Posted
233400 HVAC FAN.pdf PDF
092900 Gypsum.pdf PDF
090516 Subsurface Preparation for Floor Finishes.pdf PDF
040100 Maintenance Mansory.pdf PDF
010000 General Requirement.pdf PDF
36C24226B0036 0001.docx DOCX document
230711 HVAC and Boiler Plant Insulation.pdf PDF
033000 Cast In Place.pdf PDF
015719 Temporary Enviromental Control.pdf PDF
013526 Safety Requirement.pdf PDF
013323 Shop Drawing.pdf PDF
013216.01 CMP.pdf PDF
000115 List of Drawing Sheets.pdf PDF
Repair Tunnel Utilities_Contract Document_Drawing.pdf PDF
RFI Questions_Repair Tunnel and Crawler Spaces Utilities_VA responses.pdf PDF
260511 Requirements for Electrical Installations.pdf PDF
220511 Common Work Plumbing.pdf PDF
024100 Existing Condition.pdf PDF
014500 Quality Control.pdf PDF
013216.15 Project Schedule.pdf PDF
013200 Construction Documentation.pdf PDF
260526 Grounding and Bounding.pdf PDF
260519 Low Voltage Electrical Power.pdf PDF
Wage Determination.pdf PDF
VA NOTICE OF LIMITATIONS ON SUBCONTRACTING CERTIFICATION.pdf PDF
52.225-2 Buy American Certificate.pdf PDF
NY Tax Exempt Form.pdf PDF
Steam Piping Pennoni Drawing.pdf PDF
36C24226B0036_1.docx DOCX document
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Margaret Cochran Campus

Project: REPAIR TUNNELS UTILITIES

Project #: 630-26-800

09 91 00 - 1

SECTION 09 91 00

PAINTING

PART 1 - GENERAL

DESCRIPTION

A. Work of this Section includes all labor, materials, equipment, and services necessary to complete the painting and finishing as shown on the construction documents and/or specified herein, including, but not limited to, the following:

1. Prime coats which may be applied in shop under other sections.

2. Prime painting unprimed surfaces to be painted under this Section.

3. Painting items furnished with a prime coat of paint, including touching up of or repairing of abraded, damaged or rusted prime coats applied by others.

4. Painting ferrous metal (except stainless steel) exposed to view.

5. Painting galvanized ferrous metals exposed to view.

6. Painting interior concrete block exposed to view.

7. Painting gypsum drywall exposed to view.

8. Painting of wood exposed to view, except items which are specified to be painted or finished under other Sections of these specifications.

Back painting of all wood in contact with concrete, masonry or other moisture areas.

9. Painting pipes, pipe coverings, conduit, ducts, insulation, hangers, supports and other mechanical and electrical items and equipment exposed to view.

10. Painting surfaces above, behind or below grilles, gratings, diffusers, louvers lighting fixtures, and the like, which are exposed to view through these items.

11. Painting includes shellacs, stains, varnishes, coatings specified, and striping or markers and identity markings.

12. Incidental painting and touching up as required to produce proper finish for painted surfaces, including touching up of factory finished items.

13. Painting of any surface not specifically mentioned to be painted herein or on construction documents, but for which painting is obviously necessary to complete the job, or work which comes within the intent of these specifications, is to be included as though specified.

09 91 00 - 2

RELATED WORK

A. Section 01 35 26, SAFETY REQUIREMENTS.

B. Section 08 14 00, INTERIOR WOOD DOORS: Prefinished flush doors with transparent finishes.

C. Section 09 06 00, SCHEDULE FOR FINISHES: Type of Finish, Color, and Gloss

Level of Finish Coat.

D. Division 12 FURNISHINGS: Shop prime painting of steel and ferrous metals.

SUBMITTALS

A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.

B. Sustainable Design Submittals as described below:

1. Volatile organic compounds per volume as specified in PART 2 –

PRODUCTS.

C. Painter qualifications.

D. Manufacturer's Literature and Data:

1. Before work is started, or sample panels are prepared, submit manufacturer's literature and technical data, the current Master

Painters Institute (MPI) "Approved Product List" indicating brand label, product name and product code as of the date of contract award, will be used to determine compliance with the submittal requirements of this specification. The Contractor may choose to use subsequent MPI

"Approved Product List", however, only one (1) list may be used for the entire contract and each coating system is to be from a single manufacturer. All coats on a particular substrate must be from a single manufacturer. No variation from the MPI "Approved Product List" where applicable is acceptable.

E. Sample Panels:

1. After painters' materials have been approved and before work is started, submit sample panels showing each type of finish and color specified.

2. Panels to Show Color: Composition board, 100 x 250 mm (4 x 10 inch).

3. Panel to Show Transparent Finishes: Wood of same species and grain pattern as wood approved for use, 100 x 250 mm (4 x 10 inch face) minimum, and where both flat and edge grain will be exposed, 250 mm

(10 inches) long by sufficient size, 50 x 50 mm (2 x 2 inch) minimum or actual wood member to show complete finish.

4. Attach labels to panel stating the following:

09 91 00 - 3

a. Federal Specification Number or manufacturers name and product number of paints used.

b. Specification code number specified in Section 09 06 00, SCHEDULE

FOR FINISHES.

c. Product type and color.

d. Name of project.

