This document is a pre-solicitation notice for a construction project at the VA Puget Sound Healthcare System in Seattle, Washington. The project involves parking garage corrections and mental health research building completion items, with an estimated construction cost range of $500,000 to $1,000,000. The solicitation will be posted on November 7, 2019 and restricted to verified Service-Disabled Veteran-Owned Small Businesses. An optional site visit will be held approximately two weeks after posting. Questions regarding the solicitation must be submitted in writing by a specified deadline. Proposals will be due 30 days after posting and must demonstrate the ability to provide bid, performance, and payment bonds. The work must be completed within 180 calendar days of notice to proceed. The contracting office is the VA Office of Construction and Facilities Management in Vallejo, California.
36C10F19B0006 36C10F19B0006.docx
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation Document No.36C10F19B0006 Continuation Block #10 of SF1442(continued) Project No. 663-405 Project. Parking Garage Correction Items & Mental Health Research Building Completion Items
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
36C10F19B0006 X
11-07-2019
605-405 003C4E Department of Veterans Affairs Office of Construction and Facilities Management 400 Mare Island Way, Suite 100 Vallejo CA 94590-5867 Dominik Gammon Department of Veterans Affairs Office of Construction and Facilities Management Vallejo CA 94590-5867
DOMINIK GAMMON
707-647-8990 Project No. 605-405B, Project Description: Parking Garage Correction Items & Mental Health Research Building Completion Items at the VA Puget Sound Health Care System, Seattle 1660 S Columbian Way, Seattle, WA 98108-1597.
The Contractor shall provide all labor, materials, equipment and supervision and perform all necessary work including but not be limited to preparing the site for building operations including demolition and removal of all existing structures. Contractor shall perform all work for repairing or replacement of Parking Garage Corrections Items and Mental Health Research Building Completion Items as required by the specification and drawings. Prior to construction, contractor will be required to provide a phasing schedule along with a detailed breakdown on schedule of values indicating all sub-contractor performance in each task of the work breakdown structure with consideration for not disrupting patients and employees. All work to be completed in accordance with attached VA plans and all specifications.
IAW VAAR 836.204 Disclosure of the magnitude of construction projects- This project magnitude range for bidding purposes is between $500,000 and $1,000,000. Prior to start of work the Contractor shall provide proof that an OSHA certified "competent person" in accordance with 29CFR 1926.20(b)(2) will maintain a presence at the work site whenever the Prime or Subcontractor(s) are present. All employees of Prime and Subcontractor(s) shall have proof of completion of the 10-hours OSHA certified construction safety course and/or other relevant competency training.
In accordance with FAR 52.236-27 Site Visit (construction),there will be a Pre-Bid Conference/Site Inspection held for this project on 11-20-2019 at 1:00 pm PST.
ALL BIDDERS ARE ENCOURAGED TO ATTEND. ENGINEERING OFFICE CONFERNCE ROOM 115 AT BUILDING 18.
This is a SERVICE-DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE. All prospective bidders must be registered in the SAM database to be eligible for a contract award. Firms can register via the Internet at https://www.sam.gov by contacting the SAM Customer Service at 1-866-606-8220 and are required to submit their Representations and Certifications on-line through SAM. Bidders must also be registered in VETS 100, https://vets100.ets.dol.gov.
Any vendor wishing to receive an award must be "verified" by the Center for Veterans Enterprise (CVE), VIP at the time of submission of bid and at time of award. Lack of verification may be considered "non-responsive".
Visit www.vip.vetbiz for details.
NAICS: 236220 Commercial and Institutional Building Construction Size Standard: $36.5 Million
AWARD WILL BE MADE TO THE LOWEST, RESPONSIBLE, RESPONSIVE BIDDER WHOSE BID CONFORMS TO ALL SOLICITATION REQUIREMENTS.
IN ORDER TO PROTECT THE INTEGRITY OF THE BIDDING PROCESS ALL QUESTIONS SHALL BE SUBMITTED IN WRITING TO THE CONTRACTING OFFICER at Dominik.Gamnon@va.gov REQUEST FOR INFORMATION NO LATER THAN 4:30 PM, 12-02-2019 PST. Award is subject to the availability of funds.
X X
52.211-10 X
10 CALENDAR DAYS FORM NTP
2:00 PM PST
12-09-2019
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
See Bid Continuation Sheet
003C4E Department of Veterans Affairs Office of Construction and Facilities Management 400 Mare Island Way, Suite 100 Vallejo CA 94590
Department of Veterans Affairs
FMS-VA-2(101)
Financial Services Center PO Box 149971 Austin TX 78714-9971
Ronald Ferrer Contracting Officer
Table of Contents
| PART I - THE SCHEDULE | 1 |
| SECTION A - SOLICITATION/CONTRACT FORM | 1 |
| A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair) | 1 |
| A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK | 2 |
| SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS | 6 |
| B.1 PRICE/COST SCHEDULE | 7 |
| ITEM INFORMATION | 7 |
| SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK | 12 |
| [ X ] VAAR 852.219-10 VA Notice of Total Service-Disabled Veteran-Owned Small Business Set- Aside (JUL 2016)(DEVIATION) | 14 |
| SECTION D - PACKAGING AND MARKING | 14 |
| SECTION E - INSPECTION AND ACCEPTANCE | 15 |
| F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) | 15 |
| SECTION G - CONTRACT ADMINISTRATION DATA | 15 |
| SECTION H - SPECIAL CONTRACT REQUIREMENTS | 15 |
| PART II - CONTRACT CLAUSES | 15 |
| SECTION I - CONTRACT CLAUSES | 15 |
| I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998) | 15 |
| I.2 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014) | 19 |
| I.3 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) | 19 |
