About this file

This is an Insurance Requirements Form issued by the Collier County Board of County Commissioners for ITB #26-8632, a grant-funded Beach Compatible Sand Supply contract. The procurement seeks qualified bidders to supply approximately 75,000 tons per year of beach-compatible sand for coastal re-nourishment and erosion control projects, with individual projects potentially requiring up to 225,000 tons and multiple projects scheduled annually. Sand must comply with Florida Department of Environmental Protection Permit JCP 0331817-001-JC requirements and meet specified technical standards including a preferred Munsell Color Value of 8 for moist samples. Delivery is to Lowdermilk Park in Naples, Florida. Bids are due February 26, 2026, at 3:00 PM EST and must be submitted electronically through the Collier County Procurement Services Division Online Bidding System. The contract term is three years with two optional one-year renewal periods, with prices remaining firm during the initial term and subject to annual increase requests thereafter with 30-day advance notice and Procurement Director approval.

Bidders must provide pricing on a unit cost basis with an adjustment factor of $0.20 per ton per mile, calculated from the shortest allowable truck route from the mining operation to the delivery location. All contractors must maintain workers' compensation coverage in accordance with Florida Statutes Chapter 440, employer's liability insurance with statutory limits, commercial general liability insurance with limits of $1,000,000 per occurrence and $2,000,000 aggregate, and automobile liability coverage. A 5 percent Bid Bond must be submitted with the proposal. For contracts exceeding $200,000, Performance and Payment Bonds equal to 100 percent of the contract award amount are required, underwritten by sureties rated A- or better by A.M. Best Company. The contract is grant-funded and requires compliance with federal requirements including 2 CFR Part 200 and FEMA regulations. Three upland sand sources are currently approved: Stewart's Immokalike mine, Vulcan's Witherspoon mine, and CEMEX's Lake Wales mine. The County intends to award to the lowest responsive and responsible bidder and may select one or more bidders on a line-item basis, establishing Primary, Secondary, and Tertiary awardees. Local vendor preference eligibility applies to Collier County and Lee County business tax receipt holders, and all bidders must be enrolled in E-Verify at the time of bid submission.

View the file

Other files

File Type Posted
Form_2_Conflict_of_Interest_Certification.pdf PDF
Checklist_-_Vendor_Checklist_.pdf PDF
Form_1_Vendor_Declaration_Statement.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
Form_4_Reference_Questionnaire.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
Checklist_-_Vendor_Checklist_.pdf PDF
Form_1_Vendor_Declaration_Statement.pdf PDF
26-8632_Insurance_Requirements_Version_2_FE.pdf PDF
Form_2_Conflict_of_Interest_Certification.pdf PDF
Checklist_-_Vendor_Checklist_.pdf PDF
Form_1_Vendor_Declaration_Statement.pdf PDF
Form_4_Reference_Questionnaire.pdf PDF
Multi-Contractor_Award_Agreement_2025_ver.4_-_Fillable.pdf PDF
Form_4_Reference_Questionnaire.pdf PDF
Multi-Contractor_Award_Agreement_2025_ver.4_-_Fillable.pdf PDF
Form_2_Conflict_of_Interest_Certification.pdf PDF
Multi-Contractor_Award_Agreement_2025_ver.4_-_Fillable.pdf PDF
26-8632_Grant_Provisions.pdf PDF
26-8632_Insurance_Requirements_Version_2_FE.pdf PDF
Form_3_Immigration_Certification.pdf PDF
Checklist_-_Vendor_Checklist_.pdf PDF
Form_3_Immigration_Certification.pdf PDF
26-8632_Bid_Schedule.xlsx XLSX spreadsheet
26-8632_-_Attachment_1_Truck_Haul_Routes.pdf PDF
26-8632_-_Attachment_2_-_Sediment_QAQC_Plan.pdf PDF
26-8632_Grant_Provisions.pdf PDF
26-8632_Solicitation_.pdf PDF
Invitation_to_Bid_Instructions_Version_2.pdf PDF
Multi-Contractor_Award_Agreement_2025_ver.4_-_Fillable.pdf PDF
26-8632_-_ATA.pdf PDF
26-8632_-_Attachment_1_Truck_Haul_Routes.pdf PDF
26-8632_Solicitation_.pdf PDF
Invitation_to_Bid_Instructions_Version_2.pdf PDF
26-8632_-_Attachment_2_-_Sediment_QAQC_Plan.pdf PDF
26-8632_Solicitation_.pdf PDF
26-8632_-_ATA.pdf PDF
Invitation_to_Bid_Instructions_Version_2.pdf PDF
26-8632_Bid_Schedule.xlsx XLSX spreadsheet
Form_1_Vendor_Declaration_Statement.pdf PDF
26-8632_-_Attachment_2_-_Sediment_QAQC_Plan.pdf PDF
Invitation_to_Bid_Instructions_Version_2.pdf PDF
26-8632_Bid_Schedule.xlsx XLSX spreadsheet
26-8632_Solicitation_.pdf PDF
26-8632_-_ATA.pdf PDF
26-8632_-_Attachment_1_Truck_Haul_Routes.pdf PDF
26-8632_Insurance_Requirements_Version_2_FE.pdf PDF
Form_4_Reference_Questionnaire.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
26-8632_Bid_Schedule.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Version 2 10.2.25