5. Strips showing not less than 50 mm (2 inch) wide strips of undercoats and 100 mm (4 inch) wide strip of finish coat.

F. Sample of identity markers if used.

G. Manufacturers' Certificates indicating compliance with specified requirements:

1. Manufacturer's paint substituted for Federal Specification paints meets or exceeds performance of paint specified.

2. High temperature aluminum paint.

3. Epoxy coating.

4. Intumescent clear coating or fire-retardant paint.

5. Epoxy floor coating.

DELIVERY AND STORAGE

A. Deliver materials to site in manufacturer's sealed container marked to show following:

1. Name of manufacturer.

2. Product type.

3. Batch number.

4. Instructions for use.

5. Safety precautions.

B. In addition to manufacturer's label, provide a label legibly printed as following:

1. Federal Specification Number, where applicable, and name of material.

2. Surface upon which material is to be applied.

3. Specify Coat Types: Prime; body; finish; etc.

C. Maintain space for storage, and handling of painting materials and equipment in a ventilated, neat and orderly condition to prevent spontaneous combustion from occurring or igniting adjacent items.

D. Store materials at site at least 24 hours before using, at a temperature between 7 and 30 degrees C (45 and 85 degrees F).

09 91 00 - 4

QUALITY ASSURANCE

A. Qualification of Painters: Use only qualified journeyman painters for the mixing and application of paint on exposed surfaces. Submit evidence that key personnel have successfully performed surface preparation and application of coating on a minimum of three (3) similar projects within the past three (3) years.

B. Paint Coordination: Provide finish coats which are compatible with the prime paints used. Review other Sections of these specifications in which prime paints are to be provided to ensure compatibility of the total coatings system for the various substrates. Upon request from other subcontractors, furnish information on the characteristics of the finish materials proposed to be used, to ensure that compatible prime coats are used. Provide barrier coats over incompatible primers or remove and re-prime as required. Notify the Contracting Officer Representative (COR) in writing of any anticipated problems using the coating systems as specified with substrates primed by others.

MOCK-UP PANEL

A. In addition to the samples specified herein to be submitted for approval, apply in the field, at their final location, each type and color of approved paint materials, applied 3.05 m (10 feet) wide, floor to ceiling of wall surfaces, before proceeding with the remainder of the work, for approval by the COR. Paint mock-ups to include one (1) door and frame assembly.

B. Finish and texture approved by COR will be used as a standard of quality and workmanship for remainder of work.

C. Repaint individual areas which are not approved, as determined by the COR, until approval is received. //

REGULATORY REQUIREMENTS

A. Paint materials are to conform to the restrictions of the local

Environmental and Toxic Control jurisdiction.

1. Volatile Organic Compounds (VOC) Emissions Requirements: Field-applied paints and coatings that are inside the waterproofing system to not exceed limits of authorities having jurisdiction.

2. Lead-Base Paint:

a. Comply with Section 410 of the Lead-Based Paint Poisoning Prevention

Act, as amended, and with implementing regulations promulgated by

Secretary of Housing and Urban Development.

09 91 00 - 5

b. Regulations concerning prohibition against use of lead-based paint in federal and federally assisted construction, or rehabilitation of residential structures are set forth in Subpart F, Title 24, Code of

Federal Regulations, Department of Housing and Urban Development.

c. Do not use coatings having a lead content over 0.06 percent by weight of non-volatile content.

d. For lead-paint removal, see Section 02 83 33.13, LEAD-BASED PAINT

REMOVAL AND DISPOSAL.

3. Asbestos: Provide materials that do not contain asbestos.

4. Chromate, Cadmium, Mercury, and Silica: Provide materials that do not contain zinc-chromate, strontium-chromate, Cadmium, mercury or mercury compounds or free crystalline silica.

5. Human Carcinogens: Provide materials that do not contain any of the

ACGIH-BKLT and ACGHI-DOC confirmed or suspected human carcinogens.

6. Use high performance acrylic paints in place of alkyd paints.

SAFETY AND HEALTH

A. Apply paint materials using safety methods and equipment in accordance with the following:

1. Comply with applicable Federal, State, and local laws and regulations, and with the ACCIDENT PREVENTION PLAN, including the Activity Hazard

Analysis (AHA) as specified in Section 01 35 26, SAFETY REQUIREMENTS.

The AHA is to include analyses of the potential impact of painting operations on painting personnel and on others involved in and adjacent to the work zone.

B. Safety Methods Used During Paint Application: Comply with the requirements of SSPC PA Guide 10.

C. Toxic Materials: To protect personnel from overexposure to toxic materials, conform to the most stringent guidance of:

1. The applicable manufacturer’s Material Safety Data Sheets (MSDS) or local regulation.

2. 29 CFR 1910.1000.

3. ACHIH-BKLT and ACGHI-DOC, threshold limit values.

APPLICABLE PUBLICATIONS

A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced in the text by basic designation only.

