260560 - ELECTRICAL TESTING.pdf

PDF 48 KB Posted

Attached to
Amity Middle School Bethany Fire Pump Replacement
Solicitation number
Amity 2025-4
Issued by
Connecticut

About this file

This is a Scope of Work specification document for Section 260560 - Electrical Testing for the Amity Middle School Bethany Fire Pump Replacement project under Amity Regional School District No. 5 in Connecticut. The specification establishes comprehensive requirements for electrical field testing and inspection activities that must be performed as part of the fire pump replacement project. Key requirements include engagement of a qualified independent testing agency, preliminary testing by the contractor including insulation-resistance tests, continuity tests, and rotation tests for motors, and general wiring tests to verify systems are free from short circuits and ground faults. The specification mandates that a NETA Accredited Company perform testing with technicians certified under ANSI/NETA ETT-2010 standards, with each on-site crew leader holding Level III or higher certification. Testing must comply with current ANSI/NETA Standards for Acceptance Testing. Sealed proposals for the overall fire pump replacement project are due no later than Friday, November 14, 2025 at 1:00 P.M., with a mandatory pre-bid walk-through required by appointment only, with no appointments scheduled after 2:00 PM on Friday, November 7, 2025.

The specification requires comprehensive testing documentation including motor performance data, overcurrent protective device settings verified against study parameters, operational testing of all electrical equipment for a minimum one-hour period, and submission of test reports in triplicate to the Engineer. All corrections, replacements, and repairs necessary to achieve acceptable final testing results must be provided by the contractor. The project will include commissioning activities requiring additional labor, materials, and costs to be provided by the contractor. Test equipment must be suitable and properly calibrated per ANSI/NETA standards, and testing personnel must be trained and experienced with safe testing practices and hazard awareness specific to the apparatus and systems being evaluated.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TABLE OF CONTENTS

SECTION 260560 – ELECTRICAL TESTING

PART 1 - GENERAL

1.1 REFERENCES

1.2 SUMMARY

1.3 QUALITY ASSURANCE

PART 2 - NOT USED

PART 3 - EXECUTION

3.1 GENERAL TESTS AND INSPECTIONS

BETHANY MIDDLE SCHOOL JUNE 6, 2025

FIRE PUMP REPLACEMENT VAN ZELM #2024090.00

ELECTRICAL TESTING 260560 - 1

SECTION 260560 - ELECTRICAL TESTING

PART 1 - GENERAL

1.1 REFERENCES

A. This section covers the specification of testing for electrical systems. Refer to Section -

COMMON WORK RESULTS FOR ELECTRICAL WORK, GENERAL CONDITIONS,

SUPPLEMENTARY CONDITIONS, applicable Sections of Division 1, and all other project instructions for other requirements.

B. THIS PROJECT WILL BE COMMISSIONED. REFER TO COMMISSIONING

SPECIFICATION SECTIONS FOR COMMISSIONING INFORMATION AND

RESPONSIBILITIES. THE COMMISSIONING PROCESS WILL REQUIRE ADDITIONAL

LABOR, MATERIAL AND/OR OTHER COSTS WHICH MUST BE PROVIDED BY THE

CONTRACTOR AS PART OF THIS PROJECT.

1.2 SUMMARY

A. This Section includes general requirements for electrical field testing and inspecting.

Additional detailed requirements are specified in each Section containing components that require testing.

B. General requirements include the following:

1. Qualifications of testing agencies and their personnel.

2. Suitability of test equipment.

3. Calibration of test instruments.

4. Coordination requirements for testing and inspecting.

5. Reporting requirements for testing and inspecting.

C. A qualified Testing Agency is to be engaged to perform the required testing.

D. All corrections, replacements, repairs so that final testing report describes all equipment “as-left” as acceptable is to be provided.

1.3 QUALITY ASSURANCE

A. Testing Agency Basic Qualifications: Each Section containing electrical testing may include additional requirements from that specified below.

