AA-100.pdf
PDF 625 KB Posted
- Attached to
- Z1DA--528-18-109 WARD 9C RENOVATIONS
- Solicitation number
- 36C24222B0069
About this file
This document includes plans and specifications for an asbestos abatement project at a Veterans Affairs Medical Center. The project involves removing and disposing of asbestos insulation from piping and radiator heat shields located throughout the 9th floor as well as limited areas on the 7th and 8th floors. The contractor must follow all applicable federal and state regulations for asbestos abatement work. Precautions must be taken to isolate the work areas, establish negative air pressure, and properly remove and dispose of asbestos-containing materials. The project will be conducted in phases to avoid disturbing occupied areas of the facility. The solicitation number for this opportunity is 36C24222B0069 and it was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 2 for a renovation project located at the Buffalo VAMC.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AA-102.pdf | ||
| A-406.pdf | ||
| AD-102.pdf | ||
| A-604.pdf | ||
| A-405.pdf | ||
| AA-101.pdf | ||
| A-404.pdf | ||
| AD-100.pdf | ||
| A-109.pdf | ||
| 117300.pdf | ||
| A-108.pdf | ||
| 36C24222B0069 0005.docx | DOCX document | |
| 36C24222B0069 0004.docx | DOCX document | |
| Abatement Ward 9c Report.pdf | ||
| 36C24222B0069 0003.docx | DOCX document | |
| 36C24222B0069 0002.docx | DOCX document | |
| 36C24222B0069 0001.docx | DOCX document | |
| 528-18-109 Pre Bid Attendance.pdf | ||
| SPECS 3.pdf | ||
| 36C24222B0069_1.docx | DOCX document | |
| SPECS 1.pdf | ||
| WAGE RATE.pdf | ||
| LIMITATION ON SUBCONTRACTING.docx | DOCX document | |
| SPECS 2.pdf | ||
| 528-18-109_9C DRAWINGS.pdf | ||
| FAR 52.225-2 Buy American Certification.docx | DOCX document |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROPERLY REMOVE AND DISPOSE OF THE
RECESSED RADIATOR HEAT SHIELD AND
ALL ASBESTOS INSULATION ON THE BACK
OF THE SHIELD. REMOVE ALL INSULATION
ON ANY PIPING. THE SHIELD AND ALL
INSULATION SHALL BE REMOVED AND
DISPOSED OF AS ASBESTOS-WASTE.
REMOVE EXISTING
COVER. REFER TO
DRAWING M-100.
REMOVE AND
PROPERLY DISPOSE
OF ALL INSULATION
ON EXISTING STEAM
RISERS WITHIN
EXTERIOR WALL
CAVITY. INSULATION
IS ASSUMED TO BE
ASBESTOS-CONTAINING.
NO INSULATION
SHALL REMAIN.
EL
PS
EL
PR
FINISHED FLOOR
EXISTING
WINDOW
REMOVE EXISTING BRANCH LPS & LPR PIPING TO THE EXTENT
SHOWN INCLUDING STEAM TRAP AND CONTROL VALVE. REFER
TO DRAWING M-100.
(CONTRACTOR SHALL ASSUME THAT CONCEALED LPS &
LPR PIPING IS COVERED WITH ASBESTOS INSULATION)
TYPICAL ELEVATION VIEW
EXISTING EXTERIOR
WALL
D C B A
D C B A
DD
C.1
5.1
EFGH
CC
BB
AA
13 13
1/8" = 1'-0"1
7TH FLOOR ASBESTOS ABATEMENT PLAN
ASBESTOS ABATEMENT NOTES
AA-1 NOT USED
AA-2 NOT USED
AA-3 NOT USED
AA-4 NOT USED
AA-5 CONTRACTOR SHALL REMOVE AND PROPERLY DISPOSE OF THE ASBESTOS-CONTAINING RED-BROWN MASTIC ON THE NON-ASBESTOS-CONTAINING CORK PIPE
INSULATION. CONTRACTOR SHALL BE RESPONSIBLE FOR THE DEMOLITION OF SUSPENDED CEILINGS TO ACCESS THE MASTIC.