B. American Conference of Governmental Industrial Hygienists (ACGIH):

09 91 00 - 6

ACGIH TLV-BKLT-2012.....Threshold Limit Values (TLV) for Chemical

Substances and Physical Agents and Biological

Exposure Indices (BEIs)

ACGIH TLV-DOC-2012......Documentation of Threshold Limit Values and

Biological Exposure Indices, (Seventh Edition)

C. ASME International (ASME):

A13.1-07(R2013).........Scheme for the Identification of Piping Systems

D. Code of Federal Regulation (CFR):

40 CFR 59...............Determination of Volatile Matter Content, Water

Content, Density Volume Solids, and Weight Solids of Surface Coating

E. Commercial Item Description (CID):

A-A-1272A...............Plaster Gypsum (Spackling Compound)

F. Federal Specifications (Fed Spec):

TT-P-1411A..............Paint, Copolymer-Resin, Cementitious (For

Waterproofing Concrete and Masonry Walls) (CEP)

G. Master Painters Institute (MPI):

1.......................Aluminum Paint

3.......................Primer, Alkali Resistant, Water Based

4.......................Interior/ Exterior Latex Block Filler

5.......................Exterior Alkyd Wood Primer

6.......................Exterior, Latex for Exterior Wood Primer

7.......................Exterior Oil Wood Primer

8.......................Exterior Alkyd, Flat MPI Gloss Level 1

9.......................Exterior Alkyd Enamel MPI Gloss Level 6

10......................Exterior Latex, Flat

11......................Exterior Latex, Semi-Gloss

15......................Exterior Latex, Low Sheen (MPI Gloss Level 3-4)

17......................Primer, Bonding, Waterbased

18......................Organic Zinc Rich Primer

22......................Aluminum Paint, High Heat (up to 590% - 1100F)

23......................Primer, Metal, Surface Tolerant

27......................Exterior / Interior Alkyd Floor Enamel, Gloss

31......................Polyurethane, Moisture Cured, Clear Gloss

36......................Knot Sealer

39......................Primer, Latex, for Interior Wood

09 91 00 - 7

40......................Exterior, Latex High Build

42......................Textured Coating, Latex, Flat

43......................Interior Satin Latex, MPI Gloss Level 4

44......................Interior Low Sheen Latex, MPI Gloss Level 2

45......................Interior Primer Sealer

46......................Interior Enamel Undercoat

47......................Interior Alkyd, Semi-Gloss, MPI Gloss Level 5

48......................Interior Alkyd, Gloss, MPI Gloss Level 6

50......................Interior Latex Primer Sealer

51......................Interior Alkyd, Eggshell, MPI Gloss Level 3

52......................Interior Latex, MPI Gloss Level 3

53......................Interior Latex, Flat, MPI Gloss Level 1

54......................Interior Latex, Semi-Gloss, MPI Gloss Level 5

59......................Interior/Exterior Alkyd Porch & Floor Enamel, Low

Gloss

60......................Interior/Exterior Latex Porch & Floor Paint, Low

Gloss

66......................Interior Alkyd Fire Retardant, Clear Top-Coat (ULC

Approved)

67......................Interior Latex Fire Retardant, Top-Coat (ULC

Approved)

68......................Interior/ Exterior Latex Porch & Floor Paint, Gloss

71......................Polyurethane, Moisture Cured, Clear, Flat

77......................Epoxy Cold Cured, Gloss

79......................Marine Alkyd Metal Primer

90......................Interior Wood Stain, Semi-Transparent

91......................Wood Filler Paste

94......................Exterior Alkyd, Semi-Gloss

95......................Fast Drying Metal Primer

98......................High Build Epoxy Coating

99......................Sealer, Water-based, for Concrete Floors

101.....................Epoxy Anti-Corrosive Metal Primer

107.....................Primer, Rust-Inhibitive, Water-based

108.....................High Build Epoxy Coating, Low Gloss

09 91 00 - 8

113.....................Elastomeric, Pigmented, Exterior, Water-based, Flat

114.....................Interior Latex, Gloss

115.....................Epoxy-Modified Latex, Interior Gloss (MPI gloss level 6)

118.....................Dry Fall, Latex Flat

119.....................Exterior Latex, High Gloss (acrylic)

134.....................Galvanized Water Based Primer

135.....................Non-Cementitious Galvanized Primer

138.....................Interior High Performance Latex, MPI Gloss Level 2

139.....................Interior High Performance Latex, MPI Gloss Level 3

140.....................Interior High Performance Latex, MPI Gloss Level 4

141.....................Interior High Performance Latex (SG) MPI Gloss

Level 5

144.....................Latex, Interior, Institutional Low Odor / VOC, (MPI Gloss Level 2)

145.....................Latex, Interior, Institutional Low Odor / VOC, (MPI Gloss Level 3)

146.....................Latex, Interior, Institutional Low Odor / VOC, (MPI Gloss Level 4)

151.....................Light Industrial Coating, Interior, Water-based, (MPI Gloss Level 3)

153.....................Light Industrial Coating, Interior, Water-based, (MPI Gloss Level 4)