Solicitation Number, Services, or Products Being Procured:

Insurance / Bond Type Required Limits

Worker’s Compensation Statutory Limits of Florida Statutes, Chapter 440 and all Federal Government Statutory Limits and Requirements

Evidence of Workers’ Compensation coverage or a Certificate of Exemption issued by the State of Florida is required. Entities that are formed as Sole Proprietorships shall not be required to provide a proof of exemption. An application for exemption can be obtained online at https://apps.fldfs.com/bocexempt/

1.

Employer’s Liability $ single limit per occurrence

3. Commercial General Liability (Occurrence Form) patterned after the current ISO form

Bodily Injury and Property Damage

$ single limit per occurrence, $2,000,000 aggregate for Bodily Injury Liability and Property Damage Liability. The General Aggregate Limit shall be endorsed to apply per project. This shall include Premises and Operations; Independent Contractors; Products and Completed Operations and Contractual Liability.

4. Indemnification To the maximum extent permitted by Florida law, the Contractor/Vendor shall defend, indemnify and hold harmless Collier County, its officers and employees from any and all liabilities, damages, losses and costs, including, but not limited to, reasonable attorneys’ fees and paralegals’ fees, to the extent caused by the negligence, recklessness, or intentionally wrongful conduct of the Contractor/ Vendor or anyone employed or utilized by the Contractor/Vendor in the performance of this Agreement.

5. Automobile Liability $ Each Occurrence; Bodily Injury & Property Damage Owned/Non-owned/Hired; Automobile Included

6 Other insurance as noted: Watercraft $ Per Occurrence

United States Longshoreman's and Harborworker's Act coverage shall be maintained where applicable to the completion of the work.

$ Per Occurrence

Maritime Coverage (Jones Act) shall be maintained where applicable to the completion of the work.

$ Per Occurrence

Aircraft Liability coverage shall be carried in limits of not less than $5,000,000 each occurrence if applicable to the completion of the Services under this Agreement.

$ Per Occurrence

☐Umbrella/Excess Coverage $_____________ Per Occurrence

Pollution $ Per Occurrence

Professional Liability $ Per claim & in the aggregate

Cyber Liability $ Per Occurrence Valuable

$ Per Occurrence

$ __ Per Occurrence

Technology Errors & Omissions

Other:

Other: $ __ Per Occurrence

☐Other: $____________ Per Occurrence

INSURANCE AND BONDING REQUIREMENTS FORM

2.

https://apps.fldfs.com/bocexempt/ emily jackson Rectangle

Version 2 10.2.25

7. Bid Bond Shall be submitted with the proposal response in the form of proposal bond in a sum equal to 5% of the cost proposal.