AA-6 NOT USED
AA-7 NOT USED
AA-8 CONTRACTOR SHALL REMOVE AND PROPERLY DISPOSE OF ALL ASBESTOS-CONTAINING PIPE AND MUD FITTING INSULATION THAT IS WITHIN WALL CHASES TO ACCOMMODATE ALL DEMOLITION, REMOVAL, AND INSTALLATION OF PIPING AND HVAC DUCTWORK. REFER TO PLUMBING AND MECHANICAL PLANS FOR APPROXIMATE LOCATIONS OF NEW PIPING AND DUCTS. ALL INSULATION AND PIPING WITHIN DESIGNATED CHASES SHALL BE REMOVED WITHIN THE REGULATED ASBESTOS ABATEMENT WORK AREA. CLEAN
CHASES TO ALLOW FOR INSTALLATION OF NEW PIPING AND DUCTWORK.
AA-9 NOT USED
AA-10 CONTRACTOR SHALL CONDUCT CEILING DEMOLITION WITHIN PROJECT LIMITS AND REMOVE AND PROPERLY DISPOSE OF ALL ASBESTOS-CONTAINING PIPE AND
MUD FITTING INSULATION THAT IS ABOVE CEILINGS THAT BECOME ACCESSIBLE AS A RESULT OF THE DEMOLITION/RENOVATION WORK. ALL CEILING
DEMOLITION SHALL OCCUR UNDER NEGATIVE PRESSURE WITHIN THE REGULATED ASBESTOS ABATEMENT WORK AREA. REFER TO ARCHITECTURAL
DEMOLITION PLANS FOR LIMITS OF CEILING DEMOLITION. ALL PIPE INSULATION, HARD CEILINGS, SUSPENDED CEILINGS AND ASSOCIATED SUPPORT GRID, AND
ASSOCIATED DEBRIS SHALL BE DISPOSED OF AS ASBESTOS-WASTE.
NORTH
KEY PLAN
C D
A B
0' 4' 8' 16' 32'
1/8" = 1'-0"
DRAWING NOTES
A. THERE IS AN ASBESTOS-CONTAINING INSULATION BOARD BEHIND THE RECESSED RADIATOR HEAT SHIELDS. ONLY THE RECESSED RADIATORS ON THE NINTH FLOOR ARE TO BE
DISTURBED. THE RADIATORS CAN ONLY BE SHUT DOWN DURING THE NON-HEATING SEASON. CAREFULLY COORDINATE WORK TO PERFORM THE REQUIRED ABATEMENT DURING THE
NON-HEATING PERIODS. ALL OTHER RADIATORS SHALL NOT BE REMOVED OR DISTURBED.
B. THERE IS AN ASBESTOS-CONTAINING BLACK PAPER AND TAR COVERING THE COPPER FLASHING BELOW THE WINDOWS. THE MATERIAL IS NOT SCHEDULED TO BE DISTURBED AS A
RESULT OF THIS PROJECT.
C. ALL CEILINGS WITHIN THE NINTH FLOOR PROJECT LIMITS SHALL BE DEMOLISHED. LIMITED CEILING DEMOLITION IS SCHEDULED TO TAKE PLACE ON THE EIGHTH FLOOR DIRECTLY
BELOW THE NINTH FLOOR TO REMOVE AND REPLACE THE WASTE PIPING AND TO PERFORM TIE-INS TO THE PLUMBING AND MECHANICAL LINES ASSOCIATED WITH THE NINTH FLOOR
RENOVATIONS. THERE IS ASBESTOS INSULATION ON THE HEATING AND DOMESTIC WATER LINES AND ASBESTOS DEBRIS ABOVE ALL HARD CEILINGS. CONTRACTOR SHALL ASSUME
THERE WILL BE SOME ABATEMENT WORK AT EACH RISER LOCATION ON THE EIGHTH FLOOR WHERE NEW CONNECTIONS WILL BE MADE FOR THE SANITARY LINES. THE CEILING TILES
AND CEILING PLASTER IN THE BUILDING DO NOT CONTAIN ASBESTOS AND THE WASTE PIPING IS NOT INSULATED. DEMOLITION OF CEILING AND REMOVAL OF ANY PLUMBING OR
WASTE PIPING ABOVE CEILINGS MUST BE CONDUCTED AS AN ASBESTOS PROJECT.