| I.4 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016) | 19 |
| I.5 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB AND OTHER COVERED ENTITIES (JUL 2018) | 21 |
| I.6 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 22 |
| I.7 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JUL 2013) | 23 |
| I.8 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (OCT 2015) | 24 |
| I.9 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUL 2014) | 24 |
| I.10 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010) | 25 |
| I.11 52.225-23 REQUIRED USE OF AMERICAN IRON, STEEL, AND MANUFACTURED GOODS—BUY AMERICAN STATUTE—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (OCT 2016) | 26 |
| I.12 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014) | 30 |
| I.13 52.227-1 AUTHORIZATION AND CONSENT (DEC 2007) | 33 |
| I.14 52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT COPYRIGHT INFRINGEMENT (DEC 2007) | 33 |
| I.15 52.232-35 DESIGNATION OF OFFICE FOR GOVERNMENT RECEIPT OF ELECTRONIC FUNDS TRANSFER INFORMATION (JUL 2013) | 34 |
| I.16 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) ALTERNATE II (APR 1984) | 34 |
| I.17 52.244-2 SUBCONTRACTS (OCT 2010) | 35 |
| I.18 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2016)(DEVIATION) | 37 |
| I.19 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018) | 38 |
| I.20 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018) | 39 |
| I.21 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019) | 40 |
| I.22 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019) | 40 |
| I.23 SUPPLEMENTAL INSURANCE REQUIREMENTS | 41 |
| PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS | 42 |
| SECTION J - LIST OF ATTACHMENTS | 42 |
| PART IV - REPRESENTATIONS AND INSTRUCTIONS | 43 |
| SECTION K - REPRESENTATIONS, CERTIFICATIONS AND OTHER STATEMENTS OF OFFERORS | 43 |
| K.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (OCT 2018) | 43 |
| K.2 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018) | 46 |
| K.3 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018) | 47 |
| K.4 52.222-22 PREVIOUS CONTRACTS AND COMPLIANCE REPORTS (FEB 1999) | 49 |
| SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS | 49 |
| L.1 52.211-1 AVAILABILITY OF SPECIFICATIONS LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS, FPMR PART 101-29 (AUG 1998) | 49 |
| L.2 52.211-2 AVAILABILITY OF SPECIFICATIONS, STANDARDS, AND DATA ITEM DESCRIPTIONS LISTED IN THE ACQUISITION STREAMLINING AND STANDARDIZATION INFORMATION SYSTEM (ASSIST) (APR 2014) | 49 |
| L.3 52.211-3 AVAILABILITY OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (JUN 1988) | 50 |
| L.4 52.211-4 AVAILABILITY FOR EXAMINATION OF SPECIFICATIONS NOT LISTED IN THE GSA INDEX OF FEDERAL SPECIFICATIONS, STANDARDS AND COMMERCIAL ITEM DESCRIPTIONS (JUN 1988) | 50 |
| L.5 52.216-1 TYPE OF CONTRACT (APR 1984) | 50 |
| L.6 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) | 51 |
| L.7 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999) | 51 |
| L.8 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014) | 52 |
| L.9 52.225-24 NOTICE OF REQUIRED USE OF AMERICAN IRON, STEEL, AND MANUFACTURED GOODS—BUY AMERICAN STATUTE—CONSTRUCTION MATERIALS UNDER TRADE AGREEMENTS (MAY 2014) ALTERNATE II (MAR 2009) | 53 |
| L.10 52.228-1 BID GUARANTEE (SEP 1996) | 54 |
| L.11 52.233-2 SERVICE OF PROTEST (SEP 2006) | 54 |
| L.12 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995) | 55 |
| L.13 52.252-3 ALTERATIONS IN SOLICITATION (APR 1984) | 55 |
| L.14 52.252-5 AUTHORIZED DEVIATIONS IN PROVISIONS (APR 1984) | 55 |
| L.15 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018) | 55 |
| L.16 VAAR 852.214-74 MARKING OF BID SAMPLES (MAY 2018) | 56 |
| L.17 VAAR 852.252-70 SOLICITATION PROVISIONS OR CLAUSES INCORPORATED BY REFERENCE (JAN 2008) | 56 |
| L.18 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) | 56 |
| L.19 VAAR 852.236-92 NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE ITEMS (APR 2019) | 57 |
| SECTION M - EVALUATION FACTORS FOR AWARD | 57 |
| M.1 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998) | 57 |
SECTION B - SUPPLIES OR SERVICES AND PRICE/COSTS
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
************************ NOTICE TO OFFERORS************************
Invitations For Bid NO.: 36C10F19B0006 BID DUE DATE 12/09/2019 2:00 PM Pacific Standard Time The bid opening shall take place at the above stated date/time at 400 Mare Island Way, Suite 100, Vallejo, CA. 94950.
PROJECT TITLE: Parking Garage Correction Items & Mental Health Research Building Completion Items ALL REQUEST FOR INFORMATION/INQUIRIES (RFI’s) CONCERNING THIS IFB MUST BE SUBMITTED IN WRITING VIA EMAIL TO THE BELOW ADDRESS AS INDICATED BELOW, AND MUST BE RECEIVED NO LATER THAN 12/02/2019 2:00 PM PST., IN ORDER TO PERMIT ADEQUATE TIME FOR THE GOVERNMENT TO RESPOND TO RFI’s.
YOU MAY SEND YOUR RFI’s UNDER THE SUBJECT LINE:
Bidder Company Name | Request for Information # | Parking Garage Correction Items & Mental Health Research Building Completion Items| IFB. 36C10F19B0006| Project No. 663-405 VIA E-MAIL TO: DOMINIK.GAMMON@VA.GOV. It is recommended to use a read receipt for verification of RFI’s delivery confirmation.
YOUR BID AND/OR OTHER CORRESPONDENCE REQUESTING INTERPRETATION AND/OR CLARIFICATION SHOULD BE ADDRESSED TO:
Office of Construction and Facilities Management West Region ATTN: DOMINIK GAMMON 400 Mare Island Way, Suite 100
NOTE: All documents for the solicitation are available at www.FBO.gov. Is the contractor’s responsibility to check this site for amendments to the solicitation? Although not mandatory interested parties should attend the site visit being held IAW FAR 52.236-27 date, location, time contained in this solicitation.
The solicitation will be awarded pursuant to FAR part 14 – Sealed Bidding. This is 100% set aside for Service-Disabled Veteran Owned Small Business (SDVOSB). Contractors shall be Center for Veterans Enterprise (CVE) VIP verified at the time of submission of bid and at time of award.
