210510 - PROJECT COORDINATION AND COORDINATION DRAWINGS.pdf
PDF 92 KB Posted
- Solicitation number
- Amity 2025-4
- Issued by
- Connecticut
About this file
This is a Project Coordination and Coordination Drawings specification document (Section 210510) prepared for Amity Regional School District No. 5 in Connecticut for the Bethany Middle School Fire Pump Replacement project. The specification establishes requirements for comprehensive project coordination and the development of coordination drawings that integrate work across multiple trades, including fire protection, HVAC, plumbing, and electrical systems. The document mandates that all trade contractors and sub-contractors collaborate to produce scaled coordination drawings (minimum 1/4" = 1'-0") that accurately represent floor plan layouts, building structure, ceiling systems, equipment placement, piping, ductwork, conduit runs, working clearances, and service connections. The contractor must prepare separate coordination drawings for demolition work, below-slab utilities, site work, and sections through mechanical and electrical rooms. All contractors must sign off on final coordination drawings before installation commences, with periodic updates required to reflect field changes made by Change Order. The specification emphasizes investigation of existing conditions, coordination of investigative work to minimize operational disruption, and adherence to commissioning requirements outlined in Section 019113, including start-up documentation, functional testing, and operator training for fire protection systems.
The specification includes no pricing terms, set-asides, or funding information, as it is a technical requirements document rather than a bid solicitation. The document establishes the contractor's responsibility for managing the coordination process, translating design intent into fabrication drawings, and resolving apparent conflicts in the work through reasonable efforts before involving the Architect/Engineer. The Owner has contracted directly with a Commissioning Agent responsible for coordinating the commissioning team across all design and construction parties. Electronic CAD files of project plans will not be made available to contractors, and BIM model content for mechanical and electrical systems will not be released for contractor coordination purposes.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
SECTION 210510 – PROJECT COORDINATION AND COORDINATION DRAWINGS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
1.2 COMMISSIONING OF FIRE PROTECTION SYSTEMS
1.3 REFERENCES
1.4 INTENT
1.5 SUSTAINABLE DESIGN INTENT
1.6 RELATED SECTIONS
1.7 SEQUENCE OF WORK
1.8 RENOVATIONS & EXISTING CONDITIONS
1.9 AVAILABILITY OF ELECTRONIC FILES
1.10 SUBMITTALS
PART 2 - PRODUCTS
2.1 GENERAL
PART 3 - EXECUTION
3.1 TRADE SPECIFIC LAYOUT AND FABRICATION DRAWINGS
3.2 SITE WORK AND UTILITIES
3.3 BELOW SLAB LAYOUT DRAWINGS
3.4 COORDINATION DRAWINGS – DEMOLITION
3.5 COORDINATION DRAWINGS – NEW WORK
3.6 RISERS, SHAFTS, AND CHASES
3.7 SECTIONS AND ELEVATIONS
BETHANY MIDDLE SCHOOL JUNE 6, 2025
FIRE PUMP REPLACEMENT VAN ZELM #2024090.00
PROJECT COORDINATION AND COORDINATION DRAWINGS 210510 - 1
SECTION 210510 - PROJECT COORDINATION AND COORDINATION DRAWINGS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 COMMISSIONING OF FIRE PROTECTION SYSTEMS
A. Owner's Commissioning Agent
1. The Commissioning Agent (CA) has been contracted directly by Amity Regional School
District 5 for this project. The CA has overall responsibility for planning and coordinating the commissioning process and the commissioning team. The commissioning team is made up of all parties in the design and construction process, including the fire protection (Division 21) contractor and all sub-contractors within
Division 21, plus major equipment suppliers as required.
B. Contractor Responsibility
1. The fire protection (Division 21) contractor's responsibilities are defined in EXHIBIT A -
Detailed Scope Of Work And Related Information, as well as specification Section
019113 – General Commissioning Requirements. These responsibilities apply to all contractors and sub-contractors, plus major equipment suppliers providing equipment for
Division 21. Each contractor and supplier shall review Section 019113 as it applies to each section within the Division 21 specifications, individually and collectively.
