About this file
This is a bid schedule for ITB No. 26-8672 for the Collier Senior Center Expansion Project in Naples, Florida, a project designed by PBK Architects that adds 2,710 square feet to the existing 7,120 square foot Senior Center. The project encompasses three distinct scopes: Scope A covers new construction for the building and site improvements; Scope B addresses hardening and weatherproofing of the existing facility; and Scope C includes moving and relocation costs. Scope A construction consists of 19 line items covering general requirements, concrete, masonry, metals, wood/plastic composites, thermal and moisture protection, openings, exterior and interior finishes, specialties, window blinds, fire suppression, plumbing, HVAC, electrical, technology systems, and exterior lighting for building construction, plus eight line items for site construction including earthwork, landscaping, irrigation, water, sanitary, storm drainage, and technology. Scope B contains 17 building construction line items including existing conditions assessment, concrete, rebar installation totaling 690 linear feet, thermal protection, openings, finishes, GPR scanning of exterior concrete masonry unit walls, systems for fire suppression, plumbing, HVAC, electrical and emergency power, and technology, along with eight site construction line items. Scope C includes provisions for on-site and off-site storage containers, movers for relocation of contents, and 192 hours of unskilled labor for senior center breakdown activities.
The bid schedule identifies all line items using lump sum (LS) pricing except for Scope B Item 32 (rebar installation) and Scope C Item 57 (labor) which employ unit-based pricing. Owner's Allowances of $203,919.90 for Scope A and $300,685.80 for Scope B have been allocated for use at the owner's direction to address unforeseen conditions, with expenditures managed through change orders with supporting documentation. The project is partially grant-funded and requires an expedited construction schedule with the Senior Center vacant during construction, while surrounding facilities including the Golden Gate Community Center, Golden Gate Public Library, Sheriff's office, Tax Collector, BMX/Skate Park, and Fire Rescue Station #70 remain operational. Line items 11 and 26 have been intentionally zero-valued and contractors are instructed not to assign values to these lines.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
26-8672 BID SCHEDULE
| COLLIER SENIOR CENTER EXPANSION PROJECT | |||||
| NEW CONSTRUCTION - SCOPE A | |||||
| CONSTRUCTION ITB NO. 26-8672 | |||||
| BID SCHEDULE | |||||
| Vendor Name: | |||||
| BUILDING CONSTRUCTION | |||||
| ITEM NO. | DESCRIPTION | QTY | UNIT | UNIT COST | TOTAL |
| 1 | General Requirements | 1 | LS | $ - 0 | |
| 2 | Concrete | 1 | LS | $ - 0 | |
| 3 | Masonry | 1 | LS | $ - 0 | |
| 4 | Metals | 1 | LS | $ - 0 | |
| 5 | Wood / Plastic / Composites | 1 | LS | $ - 0 | |
| 6 | Thermal & Moisture Protection | 1 | LS | $ - 0 | |
| 7 | Openings | 1 | LS | $ - 0 | |
| 8 | Exterior Wall Finishes | 1 | LS | $ - 0 | |
| 9 | Interior Finishes | 1 | LS | $ - 0 | |
| 10 | Specialties | 1 | LS | $ - 0 | |
| 11 | Line Item Removed - Intentional Zero | 0 | 0 | $ - 0 | $ - 0 |
| 12 | Window blinds | 1 | LS | $ - 0 | |
| 13 | Fire Suppression System | 1 | LS | $ - 0 | |
| 14 | Plumbing | 1 | LS | $ - 0 | |
| 15 | HVAC | 1 | LS | $ - 0 | |
| 16 | Electrical | 1 | LS | $ - 0 | |
| 17 | Not Used | 1 | LS | $ - 0 | |
| 18 | Technology Systems | 1 | LS | $ - 0 | |
| 19 | Pole Exterior Lighting | 1 | LS | $ - 0 | |
| SCOPE A - TOTAL BUILDING CONSTRUCTION: | $ - 0 |
| SITE CONSTRUCTION | |||||