STATEMENT OF BID ITEM(S)
The Contractor shall provide all labor, tools, equipment, materials and supplies necessary to perform the work identified in specifications, and drawings. Work includes, but is not limited to: Removal and replacement of building floor expansion joints, joint covers and related under joint drainage system; Installation of under-slab structural “alignment lugs;” Installation of pipe railing(s); Removal and replacement of fire alarm strobe lights; Alterations to pendant and exit lighting; Additional lighting; Relocation of a security camera; Corrections to drainage issues at stairwells; Installation of expansion provisions to existing glass guardrail; Installation of additional roof drains; Installation of a drainage system from expansion joint drains to existing floor drains; Installation of various joint covers and ceiling materials; Miscellaneous concrete crack sealing; Painting and finishes; Scheduling, traffic control and security measures.
B.1 PRICE/COST SCHEDULE
ITEM INFORMATION
| ITEM NUMBER |
| DESCRIPTION OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
Parking Garage Correction Items
00001
| 1.00 |
| JB |
| __________________ |
| __________________ |
Testing & Laboratory Services, Reinforcement Location and Marking.
00002
| 1.00 |
| JB |
| __________________ |
| __________________ |
Traffic Control and Signage.
00003
| 1.00 |
| JB |
| __________________ |
| __________________ |
Add Slab Alignment Lugs.
00004
| 1.00 |
| JB |
| __________________ |
| __________________ |
Add Fire Sprinkler Pipe Expansion Joints.
00005
| 1.00 |
| JB |
| __________________ |
| __________________ |
Expansion Joint Cover / Drainage Trough Replacement.
00006
| 1.00 |
| JB |
| __________________ |
| __________________ |
Reduce Ponding on Level 4 / Floor Drains.
00007
| 1.00 |
| JB |
| __________________ |
| __________________ |
Expansion Joint / Drainage Trough / Floor Drain Piping.
00008
| 1.00 |
| JB |
| __________________ |
| __________________ |
Repair Concrete Wall Joints Level B3, Grid Line H/4 and Level B2 Grid Lines G/23 and G/4.
00009
| 1.00 |
| JB |
| __________________ |
| __________________ |
Add Cover Plates at Wall Joints at Level B2 and B3, Grid Lines G & H.
00010
| 1.00 |
| JB |
| __________________ |
| __________________ |
Add Joint Seal and Cover Plate Level B1, Grid Line 12.5.
00011
| 1.00 |
| JB |
| __________________ |
| __________________ |
Repair Concrete Beam Spall, Ceiling of Level B3, Grid Line H.
00012
| 1.00 |
| JB |
| __________________ |
| __________________ |
Correct Runoff into Stairs 2, 3, 4.
00013
| 1.00 |
| JB |
| __________________ |
| __________________ |
Fix Leaking Ceilings at Stair 5, at Level B2 (the Floor Above Storage Room B3-A-9) and at Level B3 (Ceiling of Storage Room B3A-9).
00014
| 1.00 |
| JB |
| __________________ |
| __________________ |
Add Planter and Waterproofing at Stair
00015
| 1.00 |
| JB |
| __________________ |
| __________________ |
Correct Storage Room Concrete Roof leaks
00016
| 1.00 |
| JB |
| __________________ |
| __________________ |
Add Pipe Railing in Exhaust Shaft Vicinity of Level B, Grid Line R / 24 & 25.
00017
| 1.00 |
| JB |
| __________________ |
| __________________ |
Add Handrail Seismic Joint at Level B1, Grid Line 12.5.
Mental Health Research Building Completion Items
00018
| 1.00 |
| JB |
| __________________ |
| __________________ |
Entrance Mat Statement of Work 1.Remove and dispose of existing entrance mat tiles located at the 1st floor entrance of the Mental Health and Research Building.
2.Provide submittal for replacement entrance mat tiles to be reviewed and accepted by the RE office.
3.Provide and install approved entrance mat tiles. Installation shall be symmetrical with edge tiles cut to fit existing depressed slab frame.
4.Entrance tile product and installation to conform to attached specification 12 93 00. Extent of entrance mat work shown via red clouded sections on attached drawings.
00019
| 1.00 |
| JB |
| __________________ |
| __________________ |
West Loop Road Asphalt Paving Statement of Work and Supplemental Information
1.Construct north end West Loop Road curb & gutter along east side (Ref attached CP101, CP-200). Regrade and compact subgrade for curb & gutter. Work to be in accordance with attached specifications 312000 & 320523.
2.Construct asphalt thickened edge section along east side of West Loop Rd (Ref attached CP101, CP102, CP200). Cut back and demolish existing asphalt edge. Prepare and compact existing base. Minimum ambient temperature to be 40F & rising. Work to be in accordance with attached specifications 312000 & 321216.
3.Complete West Loop Rd paving. Provide 2” asphalt surface course over existing asphalt, w/ tack coat & sealer on W Loop Rd (Ref attached CP101, CP102, CP200).
Existing asphalt surface to be dry and thoroughly cleaned by sweeping prior to tack coat application. Existing asphalt surface temperature to be minimum 35F and minimum ambient temperature to be 40F & rising. Work to be in accordance with attached specification 321216.
4.Prior to providing work in item 3 above, raise all catch basins, manholes, and valve boxes in the section of road to receive the 2” asphalt lift so that the covers or grates are flush with finished asphalt elevation.
5.Provide independent testing laboratory services per attached specification 01 45 29 for the following work only:
a. Concrete testing for curb and gutter work outlined in item 1 above.
b. Subgrade compaction testing for thickened edge work outlined in item 2 above.
c. Asphalt paving testing for work outlined in item 3 above.
00020
| 1.00 |
| JB |
| __________________ |
| __________________ |
Medical Gas Shutoff Zone Valve Cabinet
1.Provide and install a medical gas zone valves and zone valve cabinet in hallway 5H65 in the Mental Health and Research Building (MHR). Zone valve cabinet shall have pressure gages installed on piping downstream of the valves. Valves shall isolate the medical gases from the riser to the patient observation rooms. Valves to be installed on Medical Air, Vacuum, and Oxygen piping serving the 5th floor. All work to be in compliance with NFPA 99 and applicable sections of attached specifications 22 62 00 and 22 63 00.