D. REFER TO MECHANICAL DEMOLITION DRAWINGS MD-101 AND MD-102 AND PLUMBING DEMOLITION DRAWINGS PD-100, PD-101, AND PD-102 FOR ADDITIONAL INFORMATION REGARDING
THE LOCATION OF ASBESTOS INSULATED PIPING. REFER TO ARCHITECTURAL DEMOLITION DRAWINGS FOR EXTENTS OF DEMOLITION.
E. REFER TO DRAWINGS G-005 THROUGH G-009 FOR REQUIREMENTS PERTAINING TO LIFE SAFETY MEASURES AND TO COORDINATE PHASING OF THE WORK.
F. REFER TO THE RECORD DRAWINGS THAT HAVE BEEN INCLUDED WITH THE BID DOCUMENTS FOR ADDITIONAL INFORMATION REGARDING THE LOCATION OF PLUMBING AND STEAM
LINES THAT MAY BE COVERED WITH ASBESTOS INSULATION. ASSUME ALL HOT AND COLD WATER LINES AND STEAM LINES HAVE ASBESTOS INSULATION. THE RECORD DRAWINGS
HAVE BEEN INCLUDED FOR REFERENCE ONLY.
G. REFER TO ARCHITECTURAL DRAWINGS FOR CEILING TYPES.
H. THE ABATEMENT WORK WILL OCCUR IN PHASES. REFER TO DRAWING G-005 AND G-006 FOR PHASING PLANS. ALL DEMOLITION OF CEILINGS AND WALL CHASES SHALL BE PERFORMED
WHILE THE ABATEMENT CONTRACTOR IS ON SITE AND THE AREA IS UNDER NEGATIVE PRESSURE. ABATEMENT CONTRACTOR SHALL VERIFY THAT ALL AREAS WHERE ASBESTOS PIPE
INSULATION MAY BE PRESENT, I.E. INSIDE WALL CHASES AND COLUMNS, IS REMOVED PRIOR TO THE ABATEMENT CONTRACTOR DEMOBILIZING.
I. ALL SHUT DOWNS MUST BE APPROVED BY VAMC FACILITIES DEPARTMENT PRIOR TO IMPLEMENTATION.
GENERAL NOTES
A. CONTRACTOR SHALL PERFORM ALL WORK IN STRICT ACCORDANCE WITH ALL APPLICABLE FEDERAL AND STATE RULES, REGULATIONS, GUIDELINES AND THE
CONTRACT DOCUMENTS.
B. ALL MATERIAL MEASUREMENTS AND/OR QUANTITIES AND LOCATIONS ARE APPROXIMATE AND FOR GENERAL ORIENTATION ONLY. CONTRACTOR IS RESPONSIBLE
FOR FIELD VERIFICATION OF EXISTING CONDITIONS PRIOR TO BIDDING.
C. THE LOCATION OF ANY SITE STORAGE OF MATERIAL, EQUIPMENT, AND WASTE TRAILER/DUMPSTER SHALL BE COORDINATED WITH AND APPROVED BY THE
RESIDENT ENGINEER.
D. CONTRACTOR IS RESPONSIBLE FOR ALL TOOLS, EQUIPMENT AND SUPPLIES.
E. CONTRACTOR IS RESPONSIBLE FOR KEEPING THE WORK AREA IN A CLEAN AND SAFE CONDITION. CONTRACTOR SHALL ENSURE THAT UNCERTIFIED PERSONNEL
OR UNAUTHORIZED VISITORS DO NOT ENTER ACTIVE WORK AREAS AT ANY TIME.
F. THE REMOVAL OR DISTURBANCE OF ANY ASBESTOS-CONTAINING MATERIAL SHALL BE PERFORMED BY A NYS LICENSED ASBESTOS ABATEMENT CONTRACTOR.
REFER TO SPECIFICATION SECTIONS 028213.13 AND 028213.19 FOR ADDITIONAL REQUIREMENTS FOR THE REMOVAL OF ASBESTOS-CONTAINING MATERIALS.
G. THE CONSTRUCTION AREA SHALL BE COMPLETELY SEPARATED FROM OTHER PORTIONS OF THE BUILDING BY USING TEMPORARY CONSTRUCTION DETAILS AS
SHOWN ON DRAWING G-005.
