26-8672_-_Bid_Schedule_R7.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- Collier Senior Center Expansion Project
- Solicitation number
- 26-8672
- Issued by
- Collier County, Florida
About this file
This is a bid schedule for ITB No. 26-8672, the Collier Senior Center Expansion Project, issued by Collier County Board of County Commissioners in Florida. The project encompasses three construction scopes: Scope A involves new construction of a 2,710 square-foot addition to the existing 7,120 square-foot Senior Center located at 4898 Coronado Parkway, Naples, Florida, including a conference room, IT room, storage, restrooms, office space, and advanced air-filtration mechanical systems; Scope B covers hardening of the existing building to achieve current code-required wind load resistance through roof replacement, impact-rated openings, wall reinforcement, HVAC upgrades, electrical work, fire suppression systems, and site improvements; and Scope C addresses relocation and storage services for Senior Center contents during construction. The bid schedule itemizes construction components under Scope A (building construction with 19 line items and site construction with 9 line items), Scope B (building construction with 17 line items and site construction with 8 line items), and Scope C (moving and relocation services including on-site and off-site storage, moving services, and unskilled labor for 1,540 hours). Sealed electronic bids were due August 31, 2026 at 3:00 p.m., with a non-mandatory pre-bid conference scheduled for July 28, 2026 at 11:00 a.m. Substantial completion is required within 456 calendar days from Notice to Proceed, with final completion within 30 calendar days thereafter.
The anticipated project budget is $5,600,000, with the project partially grant-funded through the Community Development Block Grant Mitigation Program (CDBG-MIT). Owner's Allowances have been allocated at $203,919.90 for Scope A and $300,685.80 for Scope B to address unforeseen conditions at the Owner's discretion through Change Order. A five-percent bid bond is required at submission, and upon award, the successful bidder must provide Payment and Performance Bonds at 100 percent of contract value within ten calendar days of Notice of Award. Contractors must be Florida State Certified General Contractors and hold all required licenses, with liquidated damages set at $1,839 per day for failure to achieve substantial completion. Federal provisions apply, including Davis-Bacon prevailing wage requirements, E-Verify compliance, Section 3 housing employment preferences, and participation goals of 17.1 percent for minority and 6.9 percent for female participation. A local-vendor preference utilizing Choice2 applies to this solicitation. Required insurance includes Worker's Compensation, Commercial General Liability ($1,000,000 single limit / $2,000,000 aggregate), Employer's Liability ($1,000,000), and Automobile Liability ($1,000,000). Bidders must provide five project references demonstrating similar experience within the last five years and identify key personnel including Construction Superintendent and Project Manager.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
26-8672 BID SCHEDULE
| COLLIER SENIOR CENTER EXPANSION PROJECT | |||||
| NEW CONSTRUCTION - SCOPE A | |||||
| CONSTRUCTION ITB NO. 26-8672 | |||||
| BID SCHEDULE | |||||
| Vendor Name: | |||||
| BUILDING CONSTRUCTION | |||||
| ITEM NO. | DESCRIPTION | QTY | UNIT | UNIT COST | TOTAL |
| 1 | General Requirements | 1 | LS | $ - 0 | $ - 0 |
| 2 | Concrete | 1 | LS | $ - 0 | $ - 0 |
| 3 | Masonry | 1 | LS | $ - 0 | $ - 0 |
| 4 | Metals | 1 | LS | $ - 0 | $ - 0 |
| 5 | Wood / Plastic / Composites | 1 | LS | $ - 0 | $ - 0 |
| 6 | Thermal & Moisture Protection (Including Roofing) | 1 | LS | $ - 0 | $ - 0 |
| 7 | Openings | 1 | LS | $ - 0 | $ - 0 |
| 8 | Exterior Wall Finishes | 1 | LS | $ - 0 | $ - 0 |
| 9 | Interior Finishes | 1 | LS | $ - 0 | $ - 0 |
| 10 | Specialties | 1 | LS | $ - 0 | $ - 0 |
| 11 | Line Item Removed - Do Not Calculate | 0 | 0 | $ - 0 | |
| 12 | Window blinds | 1 | LS | $ - 0 | $ - 0 |
| 13 | Fire Suppression System | 1 | LS | $ - 0 | $ - 0 |
| 14 | Plumbing | 1 | LS | $ - 0 | $ - 0 |
| 15 | HVAC | 1 | LS | $ - 0 | $ - 0 |