1. Testing Organization:

a. The testing organization shall be an independent, third party entity which can function as an unbiased testing authority, professionally independent of the manufacturers, suppliers, and installers of equipment or systems being evaluated.

ELECTRICAL TESTING 260560 - 2

b. The testing organization shall be regularly engaged in the testing of electrical equipment devices, installations, and systems.

c. The testing organization shall use technicians who are regularly employed for testing services.

d. An organization having a designation of NETA Accredited Company issued by the InterNational Electrical Testing Association meets the above criteria.

e. The testing organization shall submit appropriate documentation to demonstrate that it satisfactorily complies with these requirements.

2. Testing Personnel:

a. Technicians performing these electrical tests and inspections shall be trained and experienced concerning the apparatus and systems being evaluated. These individuals shall be capable of conducting the tests in a safe manner and with complete knowledge of the hazards involved. They must evaluate the test data and make a judgment on the serviceability of the specific equipment.

b. Technicians shall be certified in accordance with ANSI/NETA ETT-2010, Standard for Certification of Electrical Testing Technicians. Each on-site crew leader shall hold a current certification, Level III or higher, in electrical testing.

B. Test Equipment Suitability: Comply with ANSI/NETA Standards for Acceptance Testing as outlined in Section 5.

C. Test Equipment Calibration: Comply with ANSI/NETA Standards for Acceptance Testing as outlined in Section 5.

D. Acceptance Testing of Electrical Systems: Minimum Standard – Compliance with current Edition of ANSI/NETA Standards for Acceptance Testing as outlined in Section 7.

PART 2 - NOT USED

PART 3 - EXECUTION

3.1 GENERAL TESTS AND INSPECTIONS

A. If a group of tests are specified to be performed by an independent testing agency, prepare systems, equipment, and components for tests and inspections, and perform preliminary tests to ensure that systems, equipment, and components are ready for independent agency testing.

Include the following minimum preparations as appropriate:

1. Perform insulation-resistance tests.

2. Perform continuity tests.

3. Perform rotation test (for motors to be tested).

4. Provide a stable source of single-phase, 208/120-V electrical power for test instrumentation at each test location.

B. General Wiring Tests

ELECTRICAL TESTING 260560 - 3

1. Prior to final inspection and tests: wiring and connections shall be completed, devices and equipment shall be properly operating, power and lighting circuit and control wiring shall be clearly identified with acceptable tags, and lighting fixtures shall be installed, ready for acceptance.

2. Before devices or equipment is energized, test each wiring system for the following:

a. System is free from short circuits.

b. System is free from ground faults.

c. System is at or below 600 V shall have a minimum installation resistance of 100 megohms when tested with 1000 VDC potential between conductors and between conductors and ground, for a minimum of one minute at 70°F ambient air temperature and dry atmosphere (below 55% RH).

d. Grounding paths have been visually confirmed and acceptable maximum resistance to earth tested.

C. Overcurrent Protective Device Setting

1. Manufacturer's Field Service: Engage a factory-authorized service representative, of electrical distribution equipment to perform or supervise the adjustment of settings on overcurrent protective devices within equipment.

2. Testing: Perform the following device setting and prepare reports:

a. After installing overcurrent protective devices and during energizing process of electrical distribution system, perform the following:

1) Verify that overcurrent protective devices meet parameters used in studies.

2) Adjust devices to values listed in study results.

3. Adjust devices according to recommendations in ANSI/NETA Standards for Acceptance Testing as outlined in Chapter 7, and Tables 10.7 and 10.8 in Standard.

D. Motor Tests

1. After systems are balanced and ready to be turned over to the Owner, test and report motor performance data for motors.

