This document is an Amendment (#0002) to a VA Solicitation for a Mill and Fill Project at Northport VA Medical Center. The solicitation (36C24225B0009) involves milling and repaving approximately 145,000 square feet across three parking lots (A, C, and Q), including asphalt removal, installation of new 3-inch asphalt in two lifts (1.5" binder and 1.5" top layer), concrete work, sidewalk installation, curb replacement, and new striping. The project requires SuperPave asphalt, 4-inch sidewalks with wire mesh, and 6" x 18" curbs with specific rebar configurations.

Key amendment details include extending the bid due date to March 25, 2025, at 10:00 AM EDT, and providing detailed responses to 24 contractor questions about work specifications, site conditions, and project requirements. The work is to be completed in 15 calendar days, with most work occurring during standard business hours (Monday-Friday, 8 AM-5 PM), except for Parking Lot Q, which can be worked on from Friday 5 PM to Sunday 5 AM. The project includes specific safety precautions, environmental controls, and requires contractors to have VA-issued PIV badges. Add alternates include 8 ADA curb ramps and potential base repairs.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer) 632-25-001 36C242 Department of Veterans Affairs Network Contracting Office 2 James J. Peters VA Medical Center 130 West Kingsbridge Road Bronx

NY

10468-3904 36C242 Department of Veterans Affairs James J. Peters VA Medical Center Network Contracting Office 2 130 West Kingsbridge Road Bronx

NY

10468-3904 To all Offerors/Bidders

36C24225B0009 02-12-2025

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 03-25-2025 10:00 EDT X The purpose for Amendment #0002 is the for the following:

1. To answer RFI's from industry.

2. To extend the IFB due date to March 25, 2024, at 10:00am.

Vladimir Stoyanov Contracting Officer RFI Responses

1. time frame and possible extension of time As per notes on solicitation this scope of work is to be completed on weekends starting from Friday 7pm, Can we work throughout the weekend 2-3 shifts? what are the allowable hours of work?

· For parking lot “Q,” you can work throughout the entire weekend, starting on Friday 5:00PM – Sunday 5:00AM.

Will there be any extension of the time frame?

· We can extend based on what you might propose if current timeframe is not realistic.

Will the three (3) lots be available at the same time and for the duration of the project?

· As per the scope of work, “All work can be completed during normal business hours of Monday – Friday 8:00AM – 5:00PM except for Parking Lot “Q,” which is to be completed from Friday 5:00PM – Sunday 5:00AM.”

· Each parking lot will be done in separate phases.

2. sidewalk and curd details and specs throughout all three (3) lots Can you provide details and specs for the sidewalk? PCI of the concrete? Wire mesh or not? Thickness?? Any bedding??

· Sidewalk thickness is 4-inch. Match existing. 6 x 6 – W2.9 x W2.9 wire welded fabric. Use RCA to level out the elevation for the bottom of the sidewalk. See attached for sidewalk detail.

Can you provide any details and specs for the curbs? Hight above and below ground? Rebar? PCI of concrete?

· 6” x 18” One #5 continuous rebar at the top of the curb attached to a #4 at 24” vertical dowel. See attached for curb detail.

3. LOT C- proposed new concrete sidewalk Proposed new sidewalk will be about 8-12” below existing soil grade. Is there any detail that will address the difference in elevation? Grade the remaining of the area? Install knee wall?

· Grade the remaining area.

Fire Hydrant relocation – will be performed by FD, or should we include it in our scope?? Who is doing the shut off? Any requirements by Fire Department for alternating the location of this Fire Hydrant??

· FD will be doing the shut off but will not be doing the relocation. Please include in your scope. The requirements for alternative/relocating the fire hydrant will be to push it back to enable enough space for a new sidewalk.

4. - Curb replacement at lot C

Curb replacement at the above area of lot C will most probably damage/deteriorate further the sidewalk. Should we provide allowance for this sidewalk repair??

· Yes, as part of the add alternative for curb replacement.

5. - Base repair allowance As we pointed out on the walkthrough, the base below the top layer of asphalt seems to be damaged on few areas throughout the three (3) lots, Would there be any allowance for base repair or will be issued as a change order?