H. NEGATIVE PRESSURE SHALL BE ESTABLISHED INSIDE THE INTERIOR WORK AREA(S) PRIOR TO THE DISTURBANCE OF ANY ASBESTOS-CONTAINING MATERIAL.
ROUTING OF THE NEGATIVE AIR EXHAUST DUCT SHALL BE DECIDED UPON AFTER CONSULTATION WITH VAMC AND VAMC'S REPRESENTATIVE.
I. CONTRACTOR SHALL COORDINATE THE REMOVAL OF THE ASBESTOS WASTE MATERIALS FROM THE BUILDING WITH VAMC AND VAMC'S REPRESENTATIVE. THE
REMOVAL OF THE ASBESTOS WASTE SHALL BE PERFORMED AT TIMES WHEN IT DOES NOT INTERFERE WITH NORMAL FACILITY ACTIVITIES.
J. ALL ASBESTOS-CONTAINING MATERIAL SHALL BE PROPERLY PACKAGED PRIOR TO BEING REMOVED FROM THE WORK AREA. ASBESTOS WARNING LABELS SHALL
BE APPLIED TO THE ASBESTOS WASTE BAGS. ALL ASBESTOS MATERIALS THAT ARE REMOVED FROM THE SITE SHALL BE ACCOMPANIED BY A WASTE SHIPMENT
RECORD. THE COMPLETED WASTE SHIPMENT RECORDS MUST BE PROVIDED TO THE VAMC AS PART OF THE CLOSEOUT DOCUMENTATION. ALL ORIGINAL WASTE
SHIPMENT RECORDS MUST BE PROVIDED WITHIN 35 DAYS OF THE WASTE LEAVING THE SITE.
K. CONTRACTOR SHALL CLEAN ALL AREAS OUTSIDE THE WORK AREA AND ANY AREAS WHERE CONTRACTOR'S PERSONNEL TRAVEL THROUGH THE BUILDING. THESE
AREAS SHALL BE LEFT IN A CONDITION AS CLEAN AS OR CLEANER THAN WHEN THE CONTRACTOR ARRIVED ON SITE.
L. THE OTHER THREE WINGS ON THE 9TH FLOOR AND WING C ON THE 7TH, 8TH AND 10TH FLOORS WILL REMAIN OCCUPIED DURING THE ABATEMENT PROJECT.
THEREFORE, ALL ABATEMENT WORK, INCLUDING PREPARATION, MUST BE PERFORMED OFF HOURS, EITHER AT NIGHT OR ON THE WEEKEND. WORK SHALL BE
PERFORMED IN PHASES.
M. IF A REMOTE DECONTAMINATION ENCLOSURE IS UTILIZED FOR THIS WORK, AN AIRLOCK MUST BE ATTACHED TO EACH WORK AREA. THE AIRLOCK SHALL BE SIZED
LARGE ENOUGH TO ALLOW FOR THE WORKERS TO CHANGE THEIR SUITS PRIOR TO LEAVING THE WORK AREA. THE DECONTAMINATION ENCLOSURE SHALL BE
CONSTRUCTED IN ACCORDANCE WITH 29 CFR 1926.
N. CONTRACTOR SHALL BE REQUIRED TO SUBMIT A DETAILED WORK PLAN DESCRIBING THE WORK AREA PREPARATION, REMOVAL AND HANDLING PROCEDURES, AS
WELL AS DECONTAMINATION ENCLOSURES AND NEGATIVE AIR EXHAUST LOCATIONS PRIOR TO BEING ALLOWED TO START THE PROJECT. THIS WORK PLAN WILL
NEED TO BE REVIEWED AND ACCEPTED BY VAMC HEALTH AND SAFETY PERSONNEL PRIOR TO THE START OF WORK.