2.Contractor to provide certification that all work was done in accordance with NFPA 99.
00021
| 1.00 |
| JB |
| __________________ |
| __________________ |
Laboratory and Medical Gas Alarm Panels
1.Provide and Install wireless laboratory and medical gas alarms to coordinate with the existing medical center’s mad gas alarm system in compliance with NFPA 99. Basis of design is Tri-Tech Medical Inc. Equipment.
2.Provide and Install local sending panel in GE08 to send the points identified on attached Medical and Laboratory Gas Alarm Panel Schedule (PS000).
3.Provide and Install repeaters as needed for alarm points to reach the Telephone Operator’s Room and the Boiler Plant Control Office. These locations are shown on attached drawing PS100. A utility tunnel connects the MHR to both locations. For bidding purposes, include 4 repeaters.
4.Provide and install a set of Mater Alarm Panels and Receiving Panels at the Telephone Operator’s Room and the Boiler Plant Control Office. 1 set is required at each location.
5.All work to be installed in accordance with NFPA 99 and applicable sections of attached specifications 22 62 00 and 22 63 00.
6.Contractor to provide certification that all work was done in accordance with NFPA 99.
00022
| 1.00 |
| JB |
| __________________ |
| __________________ |
Medical Gas Zone Alarm
1.Provide and install a zone alarm at the observation desk located at 5E36. Zone valve shall report points identified on attached Medical and Laboratory Gas Alarm Panel Schedule (PS000).
2.All work to be installed in accordance with NFPA 99 and applicable sections of attached specifications 22 62 00 and 22 63 00.
Note- Supplemental specifications are included in this package and are applicable only as referenced in section 1.2 of specifications 22 62 00 and 22 63 00.
| GRAND TOTAL |
| __________________ |
DEDUCT ALTERNATES
Deduct Alternate No. 1: Delete the addition of a raised planter area including demolition of existing concrete, new waterproofing topsoil and plant materials. All work enumerated on Drawing Sheet AE872.
DEDUCT ALTERNATES: CLIN 00014, LUMP SUM: ($_____________________________)
Solicitation Document No.36C10F19B0006 Continuation Block #10 of SF1442(continued) Project No. 663-405 Project. Parking Garage Correction Items & Mental Health Research Building Completion Items
In the event that all of the bids exceed available funding for the Base Bid, a single award will be made exclusively on Deduct Alternate Bid Item 01.
INFORMATION REGARDING BID GUARANTEE AND BONDS
A. Bidding materials consisting of Invitation for Bids, drawings, specifications and contract forms will be available on http://www.fedbizopps.gov in electronic format only by searching for solicitation number 36C10F19B0006 . All interested parties (subs & primes) should register at http://www.fedbizopps.gov as an “Interested Vendor” so that others will know of our interest in participating in this procurement. A Bidder’s mailing list WILL NOT BE prepared by the Contract Specialist. SOLICITATION AMENDMENTS: Amendments to the solicitation will be posted at http://www.fedbizopps.gov. Paper copies of the amendments will NOT be individually mailed. By registering to “Receive Notification”, you will be notified by e-mail of any new amendments that have been issued and posted. No other notification of amendments will be provided. Offerors are reminded that they are responsible for obtaining and acknowledging all amendments to this solicitation prior to the time for receipt of offers.
B. Subcontractors, material firms and others interested in preparing sub bids may obtain a list of organizations and interested Bidders / Prime Contractors at that same www.FBO.Gov.
C. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
D. If bid exceeds $150,000 a bid bond must be submitted. A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for opening of bids, will require rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
E. If the contract will exceed $150,000 (see FAR 28.102-1 for lesser amount), the bidder to whom award is made will be required to furnish two bonds, a Payment Bond, SF 25A, and a Performance Bond, SF 25, each in the penal sum as noted in the General Conditions of the Specification. Copies of SFs 25 and 25A may be obtained upon application to the issuing office.
F. If the bid/offer is between $30,000 - $150,000. The bidder/offeror to whom award is made will be required to furnish a Payment Bond, Standard Form 25A or alternative payment protection which conforms to the requirements set forth in FAR Clause 52.228-13, Alternative Payment Protections, as noted in the General Conditions of this Specification. Copies of the Standard Form of Payment Bond may be obtained upon application to the Issuing Office.
Provided below is the Price Schedule Summary. The successful Bidder will be the responsive and responsible Bidder whose bid will provide the most features of work at the lowest price starting at the Base Item and continuing down the list of Deductive Alternate Items in descending order of priority. Award of a Deductive Alternate Item is at the sole discretion of the Department of Veterans Affairs(DVA). The number of the Deductive Alternate Items awarded, if any, is contingent on available funding A full description of each Deductive Alternate Item is provided in Attachment 1 Specifications Volume 1, Section 01 00 00 General Requirements at 1.2 Statement of Bid Items. As stated in the Statement of Bid Items, the pricing provided for each Deductive Alternate Item shall be the dollar amount to be deducted from the Base Line Item as described in the Statement of Bid Items.
CONSTRUCTION SCHEDULE
| Construction Task | Scheduled Completion | |
| Award of Contract | NTP | |
| Project Schedule, Schedule of values, | NTP +10 Days |
Submittal Log (Critical/Non-Critical) Contractor and subcontractors list including names and training records, Survey Report
| Contractor to submit critical submittals | NTP +30 Days | |||
| VA review and return critical submittals | NTP +30 Days | |||
| Contractor to submit non-critical submittals | NTP +30 Days | |||
| VA review and return non-critical submittals | NTP +30 Days | |||
| Construction starts | NTP +40 Days | |||
| Final Inspection | NTP + 180 Days | |||
| Contract Completion | NTP + 180 Days |
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
Scope of Contract
Contractor shall provide all tools, material, equipment, transportation, supervision, and labor for work as indicated and specified, involving general construction, miscellaneous repairs and alterations to the recently constructed Parking Garage Correction Item and Mental Health Research Building Completions.