163.....................Exterior Water Based Semi-Gloss Light Industrial

Coating, MPI Gloss Level 5

164.....................Exterior, Water Based, Gloss, Light Industrial

Coating, MPI Gloss Level 6

H. Society for Protective Coatings (SSPC):

SSPC SP 1-82(R2004).....Solvent Cleaning

SSPC SP 2-82(R2004).....Hand Tool Cleaning

SSPC SP 3-28(R2004).....Power Tool Cleaning

SSPC SP 10/NACE No.2....Near-White Blast Cleaning

SSPC PA Guide 10........Guide to Safety and Health Requirements

I. Maple Flooring Manufacturer’s Association (MFMA):

J. U.S. National Archives and Records Administration (NARA):

29 CFR 1910.1000........Air Contaminants

09 91 00 - 9

K. Underwriter’s Laboratory (UL)

PART 2 - PRODUCTS

BEJAMIN MOORE

MATERIALS:

A. Conform to the coating specifications and standards referenced in PART 3.

Submit manufacturer’s technical data sheets for specified coatings and solvents.

PAINT PROPERTIES:

A. Use ready-mixed (including colors), except two component epoxies, polyurethanes, polyesters, paints having metallic powders packaged separately and paints requiring specified additives.

B. Where no requirements are given in the referenced specifications for primers, use primers with pigment and vehicle, compatible with substrate and finish coats specified.

C. Provide undercoat paint produced by the same manufacturer as the finish coats. Use only thinners approved by the paint manufacturer and use only to recommended limits.

D. //VOC Content: For field applications that are inside the weatherproofing system, paints and coating to comply with VOC content limits of authorities having jurisdiction and the following VOC content limits:

1. Flat Paints and Coatings: 50 gram/liter.

2. Non-flat Paints and Coatings: 150 gram/liter.

3. Dry-Fog Coatings: 400 gram/liter.

4. Primers, Sealers, and Undercoaters: 200 gram/liter.

5. Anticorrosive and Antirust Paints applied to Ferrous Metals: 250 gram/liter.

6. Zinc-Rich Industrial Maintenance Primers: 340 gram/liter.

7. Pretreatment Wash Primers: 420 gram/liter.

8. Shellacs, Clear: 730 gram/liter.

9. Shellacs, Pigmented: 550 gram/liter.

E. VOC test method for paints and coatings is to be in accordance with

40 CFR 59 (EPA Method 24). Part 60, Appendix A with the exempt compounds’ content determined by Method 303 (Determination of Exempt Compounds) in the South Coast Air Quality Management District’s (SCAQMD) “Laboratory

Methods of Analysis for Enforcement Samples” manual.

09 91 00 - 10

PLASTIC TAPE:

A. Pigmented vinyl plastic film in colors as specified in Section 09 06 00, SCHEDULE FOR FINISHES or specified.

B. Pressure sensitive adhesive back.

C. Snap on coil plastic markers.

D. Widths as shown on construction documents.

BIOBASED CONTENT

A. Paint products shall comply with following bio-based standards for biobased materials:

Material Type Percent by Weight

Interior Paint 20 percent biobased material

Interior Paint- Oil Based and

Solvent Alkyd

67 percent biobased material

Exterior Paint 20 percent biobased material

Wood & Concrete Stain 39 percent biobased content

Polyurethane Coatings 25 percent biobased content

Water Tank Coatings 59 percent biobased content

Wood & Concrete Sealer-

Membrane Concrete Sealers

11 percent biobased content

Wood & Concrete Sealer-

Penetrating Liquid

79 percent biobased content

B. The minimum-content standards are based on the weight (not the volume) of the material.

PART 3 - EXECUTION

JOB CONDITIONS:

A. Safety: Observe required safety regulations and manufacturer's warning and instructions for storage, handling and application of painting materials.

1. Take necessary precautions to protect personnel and property from hazards due to falls, injuries, toxic fumes, fire, explosion, or other harm.

2. Deposit soiled cleaning rags and waste materials in metal containers approved for that purpose. Dispose of such items off the site at end of each day’s work.

B. Atmospheric and Surface Conditions:

1. Do not apply coating when air or substrate conditions are:

a. Less than 3 degrees C (5 degrees F) above dew point.

09 91 00 - 11

b. Below 10 degrees C (50 degrees F) or over 35 degrees C

(95 degrees F), unless specifically pre-approved by the COR and the product manufacturer. Under no circumstances are application conditions to exceed manufacturer recommendations.

c. When the relative humidity exceeds 85 percent; or to damp or wet surfaces; unless otherwise permitted by the paint manufacturer’s printed instructions.

2. Maintain interior temperatures until paint dries hard.

3. Do no exterior painting when it is windy and dusty.

4. Do not paint in direct sunlight or on surfaces that the sun will warm.

5. Apply only on clean, dry and frost-free surfaces except as follows:

a. Apply water thinned acrylic and cementitious paints to damp (not wet) surfaces only when allowed by manufacturer's printed instructions.

b. Concrete and masonry when permitted by manufacturer’s recommendations, dampen surfaces to which water thinned acrylic and cementitious paints are applied with a fine mist of water on hot dry days to prevent excessive suction and to cool surface.

6. Varnishing:

a. Apply in clean areas and in still air.

b. Before varnishing vacuum and dust area.

c. Immediately before varnishing wipe down surfaces with a tack rag.