| 16 | Electrical | 1 | LS | $ - 0 | $ - 0 |
| 17 | Line Item Removed - Do Not Calculate | 1 | LS | $ - 0 | $ - 0 |
| 18 | Technology Systems | 1 | LS | $ - 0 | $ - 0 |
| 19 | Pole Exterior Lighting | 1 | LS | $ - 0 | $ - 0 |
| SCOPE A - TOTAL BUILDING CONSTRUCTION: | $ - 0 |
| SITE CONSTRUCTION | |||||
| ITEM NO. | DESCRIPTION | QTY | UNIT | UNIT COST | TOTAL |
| 20 | General Requirements | 1 | LS | $ - 0 | $ - 0 |
| 21 | Earthwork | 1 | LS | $ - 0 | $ - 0 |
| 22 | Exterior On Site Improvements | 1 | LS | $ - 0 | $ - 0 |
| 23 | Landscape/Irrigation | 1 | LS | $ - 0 | $ - 0 |
| 24 | Domestic Water | 1 | LS | $ - 0 | $ - 0 |
| 25 | Sanitary | 1 | LS | $ - 0 | $ - 0 |
| 26 | Line Item Removed - Do Not Calculate | 0 | 0 | $ - 0 | $ - 0 |
| 27 | Storm Drainage | 1 | LS | $ - 0 | $ - 0 |
| 28 | Technology | 1 | LS | $ - 0 | $ - 0 |
| SCOPE A - TOTAL SITE CONSTRUCTION: | $ - 0 | ||||
| SCOPE A - TOTAL CONSTRUCTION (BUILDING + SITE) BID AMOUNT: | $ - 0 |
| COLLIER SENIOR CENTER HARDENING & EXPANSION PROJECT |
| HARDENING EXISTING - SCOPE B |
| CONSTRUCTION ITB NO. 26-8672 |
| BID SCHEDULE |
| BUILDING CONSTRUCTION | |||||
| ITEM NO. | DESCRIPTION | QTY | UNIT | UNIT COST | TOTAL |
| 29 | General Requirements | 1 | LS | $ - 0 | $ - 0 |
| 30 | Existing Conditions | 1 | LS | $ - 0 | $ - 0 |
| 31 | Concrete | 1 | LS | $ - 0 | $ - 0 |
| 32 | Rebar install at exterior CMU (see note B. on drawing sheet S1.0) | 690 | LF | $ - 0 | $ - 0 |
| 33 | Wood / Plastic / Composites | 1 | LS | $ - 0 | $ - 0 |
| 34 | Thermal & Moisture Protection (including Roofing) | 1 | LS | $ - 0 | $ - 0 |
| 35 | Openings | 1 | LS | $ - 0 | $ - 0 |
| 36 | Exterior Wall Finishes | 1 | LS | $ - 0 | $ - 0 |
| 37 | Interior Finishes | 1 | LS | $ - 0 | $ - 0 |
| 37b | Rebar installation locations | 54 | EA | $ - 0 | $ - 0 |
| 38 | Specialties | 1 | LS | $ - 0 | $ - 0 |
| 39 | GPR scan of exterior CMU walls | 1 | LS | $ - 0 | $ - 0 |
| 40 | Window blinds | 1 | LS | $ - 0 | $ - 0 |
| 41 | Fire Suppression System | 1 | LS | $ - 0 | $ - 0 |
| 42 | Plumbing | 1 | LS | $ - 0 | $ - 0 |
| 43 | HVAC | 1 | LS | $ - 0 | $ - 0 |
| 44 | Electrical/Emergency Power sys | 1 | LS | $ - 0 | $ - 0 |
| 45 | Technology Systems | 1 | LS | $ - 0 | $ - 0 |
| SCOPE B - TOTAL BUILDING CONSTRUCTION: | $ - 0 |
| SITE CONSTRUCTION | |||||
| ITEM NO. | DESCRIPTION | QTY | UNIT | UNIT COST | TOTAL |
| 46 | General Requirements | 1 | LS | $ - 0 | $ - 0 |
| 47 | Existing Conditions | 1 | LS | $ - 0 | $ - 0 |
| 48 | Earthwork | 1 | LS | $ - 0 | $ - 0 |
| 49 | Exterior On Site Improvements | 1 | LS | $ - 0 | $ - 0 |
| 50 | Landscape/Irrigation | 1 | LS | $ - 0 | $ - 0 |
| 51 | Domestic Water | 1 | LS | $ - 0 | $ - 0 |
| 52 | Sanitary | 1 | LS | $ - 0 | $ - 0 |
| 53 | Storm Drainage | 1 | LS | $ - 0 | $ - 0 |
| SCOPE B - TOTAL SITE CONSTRUCTION: | $ - 0 | ||||
| SCOPE B TOTAL BASE (BUILDING + SITE CONSTRUCTION) BID AMOUNT: | $ - 0 |
| COLLIER SENIOR CENTER HARDENING & EXPANSION PROJECT |
| SCOPE C |
| CONSTRUCTION ITB NO. 26-8672 |
| BID SCHEDULE |
| SCOPE C | |||||
| ITEM NO. | DESCRIPTION | # OF UNITS | UNIT | UNIT COST | TOTAL |
| 54 | On-site Storage Container 16' X 8' X 8' (Quantity 1) | 1 | LS | $ - 0 | $ - 0 |
| 55 | Off-site Storage Up to 400 Square Feet of Air Conditioned Storage | 1 | LS | $ - 0 | $ - 0 |
| 56 | Movers for Relocation of Contents | 1 | LS | $ - 0 | $ - 0 |
| 57 | Unskilled labor for daily senior center breakdown for temporary location | 1,540 | HR | $ - 0 | $ - 0 |
| SCOPE C - MOVING & RELOCATION AMOUNT: | $ - 0 |
| BID SUMMARY | |
| SCOPE A - BID AMOUNT (BUILDING + SITE CONSTRUCTION): | $ - 0 |
| SCOPE B - BID AMOUNT (HARDENING EXISTING): | $ - 0 |
| SCOPE C - NON-GRANT MOVING & RELOCATION COSTS: | $ - 0 |
| GRAND TOTAL SCOPE A + SCOPE B + SCOPE C: | $ - 0 |
| Owner Allowance |
| Staff has allocated $203,919.90 in Owner's Allowance for Scope A - for Owners Use as Directed. |
Staff has allocated $300,685.80 in Owner's Allowance for Scope B - for Owners Use as Directed.
These Allowances will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.
NOTE: Contractors are responsible for reviewing all bid documents and providing qualified responses to be considered. Line items 11, 17 & 26 have been intentionally zero‑valued. Vendor should not add values to these lines.