All work shall be accomplished in compliance with applicable local, state and federal codes, and VA specification and drawings.
SITE VISITS AND EXISTING CONDITIONS
Discrepancies in Planning Information: The contractor shall promptly report to the Contractor Officer, in writing, any discrepancy between this contract, the Specification provided by the Government and existing conditions. The contractor shall make no adjustments to his/her work due to the discrepancy before the Contracting Officer has reviewed the matter and forwarded his/her determination to the contractor.
The contractor’s failure to report any such discrepancy or wait for the Contracting Officer’s determination shall be at his/her risk and expense. The contractor shall attend a “Project Kick-off and Requirements Review.” Meeting at the Medical Center in support of this effort. This meeting will occur no later than fourteen (14) calendar days after notice to proceed has been issued by the Contracting Officer and will be used to review the requirements of the Scope of Work (SOW) and discuss roles, responsibilities, expectations and deliverables and provide answers to any questions the contractor might have. The contractor shall also identify to the Government any issues or concerns they have with the Parking Garage Completion Items & Mental Health Research Building Completion Items contract. The contractor shall communicate with the COR via e-mail to establish the dates, times, and location of this meeting.
The contractor shall daily clean up the construction areas affected by the execution of this contract sufficient to the point there are no hazards or safety concerns with VA patients and staff.
The contractor shall ensure all construction materials and equipment have been secured from the VA medical center patients and staff, theft, damage and weather and the work area cleaned and made safe at the end of each working day.
The contractor shall submit a detailed schedule defining specific milestones, tasks and phasing of the demolition, installation, startup and commissioning work for approval a minimum of 30 days prior to Notice to Proceed. In addition to the primary schedule, a two week look ahead schedule shall be provided to address potential or known issues.
Testing/Punch List/End User Training/Activation
The contractor shall prepare punch lists, if needed, and schedule a preliminary walkthrough with the COR once there is a substantial completion of each CLIN Line Items. After the preliminary walkthrough, the VA will submit its own punch list if needed.
Once the contractor has completed or resolved all punch list items, both the contractor’s and the VAs, the contractor shall schedule a final walkthrough with the COR.
Once the final walkthrough is completed, and the completed parking garage completion items are ready for operation, each CLIN line item will test for compliance. Testing and operator training should be conducted simultaneously to the greatest degree possible without interfering in preset contract schedules.
This project is reserved for 100% SDVOSB set-aside Prime Contractors. No other set-aside in accordance with FAR 19 shall be allowed to submit a bid on the above stated solicitation.
Prime contractors may share bidding materials with subcontractors and suppliers as necessary; however, all questions shall be submitted by the prime contractors on behalf of their subcontractors and suppliers.
Reference 01 00 00, Para. 1.2, B B. Site visits require written approval from the COR. Provide a minimum of 24 hours’ notice to the COR in advance of requested site visit.
Reference 01 00 00, Para. 1.2, D D. Normal hours of work shall be 07:30 a.m. to 6:00 p.m., Monday through Friday with the exception of Federal Holidays.
1. Impact construction work (pile driving, jackhammers, etc.) is limited to: 8:00 a.m. to 4:30 p.m., Monday through Friday. Additionally, the Contractor shall comply with City of Seattle noise ordinances should they be more restrictive.
2. For work performed on, within or above traffic lanes:
a. Related work specified elsewhere: Section 01 35 26, Para. 1.25, Traffic Control.
b. One traffic lane shall remain open at all times.
3. Parking spaces adjacent to the work may be used as the traffic lane. Notice of “No Parking from / to - date / time” signs shall be placed in each needed parking space a minimum of 3 working days prior closing. Show this work in the construction schedule and coordinate with the COR.
4. Requests to work beyond normal work hours shall be submitted in writing to the COR for approval and will include a description of work to be performed, and specific hours requested. Under no conditions will the Contractor proceed without written approval of the COR.
Reference 01 00 00, Para. 1.13, A A. Use of existing elevators for handling small building materials, tools, equipment, carts. and Contractor's personnel will be permitted subject to following provisions:
1. Use will be shared with patients, staff and visitors. Use by these persons shall take precedence over Contractor use. Contractors’ personnel shall defer to these persons and use common sense should an elevator car be nearly full, in use by persons on stretchers, in wheelchairs or otherwise disabled.
a. Contractor shall be responsible, at the end of each working day, to inspect elevator cars and remove any mud, dirt, or debris resulting from their usage.
b. Contractor shall educate sub-contractors, suppliers and other personnel in these procedures.
c. Should complaints be received, use of elevators may be revoked by the COR.
Reference 01 00 00, Para. 1.25, E, 1, 1, At a minimum the traffic control plan shall:
1) For vehicles: Identify locations and dates of work, identify proposed warning, barricading , flagging, directional signage and any parking spaces needing to be restricted prior to the work.
2) For pedestrians: Identify locations and dates of work, proposed barricading methods, proposed alternative routes and signage.
3) Be coordinated and correspond to activities identified in the project schedule.
A. Impact construction work (pile driving, jackhammers, etc.) is limited to: 8:00 a.m. to 4:30 p.m., Monday through Friday.
B. Work performed within or directly above traffic lanes on Levels 1, B1, B2, and B3 shall not be performed during normal hours of work.
C. Other than normal hours of work: Work performed within or directly above traffic lanes on Levels 1, B1, B2, and B3 shall commence no earlier than 5:00p.m. and extend no later than 1:30 a.m., Monday through Friday and 8:00am-5:00pm Saturday and Sunday.
Caution: No oral statements made by the contract parties or other interested parties will take precedence over the written terms and conditions of the solicitation or resultant award.
Furthermore, all questions shall be submitted by the prime contractor(s) on behalf of their subcontractor(s) and supplier(s) to the Contract Specialist. Questions submitted by subcontractors and/or suppliers directly to the Contract Specialist, or if applicable, the AE of Record, will be rejected and not answered.