· Please add an allowance for base repair.

6. If our bonding capacity is not sufficient, can we utilize our subcontractor's bonding capacity to meet the bonding requirements?

· No, this should come from the Primary contractor.

7. The sidewalk thickness is not specified in the documents. Typically, it is 4". Can you confirm the required thickness for this project?

a. Sidewalk thickness is 4-inch. Match existing. 6 x 6 – W2.9 x W2.9 wire welded fabric.

8. Could you provide the dimensions for the curb?

a. 6” x 18” One #5 continuous rebar at the top of the curb attached to a #4 at 24” vertical dowel.

9. The striping quantities are listed, but since milling and paving will remove all existing striping, does the scope include full removal and replacement of all parking lot striping?

a. Yes, the scope include full removal and replacement of all parking lot striping.

10. For Parking Lot Q are the curb ramps part of the base bid or add alternates? 4’ ADA Curb ramp – 7 each. 8’ ADA Curb ramp - 1 each

a. Add alternates.

11. If above items are part of add alternates, we do not have separate line item in the bid form provided with amendment # 1. Also no description available for add alternates in the bid documents. Please advise.

a. Contracting, please advise or alter the bid document to allow contractor to show add-alternates.

12. Do you have any details on the sidewalk?

a. Sidewalk thickness is 4-inch. Match existing. 6 x 6 – W2.9 x W2.9 wire welded fabric.

13. What do you mean by crosswalk? Sidewalk? Concrete? Asphalt? Just crosswalk striping?

a. Crosswalk referenced in parking lot “C” is just a crosswalk striping.

14. You are having us remove concrete – what is the depth of concrete in these areas?

a. Depth is unknown at this time. Please field verify.

15. Are you looking for us to provide line striping for each parking lot? Once we mill and overlay the lots will need to be restriped?

a. Yes. After the job is complete, all new striping must match what is there now.

16. On the Google Earth drawing for parking lot A, it says 150 LF of striping. That is not the entire lot, so I am confused at to what you are looking for. The same for parking lot C and Q.

a. For parking lot A, 150LF means that the space spans 150 feet. This 150 feet is not currently stripped. This will be new striping. The spacing in between each new strip shall match existing space between other striping in same lot.

b. For parking lot C, “new striping” refers to crosswalk striping.

c. Parking Lot Q does not mention any new striping from what is existing. This means that all new stripping must be replaced with what is currently existing.

17. Are you looking for line striping for parking lot Q? It doesn’t state it on the drawing.

a. Yes, as mentioned in the scope of work, “In addition, the striping of the roads, including the striping of the cross sections of roads/parking lot striping, in-kind striping to what is existing.” This means that the existing striping must remain. Obviously, you will remove them, mill and fill, and then strip new to match existing striping layout.

18. Do you have details for the concrete pad? What is the depth of concrete? Is there rebar?

a. Dumpster concrete pad is 10’x12’x10”Thick, compressive strength 5000 psi with #5 at 10” top and bottom. Provide a perimeter haunch to a depth of 18 inches.

19. Can you provide any clarification on the mill and fill scope. We see they mention mill 3" and replace 3" for the roadway but I don't see what they are looking for in the parking lots? Also depths on the binder and top?

a. The parking lot will have the same 3” or match existing roadside thickness.

20. Please provide site visit roster.

a. See attached.

21. Can the Site Superintendent serve as Site Superintendent, Quality Assurance Manager, and Safety Manager?

a. Yes.

22. Documents says 3" of asphalt, is this 3" compacted? Is it one lift or two lifts?

a. We will be using two lifts, scarify 1-1/2” binder course with a 1-1/2” top layer.

23. Also I am seeing that it is SuperPave Asphalt- can you confirm this?

a. Correct.

24. Project duration 15 calendar days is not enough time. Need at least 2 weeks cure time before seal coast new asphalt. Also need cure time on concrete before try to roll against it. Please advise.

a. We can accommodate to what’s realistic. Please provide a timeline.

See attached document: Sidewalk Detail.

See attached document: Curb Detail.

See attached document: Mill and Fill_Site Visit for Solicitation - Attendance 02.25.25.