2. Include the following information in the test report:

a. Equipment name and/or number.

b. Manufacturer’s nameplate data, including RPM, horsepower, Volts, full-load amperes per phase, service factor, power factor, manufacturer’s name, motor type and model number.

c. Motor test data, including amperes for each phase, average amperes and phase-to-phase voltage at motor, starter or disconnect switch terminals.

d. Percentage of: (average load test amperes) divided by (nameplate full-load amperes).

e. Size, number and ampere rating of overload heaters. Manufacturer’s motor starter heater table.

f. Breaker and disconnect switch data, including size and manufacturer of switches and fuses and branch circuit wiring.

ELECTRICAL TESTING 260560 - 4

E. Operational Tests

1. Each piece of electrical equipment, including lighting fixtures, motors and controls shall be operated continuously for minimum test period of one hour.

2. Demonstrate by operating equipment that circuits and devices are in good operating condition. Each item of control equipment shall be operated minimum of five times.

Demonstration shall be performed after wiring tests.

F. Mechanical System Adjustment and Testing

1. Be present during adjustment period and final testing of mechanical systems. Take readings necessary to ensure that electrical systems are operating properly. Tests for mechanical work are detailed under DIVISION 23, MECHANICAL WORK.

2. Take ampere readings at each electrical component, such as motor and heating coil, to determine proper operation.

3. Record readings and submit them in triplicate to Engineer for review.

G. Test and Inspection Reports: In addition to requirements specified elsewhere, report the following:

1. Manufacturer's written testing and inspecting instructions.

2. Calibration and adjustment settings of adjustable and interchangeable devices involved in tests.

3. Tabulation of expected measurement results made before measurements.

4. Tabulation of "as-found" and "as-left" measurement and observation results.

END OF SECTION

PART 1 -
PART 1 - GENERAL
1.1 REFERENCES
A. This section covers the specification of testing for electrical systems. Refer to Section - COMMON WORK RESULTS FOR ELECTRICAL WORK, GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS, applicable Sections of Division 1, and all other project instruction...
B. THIS PROJECT WILL BE COMMISSIONED. REFER TO COMMISSIONING SPECIFICATION SECTIONS FOR COMMISSIONING INFORMATION AND RESPONSIBILITIES. THE COMMISSIONING PROCESS WILL REQUIRE ADDITIONAL LABOR, MATERIAL AND/OR OTHER COSTS WHICH MUST BE PROVIDED BY THE ...
1.1
1.2 SUMMARY
A. This Section includes general requirements for electrical field testing and inspecting. Additional detailed requirements are specified in each Section containing components that require testing.
B. General requirements include the following:
1. Qualifications of testing agencies and their personnel.
2. Suitability of test equipment.
3. Calibration of test instruments.
4. Coordination requirements for testing and inspecting.
5. Reporting requirements for testing and inspecting.
A.
A.
C. A qualified Testing Agency is to be engaged to perform the required testing.
D. All corrections, replacements, repairs so that final testing report describes all equipment “as-left” as acceptable is to be provided.
1.3 QUALITY ASSURANCE
A. Testing Agency Basic Qualifications: Each Section containing electrical testing may include additional requirements from that specified below.
1. Testing Organization:
a. The testing organization shall be an independent, third party entity which can function as an unbiased testing authority, professionally independent of the manufacturers, suppliers, and installers of equipment or systems being evaluated.
b. The testing organization shall be regularly engaged in the testing of electrical equipment devices, installations, and systems.
c. The testing organization shall use technicians who are regularly employed for testing services.
d. An organization having a designation of NETA Accredited Company issued by the InterNational Electrical Testing Association meets the above criteria.
e. The testing organization shall submit appropriate documentation to demonstrate that it satisfactorily complies with these requirements.
2. Testing Personnel:
a. Technicians performing these electrical tests and inspections shall be trained and experienced concerning the apparatus and systems being evaluated. These individuals shall be capable of conducting the tests in a safe manner and with complete know...
b. Technicians shall be certified in accordance with ANSI/NETA ETT-2010, Standard for Certification of Electrical Testing Technicians. Each on-site crew leader shall hold a current certification, Level III or higher, in electrical testing.
A.
A.
B. Test Equipment Suitability: Comply with ANSI/NETA Standards for Acceptance Testing as outlined in Section 5.
C. Test Equipment Calibration: Comply with ANSI/NETA Standards for Acceptance Testing as outlined in Section 5.
D. Acceptance Testing of Electrical Systems: Minimum Standard – Compliance with current Edition of ANSI/NETA Standards for Acceptance Testing as outlined in Section 7.
PART 2 - NOT USED
PART 3 - EXECUTION
3.1 GENERAL TESTS AND INSPECTIONS
A. If a group of tests are specified to be performed by an independent testing agency, prepare systems, equipment, and components for tests and inspections, and perform preliminary tests to ensure that systems, equipment, and components are ready for ...
1. Perform insulation-resistance tests.
2. Perform continuity tests.
3. Perform rotation test (for motors to be tested).
4. Provide a stable source of single-phase, 208/120-V electrical power for test instrumentation at each test location.
B. General Wiring Tests
1. Prior to final inspection and tests: wiring and connections shall be completed, devices and equipment shall be properly operating, power and lighting circuit and control wiring shall be clearly identified with acceptable tags, and lighting fixture...
2. Before devices or equipment is energized, test each wiring system for the following:
a. System is free from short circuits.
b. System is free from ground faults.
c. System is at or below 600 V shall have a minimum installation resistance of 100 megohms when tested with 1000 VDC potential between conductors and between conductors and ground, for a minimum of one minute at 70 F ambient air temperature and dry at...
d. Grounding paths have been visually confirmed and acceptable maximum resistance to earth tested.
C. Overcurrent Protective Device Setting
1. Manufacturer's Field Service: Engage a factory-authorized service representative, of electrical distribution equipment to perform or supervise the adjustment of settings on overcurrent protective devices within equipment.
2. Testing: Perform the following device setting and prepare reports:
a. After installing overcurrent protective devices and during energizing process of electrical distribution system, perform the following:
1) Verify that overcurrent protective devices meet parameters used in studies.
2) Adjust devices to values listed in study results.