| ITEM NO. | DESCRIPTION | QTY | UNIT | UNIT COST | TOTAL |
| 20 | General Requirements | 1 | LS | $ - 0 | |
| 21 | Earthwork | 1 | LS | $ - 0 | |
| 22 | Exterior On Site Improvements | 1 | LS | $ - 0 | |
| 23 | Landscape/Irrigation | 1 | LS | $ - 0 | |
| 24 | Domestic Water | 1 | LS | $ - 0 | |
| 25 | Sanitary | 1 | LS | $ - 0 | |
| 26 | Line Item Removed - Intentional Zero | 0 | 0 | $ - 0 | $ - 0 |
| 27 | Storm Drainage | 1 | LS | $ - 0 | |
| 28 | Technology | 1 | LS | $ - 0 | |
| SCOPE A - TOTAL SITE CONSTRUCTION: | $ - 0 | ||||
| SCOPE A - TOTAL CONSTRUCTION (BUILDING + SITE) BID AMOUNT: | $ - 0 |
| COLLIER SENIOR CENTER HARDENING & EXPANSION PROJECT |
| HARDENING EXISTING - SCOPE B |
| CONSTRUCTION ITB NO. 26-8672 |
| BID SCHEDULE |
| BUILDING CONSTRUCTION | |||||
| ITEM NO. | DESCRIPTION | QTY | UNIT | UNIT COST | TOTAL |
| 29 | General Requirements | 1 | LS | $ - 0 | |
| 30 | Existing Conditions | 1 | LS | $ - 0 | |
| 31 | Concrete | 1 | LS | $ - 0 | |
| 32 | Rebar install at exterior CMU (see note B. on drawing sheet S1.0) | 690 | LF | $ - 0 | |
| 33 | Wood / Plastic / Composites | 1 | LS | $ - 0 | |
| 34 | Thermal & Moisture Protection | 1 | LS | $ - 0 | |
| 35 | Openings | 1 | LS | $ - 0 | |
| 36 | Exterior Wall Finishes | 1 | LS | $ - 0 | |
| 37 | Interior Finishes | 1 | LS | $ - 0 | |
| 38 | Specialties | 1 | LS | $ - 0 | |
| 39 | GPR scan of exterior CMU walls | 1 | LS | $ - 0 | |
| 40 | Window blinds | 1 | LS | $ - 0 | |
| 41 | Fire Suppression System | 1 | LS | $ - 0 | |
| 42 | Plumbing | 1 | LS | $ - 0 | |
| 43 | HVAC | 1 | LS | $ - 0 | |
| 44 | Electrical/Emergency Power sys | 1 | LS | $ - 0 | |
| 45 | Technology Systems | 1 | LS | $ - 0 | |
| SCOPE B - TOTAL BUILDING CONSTRUCTION: | $ - 0 |
| SITE CONSTRUCTION | |||||
| ITEM NO. | DESCRIPTION | QTY | UNIT | UNIT COST | TOTAL |
| 46 | General Requirements | 1 | LS | $ - 0 | |
| 47 | Existing Conditions | 1 | LS | $ - 0 | |
| 48 | Earthwork | 1 | LS | $ - 0 | |
| 49 | Exterior On Site Improvements | 1 | LS | $ - 0 | |
| 50 | Landscape/Irrigation | 1 | LS | $ - 0 | |
| 51 | Domestic Water | 1 | LS | $ - 0 | |
| 52 | Sanitary | 1 | LS | $ - 0 | |
| 53 | Storm Drainage | 1 | LS | $ - 0 | |
| SCOPE B - TOTAL SITE CONSTRUCTION: | $ - 0 | ||||
| SCOPE B TOTAL BASE (BUILDING + SITE CONSTRUCTION) BID AMOUNT: | $ - 0 |
| COLLIER SENIOR CENTER HARDENING & EXPANSION PROJECT |
| SCOPE C |
| CONSTRUCTION ITB NO. 26-8672 |
| BID SCHEDULE |
| SCOPE C | |||||
| ITEM NO. | DESCRIPTION | # OF UNITS | UNIT | UNIT COST | TOTAL |
| 54 | On-site Storage Container 16' X 8' X 8' (Quantity 1) | 1 | LS | $ - 0 | |
| 55 | Off-site 10' X 10' Storage Unit | 1 | LS | $ - 0 | |
| 56 | Movers for Relocation of Contents | 1 | LS | $ - 0 | |
| 57 | Unskilled labor for daily senior center breakdown for temporary location | 192 | HR | $ - 0 | |
| SCOPE C - MOVING & RELOCATION AMOUNT: | $ - 0 |
| BID SUMMARY | |
| SCOPE A - BID AMOUNT (BUILDING + SITE CONSTRUCTION): | $ - 0 |
| SCOPE B - BID AMOUNT (HARDENING EXISTING): | $ - 0 |
| SCOPE C - NON-GRANT MOVING & RELOCATION COSTS: | $ - 0 |
| GRAND TOTAL SCOPE A + SCOPE B + SCOPE C: | $ - 0 |
| Owner Allowance |
| Staff has allocated $203,919.90 in Owner's Allowance for Scope A - for Owners Use as Directed. |
Staff has allocated $300,685.80 in Owner's Allowance for Scope B - for Owners Use as Directed.
These Allowances will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.
NOTE: Contractors are responsible for reviewing all bid documents and providing qualified responses to be considered. Line items 11 & 26 have been intentionally zero‑valued. Vendor should not add values to these lines.
File details come from the government source that posted it. Updated .