C. Commissioning
1. The work of this Section includes meeting the commissioning requirements as specified in Section 019113. The work includes producing start up documentation including pre-functional checklists, operation and maintenance documentation and the training required for the systems.
2. In addition to the startup of equipment and systems, include the time required to be on site to perform functional testing of the equipment and systems being commissioned as specified in the Commissioning Specification in Section 0191
1.3 REFERENCES
A. GENERAL CONDITIONS, SUPPLEMENTARY CONDITIONS and DIVISION 1 paragraphs may be repeated in this Division for emphasis or for inclusion of more stringent/additional related requirements. Such repetition shall NOT be construed to reduce the requirements of those Divisions NOR to eliminate other requirements under those Divisions.
B. Refer to other Sections of this Division for detailed specifications on the work of this Division.
PROJECT COORDINATION AND COORDINATION DRAWINGS 210510 - 2
1.4 INTENT
A. The Contract Documents define a complete installation, comprised of many individual components, assemblies and systems. It is the intent of these documents that the work of all trade contractors, sub-contractors, and all sub-contracted entities performing the work be coordinated to result in finished project, meeting the performance requirements of these documents.
B. The use of the terms “contractor”, “trade contractor”, or “sub-contractor” in this Section is to be interpreted as referring to all trades, singularly and collectively.
C. Definition of roles and responsibilities as pertains to the scope of this section:
1. Contractor:
a. Management, Schedule, and Execution of project coordination and coordination drawing process.
b. Translation of Design Intent and Project requirements, presented within the
Contract Documents, into coordinated layout and fabrication drawings.
c. All reasonable efforts to resolve apparent conflicts in the work, identified in the coordination process, without impact to Design Intent and Project Requirements.
2. Architect/Engineer:
a. Interpretation of Contract Documents
b. Prioritization of Project Requirements where necessary to resolve multiple requirements determined as in conflict after Contractor’s coordination activities are exhausted.
c. Review and assistance with resolution of apparent conflicts identified by
Contractor, provided that reasonable efforts by Contractor have been undertaken to first resolve apparent conflict.
d. Accept or Reject Contractor’s proposed adjustments to the work.
1.5 SUSTAINABLE DESIGN INTENT
A. Comply with project requirements intended to achieve certification, measured and documented according to the LEED Green Building Rating System, of the US Green Building Council.
Refer to Section 018110 – SUSTAINABLE DESIGN REQUIREMENTS for certification level and certification requirements.
1.6 RELATED SECTIONS
A. DIVISION 1 – Section(s) related to Phasing, Construction Schedule, Procedures, and
Coordination of the work. In particular:
1. Section 013100: Project Management and Coordination
2. Section 013129: BIM Coordination
3. Section 013300: Submittal Procedures
4. Section 017823: Operation and Maintenance Data
PROJECT COORDINATION AND COORDINATION DRAWINGS 210510 - 3
5. Section 017839: Project Record Documents
B. DIVISION 21 – Section related to “Project Coordination and Coordination Drawings”
C. DIVISION 22 – Section related to “Project Coordination and Coordination Drawings”
D. DIVISION 23 – Section related to “Project Coordination and Coordination Drawings”
E. DIVISION 26 - Section related to “Project Coordination and Coordination Drawings”
F. DIVISION 27 – Section related to “Project Coordination and Coordination Drawings”
G. DIVISION 28 – Section related to “Project Coordination and Coordination Drawings”
1.7 SEQUENCE OF WORK
A. Before commencement of project coordination and before procurement of materials, Contractor and all sub-Contractors, shall familiarize themselves with the work and requirements of all trades.
B. Phased Sequence of Work:
1. Review phasing plans and requirements set forth in the Contract Documents and any
Supplementary information provided.
2. Identify work that requires careful scheduling in coordination with proposed phasing in order to meet project requirements for completion dates, and operation of systems.
3. Obtain clarifications from Owner and Architect/Engineer on requirements or conditions that directly affect scope work within specific phases of work.
4. Make adjustments to phasing plan and scope or work per phase after review and acceptance by Owner and Architect/Engineer.
