This document is a request for proposal for building envelope repairs at the Hirshhorn Museum and Sculpture Garden. The Smithsonian Institution intends to award a fixed-price multi-year contract to improve energy performance and waterproofing of the museum's exterior walls and roof. Key aspects of the work include removing existing materials, installing new insulation and waterproofing, fabricating and installing precast concrete panels to match existing designs, replacing balconies, and demolishing and rebuilding the roof. Proposals are due by August 31, 2020 and the contract is targeted for award and completion within 670 calendar days of notice to proceed. Offerors must include pricing for each annual funding increment from 2020 to 2022, schedule of values by CSI division, and cancellation charges. Subcontracting goals include 23% for small businesses and specific targets for small disadvantaged, veteran-owned, HUBZone, and women-owned small businesses.
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
B.2 Availability of Funding
The Smithsonian Institution intends to award a firm fixed-price multi-year contract to the successful
Offeror. Funds are not presently available for performance under this contract beyond an estimated
$4,000,000. The Smithsonian Institution’s obligation under this contract beyond that amount is contingent upon the availability of funds from which payment for contract purposes can be made. This contract may be terminated and no legal liability will accrue against the Smithsonian Institution for any payment(s) that may arise under this contract in excess of $4,000,000, unless and until funds are made available to the
Contracting Officer for continued performance of this contract and the Contractor receives written notice of availability of funds, from the Contracting Officer. The Contractor shall not be obligated to continue performance beyond the funds allocated under this contract. Offerors are reminded that they must include in their proposal a termination cost in the event that subsequent funds are not appropriated. Smithsonian will not be liable for any costs in excess of the termination cost (cancellation charge).
B.3 PRICING
Offerors shall submit pricing for the following lines as contained in section B for each funding increment.
FY 2020 FUNDING INCREMENT: (available through September 30, 2020)
General Conditions (5 months) $___________________ (assumes Jan. distribution of funds)
Scaffolding, Historic Building and Site Protection $_______________
Laser Scan of Existing Building $__________________
Mobilization $___________________
Submittals and shop drawings $___________________
Mock-Ups
SUBTOTAL $___________________
Termination Cost (Cancellation Charge) $___________________
Other – Offerors shall clearly and completely describe items deleted/added to FY2020 Funding Phase
(Attach pages as necessary)
TOTAL-
FY2020____________________________________________________$___________________
(Express in Words and Figures)
FY2021 FUNDING INCREMENT: (10/1/2020 - 09/30/2021) obligated by 12/1/2020 or sooner from
FY2021 appropriation.
General Conditions (12 months) $___________________
Submittals and shop drawings $___________________
Historic Building and Site Protection $_______________
Panel Demolition
Laser Scan of Concrete Drum
Concrete Drum Repair
Insulation
Waterproofing
Mockups
Pre-cast Panel fabrication and installation
Curtail Wall fabrication and installation
Roofing
Balcony and Roof Pavers
FY2021____________________________________________________$___________________
(Express in Words and Figure
SUBTOTAL $___________________
Termination Cost (Cancellation Charge) $___________________
Other – Offerors shall clearly and completely describe items deleted/added to FY2021 Funding Phase $___________________
(Attach pages as necessary)
FY2022 FUNDING INCREMENT: (10/1/2021 - 09/30/2022) obligated by 12/1/2021 or sooner from FY2022 appropriation
General Conditions $___________________
Historic Building Protection $_______________
DeMobilization $___________________
Submittals and shop drawings $___________________
Pre-cast Panel fabrication and installation
Landscaping and Site restoration
Plaza and Concrete Cleaning
Commissioning $___________________
O&M $___________________
As-built documents and Laser Scan $___________________
Project Close-out $___________________
FY2022____________________________________________________$___________________
(Express in Words and Figure
Total Price ______________________________________________ $___________________
Express in words and figures
B.5. Offeror shall, provide pricing as detailed below in the COST PROPOSAL section L.37 and in the attached Bid Schedule (see section J.).
SUBTOTAL $___________________
Termination Cost (Cancellation Charge) $___________________
Other – Offerors shall clearly and completely describe items deleted/added to FY2022 Funding Phase $___________________
(Attach pages as necessary)