INSPECTION:

A. Examine the areas and conditions where painting and finishing are to be applied and correct any conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions are corrected to permit proper installation of the work.

GENERAL WORKMANSHIP REQUIREMENTS:

A. Application may be by brush or roller. Spray application only upon acceptance from the COR in writing.

B. Furnish to the COR a painting schedule indicating when the respective coats of paint for the various areas and surfaces will be completed. This schedule is to be kept current as the job progresses.

C. Protect work at all times. Protect all adjacent work and materials by suitable covering or other method during progress of work. Upon completion of the work, remove all paint and varnish spots from floors, glass and other surfaces. Remove from the premises all rubbish and accumulated

09 91 00 - 12 materials of whatever nature not caused by others and leave work in a clean condition.

D. Remove and protect hardware, accessories, device plates, lighting fixtures, and factory finished work, and similar items, or provide in place protection. Upon completion of each space, carefully replace all removed items by workmen skilled in the trades involved.

E. When indicated to be painted, remove electrical panel box covers and doors before painting walls. Paint separately and re-install after all paint is dry.

F. Materials are to be applied under adequate illumination, evenly spread and flowed on smoothly to avoid runs, sags, holidays, brush marks, air bubbles and excessive roller stipple.

G. Apply materials with a coverage to hide substrate completely. When color, stain, dirt or undercoats show through final coat of paint, the surface is to be covered by additional coats until the paint film is of uniform finish, color, appearance and coverage, at no additional cost to the

Government.

H. All coats are to be dry to manufacturer’s recommendations before applying succeeding coats.

I. All suction spots or “hot spots” in plaster after the application of the first coat are to be touched up before applying the second coat.

J. Do not apply paint behind frameless mirrors that use mastic for adhering to wall surface.

SURFACE PREPARATION:

A. General:

1. The Contractor shall be held wholly responsible for the finished appearance and satisfactory completion of painting work. Properly prepare all surfaces to receive paint, which includes cleaning, sanding, and touching-up of all prime coats applied under other

Sections of the work. Broom clean all spaces before painting is started. All surfaces to be painted or finished are to be completely dry, clean and smooth.

2. See other sections of specifications for specified surface conditions and prime coat.

09 91 00 - 13

3. Perform preparation and cleaning procedures in strict accordance with the paint manufacturer’s instructions and as herein specified, for each particular substrate condition.

4. Clean surfaces before applying paint or surface treatments with materials and methods compatible with substrate and specified finish.

Remove any residue remaining from cleaning agents used. Do not use solvents, acid, or steam on concrete and masonry. Schedule the cleaning and painting so that dust and other contaminants from the cleaning process will not fall in wet, newly painted surfaces.

5. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows:

a. Concrete: 12 percent.

b. Fiber-Cement Board: 12 percent.

c. Masonry (Clay and CMU’s): 12 percent.

d. Wood: 15 percent.

e. Gypsum Board: 12 percent.

f. Plaster: 12 percent.

B. Masonry, Concrete, Cement Board, Cement Plaster and Stucco:

1. Clean and remove dust, dirt, oil, grease efflorescence, form release agents, laitance, and other deterrents to paint adhesion.

2. Use emulsion type cleaning agents to remove oil, grease, paint and similar products. Use of solvents, acid, or steam is not permitted.

3. Remove loose mortar in masonry work.

4. Replace mortar and fill open joints, holes, cracks and depressions with new mortar specified in Section 04 05 13, MASONRY MORTARING //

Section 04 05 16, MASONRY GROUTING //. Do not fill weep holes. Finish to match adjacent surfaces.

5. Neutralize Concrete floors to be painted by washing with a solution of

1.4 Kg (3 pounds) of zinc sulfate crystals to 3.8 L (1 gallon) of water, allow to dry three (3) days and brush thoroughly free of crystals.

6. Repair broken and spalled concrete edges with concrete patching compound to match adjacent surfaces as specified in

Division 03, CONCRETE Sections. Remove projections to level of adjacent surface by grinding or similar methods.

C. Gypsum Plaster and Gypsum Board:

09 91 00 - 14

1. Remove efflorescence, loose and chalking plaster or finishing materials.

2. Remove dust, dirt, and other deterrents to paint adhesion.

3. Fill holes, cracks, and other depressions with CID-A-A-1272A finished flush with adjacent surface, with texture to match texture of adjacent surface. Patch holes over 25 mm (1-inch) in diameter as specified in

Section for plaster or gypsum board.

PAINT PREPARATION:

A. Thoroughly mix painting materials to ensure uniformity of color, complete dispersion of pigment and uniform composition.

B. Do not thin unless necessary for application and when finish paint is used for body and prime coats. Use materials and quantities for thinning as specified in manufacturer's printed instructions.

C. Remove paint skins, then strain paint through commercial paint strainer to remove lumps and other particles.

D. Mix two (2) component and two (2) part paint and those requiring additives in such a manner as to uniformly blend as specified in manufacturer's printed instructions unless specified otherwise.

E. For tinting required to produce exact shades specified, use color pigment recommended by the paint manufacturer.

APPLICATION:

A. Start of surface preparation or painting will be construed as acceptance of the surface as satisfactory for the application of materials.