C. Project Schedule(s):
1. Review schedules published in the Contract Documents and any supplementary information provided.
2. Coordinate sufficient time allocations in the Contractor’s schedule for Shop Drawing submission and review, Procurement of materials, and the coordination process.
3. Identify elements that will establish the critical path to project completion at the designed date. Adjust schedule of work to accommodate the proper sequence of work as outlined herein.
D. Investigation and Collection of Relevant Information:
1. Review all Contract Documents and referenced standards.
2. Review all Owner requirements.
3. Investigate field conditions as it relates to installation and coordination of work.
4. Identify areas where investigation requiring partial deconstruction of existing or newly constructed work is required to fully inform the Contractor on conditions that are critical to coordination of the work.
PROJECT COORDINATION AND COORDINATION DRAWINGS 210510 - 4
5. Perform investigations in coordination with the work of other trades and/or owner’s use of existing areas.
E. Equipment Shop Drawings:
1. Shop drawings for major equipment and equipment with service connections, should be submitted and accepted prior to coordination drawing efforts in areas adjacent to equipment placement. Information on utility connections, weight and dimensions, access, working clearances, rigging methods, etc are to be represented on the
Coordination Drawings for the specific equipment being installed.
F. Preparation of Coordination Drawings:
1. Coordination Drawings are to be prepared as a collaborative effort between all trade
Contractors working on the project.
2. The following information, as a minimum, is to be represented on the Coordination
Drawing – Floor Plans:
a. Accurately scaled to no smaller than ¼” = 1’-0”.
b. Floor plan layout of walls, doors, windows, etc
c. Building structure, dimensionally accurate with depth and elevation
d. Ceiling systems, ceiling and structure suspended panels/devices, including reference to type of ceiling. Soffits and other ceiling contours represented.
e. HVAC trade work:
1) Ductwork
2) Piping
3) Equipment – base/floor mounted
4) Equipment – suspended
5) Air supply return and exhaust devices and chill beams
6) Valves on distribution systems
7) Control Panels
8) Working clearances
f. Plumbing Trade Work:
1) Sanitary, storm, and vent piping
2) Water piping
3) Valves on distribution systems
4) Equipment – base/floor mounted
5) Equipment – Suspended
6) Distribution of compressed gas systems
7) Laboratory air and laboratory vacuum piping
8) Working clearances
g. Fire Protection Work:
1) Risers, mains, sprinkler and standpipe feed mains, branch piping, and fire department connection piping
2) Heads
3) Hose/valve cabinets
PROJECT COORDINATION AND COORDINATION DRAWINGS 210510 - 5
4) Valves on distribution systems
5) Detectors for special extinguishing systems
6) Service equipment
7) Backflow preventors
8) All alarm check valve assemblies
9) Working Clearances
h. Electrical Trade Work:
1) Electrical distribution equipment
2) Conduit runs for major feeders (panels and major equipment)
3) Branch circuit wiring collection boxes
4) Main telecommunications conduits
5) Pull boxes for major feeders and telecom conduits
6) Cable tray
7) Lighting
8) Ceiling mounted devices such as speakers, detectors, sensors, etc
9) Control panels
10) Working clearances
3. All trades contributing to the development of the Coordination Drawings are to sign off on the final completed documents.
G. Equipment Placement:
1. No equipment is to be placed before all connections and provisions have been verified and coordinated.
2. Working space and clearances for service are to be maintained and verified prior to placement of equipment support provisions such as pads, frames, supports, dunnage, curbs, or anchors.
H. Installation of Work:
1. Work is to be installed in conformance with coordination drawings that have been signed off and accepted.
2. Work installed prior to completion of the Coordination Process will be subject to removal at the Contractor’s expense.
I. Changes made in the field:
1. The Coordination Drawings are to be periodically updated during the project to reflect changes to the work which are made by Change Order or adjustments for other cause.
2. Changes that result in coordination conflicts are to be resolved immediately before related work continues.
1.8 RENOVATIONS & EXISTING CONDITIONS
A. The Contract Documents do not necessarily show all existing conditions, all new work to existing work interfaces, nor the complete extent of patching, repair, and renovation.