[ X ] VAAR 852.219-10 VA Notice of Total Service-Disabled Veteran-Owned Small Business Set- Aside (JUL 2016)(DEVIATION)
Special Note: This procurement is subject to the requirements of the Buy American Act. The requirements are set forth IAW FAR 52.225-9 Buy American-Construction materials (May 2014), FAR 52.225-11 Buy American-Construction Materials Under Trade Agreements, and VAAR 852.236-89 Buy American Act- Construction Materials (JAN 2008)
SECTION D - PACKAGING AND MARKING
NONE
SECTION E - INSPECTION AND ACCEPTANCE
Solicitation Document No.36C10F19B0006 Continuation Block #10 of SF1442(continued) Project No. 663-405 Project. Parking Garage Correction Items & Mental Health Research Building Completion Items
| FAR Number |
| Title |
| Date |
| 52.246-12 |
| INSPECTION OF CONSTRUCTION |
| AUG 1996 |
F.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 180 Calendar Days aftet Notice to Proceed.. The time stated for completion shall include final cleanup of the premises.
The completion date is based on the assumption that the successful offeror will receive the notice to proceed by TBD. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.
Solicitation Document No.36C10F19B0006 Continuation Block #10 of SF1442(continued) Project No. 663-405 Project. Parking Garage Correction Items & Mental Health Research Building Completion Items (End of Clause)
SECTION G - CONTRACT ADMINISTRATION DATA
NONE
SECTION H - SPECIAL CONTRACT REQUIREMENTS
NONE
PART II - CONTRACT CLAUSES
SECTION I - CONTRACT CLAUSES
I.1 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/
| FAR Number |
| Title |
| Date |
| 52.202-1 |
| DEFINITIONS |
| NOV 2013 |
| 52.203-3 |
| GRATUITIES |
| APR 1984 |
| 52.203-5 |
| COVENANT AGAINST CONTINGENT FEES |
| MAY 2014 |
| 52.203-6 |
| RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT |
| SEP 2006 |
| 52.203-7 |
| ANTI-KICKBACK PROCEDURES |
| MAY 2014 |
| 52.203-8 |
| CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY |
| MAY 2014 |
| 52.203-10 |
| PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY |
| MAY 2014 |
| 52.203-12 |
| LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS |
| OCT 2010 |
| 52.203-15 |
| WHISTLEBLOWER PROTECTIONS UNDER THE AMERICAN RECOVERY AND REINVESTMENT ACT OF 2009 |
| JUN 2010 |
| 52.203-16 |
| PREVENTING PERSONAL CONFLICTS OF INTEREST |
| DEC 2011 |
| 52.203-17 |
| CONTRACTOR EMPLOYEE WHISTLEBLOWER RIGHTS AND REQUIREMENT TO INFORM EMPLOYEES OF WHISTLEBLOWER RIGHTS |
| APR 2014 |
| 52.203-19 |
| PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS |
| JAN 2017 |
| 52.204-9 |
| PERSONAL IDENTITY VERIFICATION OF CONTRACTOR PERSONNEL |
| JAN 2011 |
| 52.204-4 |
| PRINTED OR COPIED DOUBLE-SIDED ON POSTCONSUMER FIBER CONTENT PAPER |
| MAY 2011 |
| 52.204-10 |
| REPORTING EXECUTIVE COMPENSATION AND FIRST-TIER SUBCONTRACT AWARDS |
| OCT 2018 |
| 52.204-13 |
| SYSTEM FOR AWARD MANAGEMENT MAINTENANCE |
| OCT 2018 |
| 52.204-14 |
| SERVICE CONTRACT REPORTING REQUIREMENTS |
| OCT 2016 |
| 52.204-18 |
| COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE |
| JUL 2016 |
| 52.209-6 |
| PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT |
| OCT 2015 |
| 52.209-10 |
| PROHIBITION ON CONTRACTING WITH INVERTED DOMESTIC CORPORATIONS |
| NOV 2015 |
| 52.213-4 |
| TERMS AND CONDITIONS—SIMPLIFIED ACQUISITIONS (OTHER THAN COMMERCIAL ITEMS) |
| JAN 2019 |
| 52.214-26 |
| AUDIT AND RECORDS—SEALED BIDDING |
| OCT 2010 |
| 52.214-27 |
| PRICE REDUCTION FOR DEFECTIVE CERTIFIED COST OR PRICING DATA—MODIFICATIONS—SEALED BIDDING |
| AUG 2011 |
| 52.214-28 |
| SUBCONTRACTOR CERTIFIED COST OR PRICING DATA—MODIFICATIONS—SEALED BIDDING |
| OCT 2010 |
| 52.214-29 |
| ORDER OF PRECEDENCE—SEALED BIDDING |
| JAN 1986 |
| 52.219-8 |
| UTILIZATION OF SMALL BUSINESS CONCERNS |
| OCT 2018 |
| 52.219-27 |
| NOTICE OF SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE |
| NOV 2011 |
| 52.222-3 |
| CONVICT LABOR |
| JUN 2003 |
| 52.222-4 |
| CONTRACT WORK HOURS AND SAFETY STANDARDS—OVERTIME COMPENSATION |
| MAY 2018 |
| 52.222-6 |
| CONSTRUCTION WAGE RATE REQUIREMENTS |
| AUG 2018 |
| 52.222-7 |
| WITHHOLDING OF FUNDS |
| MAY 2014 |
| 52.222-8 |
| PAYROLLS AND BASIC RECORDS |
| AUG 2018 |
| 52.222-9 |
| APPRENTICES AND TRAINEES |
| JUL 2005 |
| 52.222-10 |
| COMPLIANCE WITH COPELAND ACT REQUIREMENTS |
| FEB 1988 |
| 52.222-11 |
| SUBCONTRACTS (LABOR STANDARDS) |
| MAY 2014 |
| 52.222-12 |
| CONTRACT TERMINATION—DEBARMENT |
| MAY 2014 |
| 52.222-13 |
| COMPLIANCE WITH CONSTRUCTION WAGE RATE REQUIREMENTS AND RELATED REGULATIONS |
| MAY 2014 |
| 52.222-14 |
| DISPUTES CONCERNING LABOR STANDARDS |
| FEB 1988 |
| 52.222-15 |
| CERTIFICATION OF ELIGIBILITY |
| MAY 2014 |
| 52.222-21 |
| PROHIBITION OF SEGREGATED FACILITIES |
| APR 2015 |
| 52.222-26 |
| EQUAL OPPORTUNITY |
| SEP 2016 |
| 52.222-27 |
| AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION |
| APR 2015 |
| 52.222-37 |
| EMPLOYMENT REPORTS ON VETERANS |
| FEB 2016 |
| 52.222-41 |
| SERVICE CONTRACT LABOR STANDARDS |
| AUG 2018 |