B. Unless otherwise specified, apply paint in three (3) coats; prime, body, and finish. When two (2) coats applied to prime coat are the same, first coat applied over primer is body coat and second coat is finish coat.

C. Apply each coat evenly and cover substrate completely.

D. Allow not less than 48 hours between application of succeeding coats, except as allowed by manufacturer's printed instructions, and approved by

COR.

E. Apply by brush or roller. Spray application for new or existing occupied spaces only upon approval by acceptance from COR in writing.

1. Apply painting materials specifically required by manufacturer to be applied by spraying.

2. In new construction and in existing occupied spaces, where paint is applied by spray, mask or enclose with polyethylene, or similar air tight material with edges and seams continuously sealed including items

09 91 00 - 15 specified in “Building and Structural Work Field Painting”; “Work not

Painted”; motors, controls, telephone, and electrical equipment, fronts of sterilizes and other recessed equipment and similar prefinished items.

F. Do not paint in closed position operable items such as access doors and panels, window sashes, overhead doors, and similar items except overhead roll-up doors and shutters.

PRIME PAINTING:

A. After surface preparation, prime surfaces before application of body and finish coats, except as otherwise specified.

B. Spot prime and apply body coat to damaged and abraded painted surfaces before applying succeeding coats.

C. Additional field applied prime coats over shop or factory applied prime coats are not required except for exterior exposed steel apply an additional prime coat.

D. Gypsum Board and Hardboard:

1. Surfaces scheduled to have MPI 10 (Exterior Latex, Flat) MPI 11

(Exterior Latex, Semi-Gloss) MPI 119 (Exterior Latex, High Gloss

(acrylic)) MPI 53 (Interior Latex, Flat) , MPI Gloss Level 1 MPI 52

(Interior Latex, MPI Gloss Level 3) MPI 54 (Interior Latex, Semi-

Gloss, MPI Gloss Level 5) MPI 114 (Interior Latex, Gloss) finish: Use

MPI 10 (Exterior Latex, Flat) MPI 11 (Exterior Latex, Semi-Gloss) MPI

119 (Exterior Latex, High Gloss (acrylic)) MPI 53 (Interior Latex, MPI

Gloss Level 3) MPI 52 (Interior Latex, MPI Gloss Level 3) MPI 54

(Interior Latex, Semi-Gloss, MPI Gloss Level 5) MPI 114 (Interior

Latex, Gloss) respectively.

2. Primer: MPI 50 (Interior Latex Primer Sealer) except use MPI 45

(Interior Primer Sealer) MPI 46 (Interior Enamel Undercoat) in shower and bathrooms.

3. Surfaces scheduled to receive vinyl coated fabric wall covering:

a. Use MPI 45 (Interior Primer Sealer) MPI 46 (Interior Enamel

Undercoat).

b. Use MPI 101 (Cold Curing Epoxy Primer) for surfaces scheduled to receive MPI 77 (Epoxy Cold Cured, Gloss) MPI 98 (High Build Epoxy

Coating) MPI 108 (High Build Epoxy Marine Coating) finish.

09 91 00 - 16

E. Gypsum Plaster and Veneer Plaster:

1. Surfaces scheduled to receive vinyl coated fabric wall covering: Use

MPI 45 (Interior Primer Sealer).

2. MPI 45 (Interior Primer Sealer), except use MPI 50 (Interior Latex

Primer Sealer) when an alkyd flat finish is specified.

3. Surfaces scheduled to have MPI 10 (Exterior Latex, Flat) MPI 11

(Exterior Latex, Semi-Gloss) MPI 119 (Exterior Latex, High Gloss

(acrylic)) MPI 53 (Interior Latex, Flat, MPI Gloss Level 1) MPI 52

(Interior Latex, MPI Gloss Level 3) MPI 54 (Interior Latex, Semi-Gloss, MPI Gloss Level 5) MPI 114 (Interior Latex, Gloss) finish: Use MPI 10

(Exterior Latex, Flat) MPI 11 (Exterior Latex, Semi-Gloss) MPI 119

(Exterior Latex, High Gloss (acrylic)) MPI 53 (Interior Latex, Flat, MPI Gloss Level 1) MPI 52 Latex, MPI Gloss Level 3) MPI 54 (Interior

Latex, Semi-Gloss, MPI Gloss Level 5) MPI 114 (Interior Latex, Gloss) respectively.

INTERIOR FINISHES:

A. Apply following finish coats over prime coats in spaces or on surfaces specified in Section 09 06 00, SCHEDULE FOR FINISHES.

B. Gypsum Board:

1. One (1) coat of MPI 45 (Interior Primer Seale MPI 46 (Interior Enamel

Undercoat) plus one (1) coat of MPI 139 (Interior HighPerformance

Latex, MPI Gloss level 3).

2. Two (2) coats of MPI 138 (Interior HighPerformance Latex, MPI Gloss

Level 2).

3. One (1) coat MPI 45 (Interior Primer Sealer) MPI 46 (Interior Enamel

Undercoat) plus one (1) coat of MPI 54 (Interior Latex, Semi-Gloss, MPI

Gloss Level 5) or MPI 114 (Interior Latex, Gloss).