PROJECT COORDINATION AND COORDINATION DRAWINGS 210510 - 6
B. Unless otherwise noted, work shall be planned and executed assuming that areas not scheduled at that time to be renovated are intended to be in use and occupied. Existing services must be maintained that serve occupied areas of the building(s) or site.
C. Thoroughly study, examine, and investigate existing field conditions including, but not limited to, conditions in areas of limited accessibility such as crawl spaces, plenums, attics, chases, and above ceilings.
D. Plan and execute investigative work, including selective demolition, of concealed spaces where new work is scheduled to be installed.
E. Coordinate investigative efforts so that the disruption of Owner’s operations is not affected.
Work after Owner’s normal hours of operation may be required and is to be provided.
F. Interruption of building services may only be made after timely notification to Owner and any involved utilities. Advance notification requirements are to be investigated and incorporated into project schedule(s) to avoid impact to the orderly installation of the work.
1.9 AVAILABILITY OF ELECTRONIC FILES
A. Electronic files (CAD) of the project floor or site plans may be available from the project
Architect (or Engineer). Refer to other Sections and Instructions of the Contract Documents to confirm if these will be made available. Unless otherwise stated, assume that electronic files will not be made available.
B. Electronic files (CAD) of the project’s Mechanical and Electrical Contract Documents will not be made available unless otherwise stated.
C. Electronic Files for BIM Projects (where applicable). BIM Model content related to the
Mechanical and Electrical systems will not be released for the purposes of coordination by the contractor.
1.10 SUBMITTALS
A. Submittal of Coordination Drawings to be made with sufficient time planned for review and revision. The potential for additional steps of coordination prior to the scheduled commencement of work should be anticipated.
B. Separately developed Coordination Drawings may be required for elements of the work. Refer to requirements outlined later in this Section.
C. Refer to other Sections and Divisions of these Specifications for other related Submittal requirements.
PROJECT COORDINATION AND COORDINATION DRAWINGS 210510 - 7
PART 2 - PRODUCTS
2.1 GENERAL
A. No specific materials are specified in this section. Refer to other sections of this Division and other Divisions of the Specifications for material specifications.
PART 3 - EXECUTION
3.1 TRADE SPECIFIC LAYOUT AND FABRICATION DRAWINGS
A. Trade or system specific layout drawings may be required in other Section of this and other
Divisions. Content that is common between these layout drawings and requirements for the
Coordination Drawings shall be coordinated and developed in parallel where practical.
3.2 SITE WORK AND UTILITIES
A. Coordination Drawing prepared reflecting:
1. Underground site utilities, size and invert
2. Site Structures for Utility Distribution, size, placement, invert
3.3 BELOW SLAB LAYOUT DRAWINGS
A. Coordinated drawing which includes all below slab utilities and distribution. Indicate dimensions and invert of all services. Include the following as a minimum:
1. Sanitary, Storm and Vent Piping
2. Electrical Conduits
3. Sumps, Drains, and other equipment that extends below the floor plane
4. Structural footing
5. Under slab and footing and drainage piping
6. All other Mechanical or Electrical services below areas of slab on grade
3.4 COORDINATION DRAWINGS – DEMOLITION
A. For renovation projects that require selective demolition, prepare a separate coordination drawing indicating:
1. Points of cut/cap for existing systems to remain
2. Major equipment removals and associated services
PROJECT COORDINATION AND COORDINATION DRAWINGS 210510 - 8
3.5 COORDINATION DRAWINGS – NEW WORK
A. Coordination Drawings prepared as indicated in this Section.
3.6 RISERS, SHAFTS, AND CHASES
A. Provide sections of all risers that extend beyond two floor levels of the building.
3.7 SECTIONS AND ELEVATIONS
A. Minimum of 1 longitudinal and 1 cross section through every Mechanical Room and Major
Electric Service and Distribution Room
B. Cross sections to be provided in areas on congestion where services are stacked in elevation.
END OF SECTION