3. Adjust devices according to recommendations in ANSI/NETA Standards for Acceptance Testing as outlined in Chapter 7, and Tables 10.7 and 10.8 in Standard.

D. Motor Tests
1. After systems are balanced and ready to be turned over to the Owner, test and report motor performance data for motors.
2. Include the following information in the test report:
a. Equipment name and/or number.
b. Manufacturer’s nameplate data, including RPM, horsepower, Volts, full-load amperes per phase, service factor, power factor, manufacturer’s name, motor type and model number.
c. Motor test data, including amperes for each phase, average amperes and phase-to-phase voltage at motor, starter or disconnect switch terminals.
d. Percentage of: (average load test amperes) divided by (nameplate full-load amperes).
e. Size, number and ampere rating of overload heaters. Manufacturer’s motor starter heater table.
f. Breaker and disconnect switch data, including size and manufacturer of switches and fuses and branch circuit wiring.
E. Operational Tests
1. Each piece of electrical equipment, including lighting fixtures, motors and controls shall be operated continuously for minimum test period of one hour.
2. Demonstrate by operating equipment that circuits and devices are in good operating condition. Each item of control equipment shall be operated minimum of five times. Demonstration shall be performed after wiring tests.
F. Mechanical System Adjustment and Testing
1. Be present during adjustment period and final testing of mechanical systems. Take readings necessary to ensure that electrical systems are operating properly. Tests for mechanical work are detailed under DIVISION 23, MECHANICAL WORK.
2. Take ampere readings at each electrical component, such as motor and heating coil, to determine proper operation.
3. Record readings and submit them in triplicate to Engineer for review.
G. Test and Inspection Reports: In addition to requirements specified elsewhere, report the following:
1. Manufacturer's written testing and inspecting instructions.
2. Calibration and adjustment settings of adjustable and interchangeable devices involved in tests.
3. Tabulation of expected measurement results made before measurements.
4. Tabulation of "as-found" and "as-left" measurement and observation results.