4. One (1) coat of MPI 45 (Interior Primer Sealer) MPI 46 (Interior Enamel

Undercoat) plus one (1) coat of MPI 48 (Interior Alkyd Gloss).

C. Plaster:

1. One (1) coat of MPI 45 (Interior Primer Sealer) MPI 46 (Interior

Enamel Undercoat MPI 50 (Interior Latex Primer Sealer) plus one (1) coat of MPI 139 (Interior HighPerformance Latex, MPI Gloss level 3).

2. Two (2) coats of MPI 51 (Interior Alkyd, Eggshell).

3. One (1) coat of MPI 45 (Interior Primer Sealer) MPI 46 (Interior

Enamel Undercoat) or MPI 50 (Interior Latex Primer Sealer) plus one (1) coat of 139 (Interior HighPerformance Latex, MPI Gloss level 3).

09 91 00 - 17

4. One (1) coat MPI 101 (Cold Curing Epoxy Prime).

D. Miscellaneous:

1. Apply where specified in Section 09 06 00, SCHEDULE FOR FINISHES.

2. MPI 1 (Aluminum Paint): Two (2) coats of aluminum paint.

3. Existing acoustical units scheduled to be repainted except acoustical units with a vinyl finish:

a. Clean units free of dust, dirt, grease, and other deterrents to paint adhesion.

b. Mineral fiber units: One (1) coat of MPI 53 (Interior Latex, Flat, MPI Gloss Level 1) MPI 52 (Interior Latex, MPI Gloss Level 3) MPI 54

(Interior Latex, Semi-Gloss, MPI Gloss Level 5) MPI 114 (Interior

Latex, Gloss).

c. Units of organic fiber or other material not having a class A rating: One (1) coat of MPI 66 (Interior Alkyd Fire Retardant, Clear Top-Coat (UL Approved)) MPI 67 (Interior Latex Fire Retardant, Top-Coat (UL Approved)) fire retardant paint.

4. Interstitial floor markings: One (1) coat MPI 27 (Exterior/ Interior

Alkyd Floor Enamel, Gloss) MPI 59 ((Interior/ Exterior Alkyd Porch &

Floor Enamel, Low Gloss) MPI 68 (Interior/ Exterior Latex Porch & Floor

Paint, Gloss) MPI 60 (interior/ Exterior Latex Porch & Floor Paint, Low

Gloss.

REFINISHING EXISTING PAINTED SURFACES:

A. Clean, patch and repair existing surfaces as specified under “Surface

Preparation”. No “telegraphing” of lines, ridges, flakes, etc., through new surfacing is permitted. Where this occurs, sand smooth and re-finish until surface meets with COR’s approval.

B. Remove and reinstall items as specified under “General Workmanship

Requirements”.

C. Remove existing finishes or apply separation coats to prevent non compatible coatings from having contact.

D. Patched or Replaced Areas in Surfaces and Components: Apply spot prime and body coats as specified for new work to repaired areas or replaced components.

E. Except where scheduled for complete painting apply finish coat over plane surface to nearest break in plane, such as corner, reveal, or frame.

F. In existing rooms and areas where alterations occur, clean existing stained and natural finished wood retouch abraded surfaces and then give

09 91 00 - 18 entire surface one (1) coat of // MPI 31 (Polyurethane, Moisture Cured, Clear Gloss) MPI 71 (Polyurethane, Moisture Cured, Clear Flat) //.

G. Refinish areas as specified for new work to match adjoining work unless specified or scheduled otherwise.

H. Coat knots and pitch streaks showing through old finish with MPI 36 (Knot

Sealer) before refinishing.

I. Sand or dull glossy surfaces prior to painting.

J. Sand existing coatings to a feather edge so that transition between new and existing finish will not show in finished work.

PAINT COLOR:

A. Color and gloss of finish coats is specified in Section 09 06 00, SCHEDULE

FOR FINISHES.

B. For additional requirements regarding color see Articles, “REFINISHING

EXISTING PAINTED SURFACE” and “MECHANICAL AND ELECTRICAL FIELD PAINTING

SCHEDULE”.

C. Coat Colors:

1. Color of priming coat: Lighter than body coat.

2. Color of body coat: Lighter than finish coat.

3. Color prime and body coats to not show through the finish coat and to mask surface imperfections or contrasts.

D. Painting, Caulking, Closures, and Fillers Adjacent to Casework:

1. Paint to match color of casework where casework has a paint finish.

2. Paint to match color of wall where casework is stainless steel, plastic laminate, or varnished wood.

IDENTITY PAINTING SCHEDULE:

A. Identify designated service in new buildings or projects with extensive remodeling in accordance with ASME A13.1, unless specified otherwise, on exposed piping, piping above removable ceilings, piping in accessible pipe spaces, interstitial spaces, and piping behind access panels. For existing spaces where work is minor match existing.

1. Legend may be identified using snap-on coil plastic markers or by paint stencil applications.

2. Apply legends adjacent to changes in direction, on branches, where pipes pass through walls or floors, adjacent to operating accessories such as valves, regulators, strainers and cleanouts a minimum of 12.2 M

(40 feet) apart on straight runs of piping. Identification next to plumbing fixtures is not required.