| 52.222-43 |
| FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT LABOR STANDARDS—PRICE ADJUSTMENT (MULTIPLE YEAR AND OPTION CONTRACTS) |
| AUG 2018 |
| 52.222-44 |
| FAIR LABOR STANDARDS ACT AND SERVICE CONTRACT LABOR STANDARDS—PRICE ADJUSTMENT |
| MAY 2014 |
| 52.222-50 |
| COMBATING TRAFFICKING IN PERSONS ALTERNATE I (MAR 2015) |
| JAN 2019 |
| 52.222-50 |
| COMBATING TRAFFICKING IN PERSONS |
| JAN 2019 |
| 52.222-54 |
| EMPLOYMENT ELIGIBILITY VERIFICATION |
| OCT 2015 |
| 52.222-55 |
| MINIMUM WAGES UNDER EXECUTIVE ORDER 13658 |
| DEC 2015 |
| 52.222-62 |
| PAID SICK LEAVE UNDER EXECUTIVE ORDER 13706 |
| JAN 2017 |
| 52.223-2 |
| AFFIRMATIVE PROCUREMENT OF BIOBASED PRODUCTS UNDER SERVICE AND CONSTRUCTION CONTRACTS |
| SEP 2013 |
| 52.223-5 |
| POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION |
| MAY 2011 |
| 52.223-6 |
| DRUG-FREE WORKPLACE |
| MAY 2001 |
| 52.223-19 |
| COMPLIANCE WITH ENVIRONMENTAL MANAGEMENT SYSTEMS |
| MAY 2011 |
| 52.223-18 |
| ENCOURAGING CONTRACTOR POLICIES TO BAN TEXT MESSAGING WHILE DRIVING |
| AUG 2011 |
| 52.223-21 |
| FOAMS |
| JUN 2016 |
| 52.224-3 |
| PRIVACY TRAINING ALTERNATE I (JAN 2017) |
| JAN 2017 |
| 52.225-13 |
| RESTRICTIONS ON CERTAIN FOREIGN PURCHASES |
| JUN 2008 |
| 52.227-4 |
| PATENT INDEMNITY—CONSTRUCTION CONTRACTS |
| DEC 2007 |
| 52.228-2 |
| ADDITIONAL BOND SECURITY |
| OCT 1997 |
| 52.228-5 |
| INSURANCE—WORK ON A GOVERNMENT INSTALLATION |
| JAN 1997 |
| 52.228-11 |
| PLEDGES OF ASSETS |
| AUG 2018 |
| 52.228-12 |
| PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS |
| MAY 2014 |
| 52.228-14 |
| IRREVOCABLE LETTER OF CREDIT |
| NOV 2014 |
| 52.228-15 |
| PERFORMANCE AND PAYMENT BONDS—CONSTRUCTION |
| OCT 2010 |
| 52.229-3 |
| FEDERAL, STATE, AND LOCAL TAXES |
| FEB 2013 |
| 52.232-5 |
| PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS |
| MAY 2014 |
| 52.232-17 |
| INTEREST |
| MAY 2014 |
| 52.232-18 |
| AVAILABILITY OF FUNDS |
| APR 1984 |
| 52.232-23 |
| ASSIGNMENT OF CLAIMS ALTERNATE I (APR 1984) |
| MAY 2014 |
| 52.232-27 |
| PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS |
| JAN 2017 |
| 52.232-33 |
| PAYMENT BY ELECTRONIC FUNDS TRANSFER—SYSTEM FOR AWARD MANAGEMENT |
| OCT 2018 |
| 52.232-36 |
| PAYMENT BY THIRD PARTY |
| MAY 2014 |
| 52.232-39 |
| UNENFORCEABILITY OF UNAUTHORIZED OBLIGATIONS |
| JUN 2013 |
| 52.232-40 |
| PROVIDING ACCELERATED PAYMENTS TO SMALL BUSINESS SUBCONTRACTORS |
| DEC 2013 |
| 52.233-1 |
| DISPUTES ALTERNATE I (DEC 1991) |
| MAY 2014 |
| 52.233-3 |
| PROTEST AFTER AWARD |
| AUG 1996 |
| 52.233-4 |
| APPLICABLE LAW FOR BREACH OF CONTRACT CLAIM |
| OCT 2004 |
| 52.236-2 |
| DIFFERING SITE CONDITIONS |
| APR 1984 |
| 52.236-3 |
| SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK |
| APR 1984 |
| 52.236-5 |
| MATERIAL AND WORKMANSHIP |
| APR 1984 |
| 52.236-6 |
| SUPERINTENDENCE BY THE CONTRACTOR |
| APR 1984 |
| 52.236-7 |
| PERMITS AND RESPONSIBILITIES |
| NOV 1991 |
| 52.236-8 |
| OTHER CONTRACTS |
| APR 1984 |
| 52.236-9 |
| PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS |
| APR 1984 |
| 52.236-10 |
| OPERATIONS AND STORAGE AREAS |
| APR 1984 |
| 52.236-11 |
| USE AND POSSESSION PRIOR TO COMPLETION |
| APR 1984 |
| 52.236-12 |
| CLEANING UP |
| APR 1984 |
| 52.236-13 |
| ACCIDENT PREVENTION |
| NOV 1991 |
| 52.236-14 |
| AVAILABILITY AND USE OF UTILITY SERVICES |
| APR 1984 |
| 52.236-15 |
| SCHEDULES FOR CONSTRUCTION CONTRACTS |
| APR 1984 |
| 52.236-16 |
| QUANTITY SURVEYS |
| APR 1984 |
| 52.236-17 |
| LAYOUT OF WORK |
| APR 1984 |
| 52.236-21 |
| SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION |
| FEB 1997 |
| 52.236-28 |
| PREPARATION OF PROPOSALS—CONSTRUCTION |
| OCT 1997 |
| 52.242-13 |
| BANKRUPTCY |
| JUL 1995 |
| 52.243-4 |
| CHANGES |
| JUN 2007 |
| 52.243-6 |
| CHANGE ORDER ACCOUNTING |
| APR 1984 |
| 52.245-9 |
| USE AND CHARGES |
| APR 2012 |
| 52.244-6 |
| SUBCONTRACTS FOR COMMERCIAL ITEMS |
| JAN 2019 |
| 52.246-11 |
| HIGHER-LEVEL CONTRACT QUALITY REQUIREMENT |
| DEC 2014 |
| 52.246-13 |
| INSPECTION—DISMANTLING, DEMOLITION, OR REMOVAL OF IMPROVEMENTS |
| AUG 1996 |
| 52.246-21 |
| WARRANTY OF CONSTRUCTION ALTERNATE I (APR 1984) |
| MAR 1994 |
| 52.246-21 |
| WARRANTY OF CONSTRUCTION |
| MAR 1994 |
| 52.248-3 |
| VALUE ENGINEERING—CONSTRUCTION |
| OCT 2015 |
| 52.249-1 |
| TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (SHORT FORM) ALTERNATE I (APR 1984) |
| APR 1984 |
| 52.249-3 |
| TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (DISMANTLING, DEMOLITION, OR REMOVAL OF IMPROVEMENTS) |
| APR 2012 |
| 52.249-2 |
| TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED PRICE) ALTERNATE I (SEPT 1996) |
| APR 2012 |
| 52.249-10 |
| DEFAULT (FIXED-PRICE CONSTRUCTION) |
| APR 1984 |
| 52.253-1 |
| COMPUTER GENERATED FORMS |
| JAN 1991 |
| 852.203-70 |
| COMMERCIAL ADVERTISING |
| MAY 2018 |
| 852.228-70 |
| BOND PREMIUM ADJUSTMENT |
| JAN 2008 |
| 852.232-71A |
| PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS– CPM) (NOV 2018) (ALTERNATE I) |