AA-100
7TH FLOOR ASBESTOS
ABATEMENT PLAN
EJ CD
AA-5
AA-5
AA-5
AA-8
AA-10
AA-10
AA-10
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
BID DOCUMENTS
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of
Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
PhaseARCHITECT/ENGINEER OF RECORD A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
ABATEMENT CONSULTANT:
Revisions: Date:
WARD 9C RENOVATIONS
3495 BAILEY AVENUE BUFFALO, NY 14215
528-18-109
528-18-109- BID ADDENDUM #1 2022/10/27 95 Perry Street, Suite 300
Buffalo, NY 14203 February 25, 2022
AA-10
AA-5
AA-10
AA-5
AA-10
AA-5
AA-10
AA-5
AA-10
AA-5
ENVIRONMENTAL NOTES
E-1 CONTRACTOR SHALL PROPERLY REMOVE, PACKAGE, AND DISPOSE OF FLUORESCENT BULBS IN LIGHTING SCHEDULED FOR REMOVAL WITHIN THE PROJECT WORK
AREA. REFER TO ELECTRICAL DEMOLITION PLANS. RECYCLE ALL REMOVED BULBS IN ACCORDANCE WITH THE 40 CFR PART 273 US EPA UNIVERSAL WASTE RULE.
ANY FLUORESCENT LAMPS BROKEN DURING DEMOLITION SHALL BE DISPOSED OF AS HAZARDOUS WASTE.
E-2 CONTRACTOR SHALL PROPERLY REMOVE, PACKAGE, AND DISPOSE OF FLUORESCENT BALLASTS SCHEDULED FOR REMOVAL WITHIN THE PROJECT WORK AREA.
REFER TO ELECTRICAL DEMOLITION PLANS. THE BALLASTS REMOVED FOR THIS PROJECT MAY CONTAIN DEHP AND/OR PCBS. CONTRACTOR TO PROPERLY
DISPOSE OF ALL BALLASTS.
E-3 CONTRACTOR SHALL PROPERLY REMOVE, PACKAGE, AND RECYCLE BATTERIES IN EXIT LIGHTS SCHEDULED FOR DEMOLITION. REFER TO ELECTRICAL
DEMOLITION PLANS.
E-1
E-2
E-3
E-1
E-2
E-3
E-1
E-2
E-3
E-1
E-2
E-3
E-1
E-2
E-3
E-1
E-2
E-3
E-1
E-2
E-3
E-1
E-2
E-3
LEAD AWARENESS NOTES
1. CONTRACTOR SHALL BE RESPONSIBLE FOR COMPLYING WITH OSHA 29 CFR 1926.62: LEAD EXPOSURE IN CONSTRUCTION; INTERIM FINAL RULE FOR ALL
ACTIVITIES DURING WHICH AN EMPLOYEE MAY BE OCCUPATIONALLY EXPOSED TO LEAD. ALL CONTRACTORS SHALL ENSURE THAT THEIR EMPLOYEES
WEAR PROPER PERSONAL PROTECTIVE EQUIPMENT AND/OR UTILIZE APPROPRIATE WORK METHODS TO PREVENT ELEVATED BLOOD LEAD LEVELS OR
EXPOSURE ABOVE THE PERMISSIBLE EXPOSURE LIMIT.
2. AREAS OF THE BUILDING HAVE BEEN INVESTIGATED FOR THE PRESENCE OF LEAD DURING PAST PROJECTS AND LEAD-BASED PAINT HAS BEEN
IDENTIFIED. SURFACES IDENTIFIED TO BE COATED WITH LEAD-BASED PAINT INCLUDE BUT ARE NOT LIMITED TO INCLUDE:
· GREEN CERAMIC WALL TILES.
· WHITE WITH BEIGE SPECKLES CERAMIC WALL TILES.
· TAN CERAMIC WALL TILES.
· WHITE BED PAN SINKS.
· BLACK WINDOW INFILL PANELS.
· OFF-WHITE METAL RADIATOR COVERS.
3. FURNISHING OF THIS INFORMATION IS NOT INTENDED TO RELIEVE THE CONTRACTOR OF ITS RESPONSIBILITIES UNDER OSHA TO DETERMINE THE
PRESENCE, LOCATION, AND QUANTITY OF EXISTING LEAD-CONTAINING MATERIALS THAT THEIR EMPLOYEES AND SUBCONTRACTORS MAY BE EXPOSED
TO, AND TO WARN THEIR EMPLOYEES OF THE POTENTIAL DANGERS OF THE DISTURBANCE OF LEAD-CONTAINING MATERIALS.
| Sheets and Views |
| AA-100 |
File details come from the government source that posted it. Updated .