09 91 00 - 19

3. Locate Legends clearly visible from operating position.

4. Use arrow to indicate direction of flow using black stencil paint.

5. Identify pipe contents with sufficient additional details such as temperature, pressure, and contents to identify possible hazard. Insert working pressure shown on construction documents where asterisk appears for High, Medium, and Low Pressure designations as follows:

a. High Pressure - 414 kPa (60 psig) and above.

b. Medium Pressure - 104 to 413 kPa (15 to 59 psig).

c. Low Pressure - 103 kPa (14 psig) and below.

d. Add Fuel oil grade numbers.

6. Legend name in full or in abbreviated form as follows:

COLOR OF COLOR OF COLOR OF LEGEND

PIPING EXPOSED PIPING BACKGROUND LETTERS ABBREVIATIONS

Blow-off Green White Blow-off

Boiler Feedwater Green White Blr Feed

A/C Condenser Water

Supply Green White A/C Cond Wtr Sup

A/C Condenser Water

Return Green White A/C Cond Wtr Ret

Chilled Water Supply Green White Ch. Wtr Sup

Chilled Water Return Green White Ch. Wtr Ret

Shop Compressed Air Blue White Shop Air

Air-Instrument Controls Green White Air-Inst Cont

Drain Line Green White Drain

Emergency Shower Green White Emg Shower

High Pressure Steam Green White H.P. ______*

High Pressure Condensate

Return Green White H.P. Ret ____*

Medium Pressure Steam Green White M. P. Stm ____*

Medium Pressure Condensate

Return Green White M.P. Ret _____*

Low Pressure Steam Green White L.P. Stm _____*

Low Pressure Condensate

Return Green White L.P. Ret _____*

High Temperature Water

Supply Green White H. Temp Wtr Sup

High Temperature Water

Return Green White H. Temp Wtr Ret

Hot Water Heating Supply Green White H. W. Htg Sup

Hot Water Heating Return Green White H. W. Htg Ret

Gravity Condensate Return Green White Gravity Cond Ret

09 91 00 - 20

Pumped Condensate Return Green White Pumped Cond Ret

Vacuum Condensate Return Green White Vac Cond Ret

Fuel Oil - Grade // // Brown White Fuel Oil-Grade // //

(Diesel Fuel included under Fuel Oil)

Boiler Water Sampling Green White Sample

Chemical Feed Green White Chem Feed

Continuous Blow-Down Green White Cont. B D

Pumped Condensate Green White Pump Cond

Pump Recirculating Green White Pump-Recirc.

Vent Line Green White Vent

Alkali Orange Black Alk

Bleach Orange Black Bleach

Detergent Yellow Black Det

Liquid Supply Yellow Black Liq Sup

Reuse Water Yellow Black Reuse Wtr

Cold Water (Domestic) White Green White C.W. Dom

Hot Water (Domestic)

Supply White Yellow Black H.W. Dom

Return White Yellow Black H.W. Dom Ret

Tempered Water White Yellow Black Temp. Wtr

Ice Water

Supply White Green White Ice Wtr

Return White Green White Ice Wtr Ret

Reagent Grade Water Green White RG

Reverse Osmosis Green White RO

Sanitary Waste Green White San Waste

Sanitary Vent Green White San Vent

Storm Drainage Green White St Drain

Pump Drainage Green White Pump Disch

Chemical Resistant Pipe

Waste Orange Black Acid Waste

Vent Orange Black Acid Vent

Atmospheric Vent Green White ATV

Silver Recovery Green White Silver Rec

Oral Evacuation Green White Oral Evac

Fuel Gas Yellow Black Gas

Fire Protection Water

Sprinkler Red Red White Auto Spr

Standpipe Red Red White Stand

Sprinkler Red Red White Drain

B. Fire and Smoke Partitions:

09 91 00 - 21

1. Identify partitions above ceilings on both sides of partitions except within shafts in letters not less than 64 mm (2 1/2 inches) high.

2. Stenciled message: "SMOKE BARRIER" or, "FIRE BARRIER" as applicable.

3. Locate not more than 6096 mm (20 feet) on center on corridor sides of partitions, and with a least one (1) message per room on room side of partition.

4. Use semi-gloss paint of color that contrasts with color of substrate.

C. Identify columns in pipe basements and interstitial space:

1. Apply stenciled number and letters to correspond with grid numbering and lettering indicated on construction documents.

2. Paint numbers and letters 101 mm (4 inches) high, locate 45 mm

(18 inches) below overhead structural slab.

3. Apply on four (4) sides of interior columns and on inside face only of exterior wall columns.

4. Color:

a. Use black on concrete columns.

b. Use white or contrasting color on steel columns.

PROTECTION CLEAN UP, AND TOUCH-UP:

A. Protect work from paint droppings and spattering by use of masking, drop cloths, removal of items or by other approved methods.

B. Upon completion, clean paint from hardware, glass and other surfaces and items not required to be painted of paint drops or smears.

C. Before final inspection, touch-up or refinished in a manner to produce solid even color and finish texture, free from defects in work which was damaged or discolored.

- - - E N D - - -

File details come from the government source that posted it. Updated .