26 29 21 - Enclosed Switches and Circuit Breakers.docx
DOCX document 29 KB Posted
- Solicitation number
- 36C25621R0127
About this file
This solicitation is for a project to replace refrigerators and freezers at a Veterans Administration medical center. The project requires replacing NFS and pharmacy refrigerators and freezers at the Overton Brooks VA Medical Center located in Shreveport, Louisiana. The procurement will be issued as a 100% set-aside for service-disabled veteran-owned small businesses. The request for proposals is anticipated to be issued on or around June 7th, 2021, with proposals due approximately 30 days later on July 7th. The contract is expected to be awarded within 30 days of receipt of proposals. The performance period for the 180-day contract will begin with the issuance of the notice to proceed. The contractor must provide all labor, materials, tools, equipment, administration and other requirements to complete the scope of work according to the project drawings and specifications. The estimated construction cost is between $500,000 and $1,000,000.
View the file
Other files
Show 40 more
Latest 50 of 72 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 26 29 21
ENCLOSED SWITCHES AND CIRCUIT BREAKERS
PART 1 - GENERAL
1.1 DESCRIPTION
A. This section specifies the furnishing, installation, and connection of fused and unfused disconnect switches (indicated as switches in this section), and separately-enclosed circuit breakers for use in electrical systems rated 600 V and below.
1.2 RELATED WORK
A. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS: Requirements that apply to all sections of Division 26.
B. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES: Low-voltage conductors.
C. Section 26 05 26, GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS: Requirements for personnel safety and to provide a low impedance path for possible ground faults.
D. Section 26 05 33, RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS: Conduits.
1.3 QUALITY ASSURANCE
A. Quality Assurance shall be in accordance with Paragraph, QUALIFICATIONS (PRODUCTS AND SERVICES) in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
1.4 SUBMITTALS
A. Submit in accordance with Paragraph, SUBMITTALS in Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, and the following requirements:
1. Shop Drawings:
a. Submit sufficient information to demonstrate compliance with drawings and specifications.
b. Submit the following data for approval:
1) Electrical ratings, dimensions, mounting details, materials, required clearances, terminations, weight, fuses, circuit breakers, wiring and connection diagrams, accessories, and device nameplate data.
2. Manuals:
a. Submit complete maintenance and operating manuals including technical data sheets, wiring diagrams, and information for ordering fuses, circuit breakers, and replacement parts.
PROJECT 667-21-101 REPLACE NFS & PHARMACY
REFRIGERATORS AND FREEZERS
VETERANS ADMINISTRATION, SHREVEPORT, LA
01-01-17
26 29 21 -
ENCLOSED SWITCHES AND CIRCUIT BREAKERS
1) Include schematic diagrams, with all terminals identified, matching terminal identification in the enclosed switches and circuit breakers.
2) Include information for testing, repair, troubleshooting, assembly, and disassembly.
b. If changes have been made to the maintenance and operating manuals originally submitted, submit updated maintenance and operating manuals two weeks prior to the final inspection.
3. Certifications: Two weeks prior to final inspection, submit the following.
a. Certification by the manufacturer that the enclosed switches and circuit breakers conform to the requirements of the drawings and specifications.
b. Certification by the Contractor that the enclosed switches and circuit breakers have been properly installed, adjusted, and tested.
1.5 APPLICABLE PUBLICATIONS
A. Publications listed below (including amendments, addenda, revisions, supplements, and errata) form a part of this specification to the extent referenced. Publications are referenced in the text by designation only.
B. International Code Council (ICC):
IBC-15..................International Building Code C. National Electrical Manufacturers Association (NEMA): FU l-12.................Low Voltage Cartridge Fuses KS l-13.................Heavy Duty Enclosed and Dead-Front Switches (600 Volts Maximum) D. National Fire Protection Association (NFPA):
70-17...................National Electrical Code (NEC) E. Underwriters Laboratories, Inc. (UL):
98-16...................Enclosed and Dead-Front Switches 248 1-11................Low Voltage Fuses 489-13..................Molded Case Circuit Breakers and Circuit Breaker Enclosures
PART 2 - PRODUCTS
2.1 FUSED SWITCHES RATED 600 AMPERES AND LESS
A. Switches shall be in accordance with NEMA, NEC, UL, as specified, and as shown on the drawings.
B. Shall be NEMA classified General Duty (GD) for 240 V switches, and NEMA classified Heavy Duty (HD) for 480 V switches.
C. Shall be horsepower (HP) rated.
D. Shall have the following features:
1. Switch mechanism shall be the quick-make, quick-break type.
2. Copper blades, visible in the open position.
3. An arc chute for each pole.
4. External operating handle shall indicate open and closed positions, and have lock-open padlocking provisions.
5. Mechanical interlock shall permit opening of the door only when the switch is in the open position, defeatable to permit inspection.
6. Fuse holders for the sizes and types of fuses specified.
7. Solid neutral for each switch being installed in a circuit which includes a neutral conductor.
8. Ground lugs for each ground conductor.
9. Enclosures:
a. Shall be the NEMA types shown on the drawings.
b. Where the types of switch enclosures are not shown, they shall be the NEMA types most suitable for the ambient environmental conditions.
c. Shall be finished with manufacturer’s standard gray baked enamel paint over pretreated steel.
2.2 UNFUSED SWITCHES RATED 600 AMPERES AND LESS
A. Shall be the same as fused switches, but without provisions for fuses.
2.3 MOTOR RATED TOGGLE SWITCHES
A. Type 1, general purpose for single-phase motors rated up to 1 horsepower.
B. Quick-make, quick-break toggle switch with external reset button and thermal overload protection matched to nameplate full-load current of actual protected motor.
2.4 CARTRIDGE FUSES
A. Shall be in accordance with NEMA FU 1.
B. Motor Branch Circuits: Class RK1, time delay.
C. Other Branch Circuits: Class RK1, time delay.
D. Control Circuits: Class CC, time delay.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be in accordance with the NEC, as shown on the drawings, and manufacturer’s instructions.
B. Fused switches shall be furnished complete with fuses. Arrange fuses such that rating information is readable without removing the fuses.
3.2 ACCEPTANCE CHECKS AND TESTS
A. Perform in accordance with the manufacturer's recommendations. In addition, include the following:
1. Visual Inspection and Tests:
a. Compare equipment nameplate data with specifications and approved shop drawings.
b. Inspect physical, electrical, and mechanical condition.
c. Verify tightness of accessible bolted electrical connections by calibrated torque-wrench method.
d. Vacuum-clean enclosure interior. Clean enclosure exterior.
3.3 SPARE PARTS
A. Two weeks prior to the final inspection, furnish one complete set of spare fuses for each fused disconnect switch installed on the project. Deliver the spare fuses to the COR.
END OF SECTION