| NOV 2018 |
| 852.236-79 |
| CONTRACTOR PRODUCTION REPORT |
| APR 2019 |
| 852.236-80 |
| SUBCONTRACTS AND WORK COORDINATION |
| APR 2019 |
| 852.236-88 |
| CONTRACT CHANGES--SUPPLEMENT |
| JUL 2002 |
| 852.270-1 |
| REPRESENTATIVES OF CONTRACTING OFFICERS |
| JAN 2008 |
I.2 52.222-42 STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014)
In compliance with the Service Contract Labor Standards statute and the regulations of the Secretary of Labor (29 CFR part 4), this clause identifies the classes of service employees expected to be employed under the contract and states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C. 5341 or 5332.
This Statement is for Information Only:
It is not a Wage Determination
| Employee Class |
| Monetary Wage—Fringe Benefits |
(End of Clause) I.3 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014) The Contractor's representations and certifications, including those completed electronically via the System for Award Management (SAM), are incorporated by reference into the contract.
(End of Clause) I.4 52.204-21 BASIC SAFEGUARDING OF COVERED CONTRACTOR INFORMATION SYSTEMS (JUN 2016)
(a) Definitions. As used in this clause— Covered contractor information system means an information system that is owned or operated by a contractor that processes, stores, or transmits Federal contract information.
Federal contract information means information, not intended for public release, that is provided by or generated for the Government under a contract to develop or deliver a product or service to the Government, but not including information provided by the Government to the public (such as on public Web sites) or simple transactional information, such as necessary to process payments.
Information means any communication or representation of knowledge such as facts, data, or opinions, in any medium or form, including textual, numerical, graphic, cartographic, narrative, or audiovisual (Committee on National Security Systems Instruction (CNSSI) 4009).
Information system means a discrete set of information resources organized for the collection, processing, maintenance, use, sharing, dissemination, or disposition of information (44 U.S.C. 3502).
Safeguarding means measures or controls that are prescribed to protect information systems.
(b) Safeguarding requirements and procedures. (1) The Contractor shall apply the following basic safeguarding requirements and procedures to protect covered contractor information systems. Requirements and procedures for basic safeguarding of covered contractor information systems shall include, at a minimum, the following security controls:
(i) Limit information system access to authorized users, processes acting on behalf of authorized users, or devices (including other information systems).
(ii) Limit information system access to the types of transactions and functions that authorized users are permitted to execute.
(iii) Verify and control/limit connections to and use of external information systems.
(iv) Control information posted or processed on publicly accessible information systems.
(v) Identify information system users, processes acting on behalf of users, or devices.
(vi) Authenticate (or verify) the identities of those users, processes, or devices, as a prerequisite to allowing access to organizational information systems.
(vii) Sanitize or destroy information system media containing Federal Contract Information before disposal or release for reuse.
(viii) Limit physical access to organizational information systems, equipment, and the respective operating environments to authorized individuals.
(ix) Escort visitors and monitor visitor activity; maintain audit logs of physical access; and control and manage physical access devices.
(x) Monitor, control, and protect organizational communications (i.e., information transmitted or received by organizational information systems) at the external boundaries and key internal boundaries of the information systems.
(xi) Implement subnetworks for publicly accessible system components that are physically or logically separated from internal networks.
(xii) Identify, report, and correct information and information system flaws in a timely manner.
(xiii) Provide protection from malicious code at appropriate locations within organizational information systems.
(xiv) Update malicious code protection mechanisms when new releases are available.
(xv) Perform periodic scans of the information system and real-time scans of files from external sources as files are downloaded, opened, or executed.
(2) Other requirements. This clause does not relieve the Contractor of any other specific safeguarding requirements specified by Federal agencies and departments relating to covered contractor information systems generally or other Federal safeguarding requirements for controlled unclassified information (CUI) as established by Executive Order 13556.
(c) Subcontracts. The Contractor shall include the substance of this clause, including…