8. Performance and Payment Bonds

For projects in excess of $200,000, bonds shall be submitted with the executed contract by Proposers receiving award, and written for 100% of the Contract award amount, the cost borne by the Bidder receiving an award. The Performance and Payment Bonds shall be underwritten by a surety authorized to do business in the State of Florida and otherwise acceptable to Owner; provided, however, the surety shall be rated as “A-“ or better as to general policy holders rating and Class V or higher rating as to financial size category and the amount required shall not exceed 5% of the reported policy holders’ surplus, all as reported in the most current Best Key Rating Guide, published by A.M.

Best Company, Inc. of 75 Fulton Street, New York, New York 10038.

9. Vendor shall ensure that all subcontractors comply with the same insurance requirements that he is required to meet. The same Vendor shall provide County with certificates of insurance meeting the required insurance provisions.

10. Collier County must be named as "ADDITIONAL INSURED" on the Insurance Certificate for Commercial General Liability where required. This insurance shall be primary and non-contributory with respect to any other insurance maintained by, or available for the benefit of, the Additional Insured and the Vendor’s policy shall be endorsed accordingly.

11. The Certificate Holder shall be named as Collier County Board of County Commissioners, OR, Board of County Commissioners in Collier County, OR Collier County Government, OR Collier County. The Certificates of Insurance must state the Contract Number, or Project Number, or specific Project description, or must read: For any and all work performed on behalf of Collier County.

12. On all certificates, the Certificate Holder must read: Collier County Board of County Commissioners, 3295 Tamiami Trail East, Naples, FL 34112

13. Thirty (30) Days Cancellation Notice required.

14. Collier County shall procure and maintain Builders Risk Insurance on all construction projects where it is deemed necessary. Such coverage shall be endorsed to cover the interests of Collier County as well as the Contractor. Premiums shall be billed to the project and the Contractor shall not include Builders Risk premiums in its project proposal or project billings. All questions regarding Builder’s Risk Insurance will be addressed by the Collier County Risk Management Division.

Approved by: Signature:

BIDDER/PROPOSER’S INSURANCE ACCEPTANCE

By submission of the bid/proposal Bidder/Proposer accepts and understands the insurance requirements of these specifications and that the evidence of insurability may be required within five (5) days of the award of this solicitation. The insurance submitted must provide coverage for a minimum of six (6) months from the date of the award.

BIDDER/PROPOSER’S INSURANCE ACCEPTANCE

undefined: 1,000,000
Commercial General: On
undefined_2: 1,000,000
Indemnification: On
Automobile Liability: On
Other insurance as noted: Off
undefined_3: 1,000,000
undefined_4:
Watercraft: Off
United States Longshoremans and Harborworkers Act coverage shall be maintained: Off
undefined_5:
Maritime Coverage Jones Act shall be maintained where applicable to the: Off
undefined_6:
Aircraft Liability coverage shall be carried in limits of not less than 5000000 each: Off
undefined_7:
undefined_8:
UmbrellaExcess Coverage: Off
Pollution: Off
Professional Liability: Off
Cyber Liability: Off
Technology Errors Omissions: Off
Other insert text box here: Off
Other insert text box here_2: Off
Other insert text box here_3: Off
undefined_9:
undefined_10:
undefined_11:
undefined_12:
Version 2 10225:
Bid Bond: Off
Shall be submitted with the proposal response in the form of proposal bond in a sum equal to 5 of the cost proposal:
2025-12-17T16:28:17-0500
GonzalezGreily
Employers Liability: On
Worker's Compensation: On
Performance and Payment: Off
9: On
10: On
11: On
12: On
13: On
Project Title: 26-8632 Beach Compatible Sand Supply