3-Allowance Authorization Release Form.pdf.pdf
PDF 229 KB Posted
- Attached to
- Kirby Street Pump Station #08 Rehabilitation
- Solicitation number
- IFB-26-00404
- Issued by
- Hillsborough County, Florida
About this file
This is an Allowance Authorization Release (AAR) form used by Hillsborough County, Florida to document authorized changes to construction contracts. The form provides a standardized template for the County to direct contractors to perform modifications to existing contracts while establishing clear terms regarding cost impacts, time extensions, and compensation. The AAR form captures essential contract information including contractor identification, bid number, and contract reference numbers (CPA and C.I.P), along with designated fields for describing the allowance work to be performed and documenting witness signatures from both the contractor and County representatives, including the applicable department director and approval from Procurement Services and Legal departments.
The form establishes a financial framework for contract modifications by tracking the total allowance work amount, cumulative costs from previous AARs, and remaining balance available for additional work. Critically, the standard AAR terms require the contractor to waive any claims for additional time extensions or monetary compensation beyond the specified allowance amount, thereby limiting the County's financial exposure and establishing cost certainty for each authorized change. The form includes fields for documenting impact days associated with the modifications and requires approval signatures and dates from Hillsborough County Procurement Services and Legal divisions before implementation, ensuring proper authorization and compliance with County procurement procedures.
View the file
Other files
Show all 36
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HILLSBOROUGH COUNTY
ALLOWANCE AUTHORIZATION RELEASE (AAR)
AAR NO.
CONTRACT:
CPA NO. C.I.P NO.
CONTRACTOR: BID NO.
The Contractor is hereby authorized and directed to make the following changes to the above contract, in accordance with all applicable requirements. The Contractor waives any and all claims to additional time extension and/or monetary compensation resulting from these changes and all cost associated with the AAR herein addressed.
COST
DESCRIPTION OF ALLOWANCE WORK TO BE PERFORMED IMPACT DAYS
AMOUNT DAYS
ALLOWANCE WORK INCLUDED IN CONTRACT: $
TOTAL OF ALL PREVIOUS AAR’S: $
BALANCE OF ALLOWANCE WORK AVAILABLE: $
TOTAL ALLOWANCE WORK - THIS AAR: $
REMAINING ALLOWANCE WORK BALANCE: $
CONTRACTOR:
BY: (SEAL)
WITNESS
WITNESS Printed Name & Title
Date
COUNTY: HILLSBOROUGH COUNTY, FLORIDA
BY:
Director, _________________ Department
Date cc: Christine Beck, CAO BOCC Accounting Fiscal & Administrative Support Section
Procurement Services Department File
APPROVAL DATE
PROCUREMENT SVCS.: ____________________ _________
LEGAL: ____________________ _______